sermsang power corporation public company limited
play

Sermsang Power Corporation Public Company Limited Results of the Year - PowerPoint PPT Presentation

Sermsang Power Corporation Public Company Limited Results of the Year 2018 7 March 2019 1 Disclaimer The information contained in this presentation is strictly confidential and is provided by Sermsang Power Corporation Public Company Limited


  1. Sermsang Power Corporation Public Company Limited Results of the Year 2018 7 March 2019 1

  2. Disclaimer The information contained in this presentation is strictly confidential and is provided by Sermsang Power Corporation Public Company Limited (“SSP” or the "Company") to you solely for your information. Neither this presentation nor any part hereof may be (i) used or relied upon by any other party or for any other purpose; (ii) copied, photocopied, duplicated or otherwise reproduced in any form or by any means; or (iii) redistributed, passed on or otherwise disseminated, to any other person either in your organization or elsewhere, without the prior written consent of the Company and its respective affiliates or advisors. By attending this presentation, participants agree not to remove this document, or any materials provided in connection herewith, from the conference room where such documents are provided without express consent from the Company and its respective affiliates or advisors. Although care has been taken to ensure that the information in this presentation is accurate, and that the opinions expressed are fair and reasonable, no representations or warranties, express or implied, are made as to, and no reliance should be placed on, the accuracy, fairness or completeness of the information presented or contained in this presentation. The information is subject to change without notice, its accuracy is not guaranteed, has not been independently verified and it may not contain all material information concerning the Company and its subsidiaries. None of the Company nor any of its respective affiliates or advisors nor any of its or their respective members, directors, officers, employees or affiliates assumes any responsibility or liability for, the accuracy or completeness of, or any errors or omissions in, any information contained herein. Accordingly, none of the above nor any other person accepts any liability (in negligence, or otherwise) for any loss arising from or in connection with any use of this presentation or its contents. This presentation is for information purposes only and does not constitute or form part of any offer or invitation by or on behalf of the Company for sale or subscription of or solicitation or invitation of any offer to or recommendation to buy or subscribe for any securities of the Company, nor shall it or any part of it form the basis of or be relied on in connection with any contract, commitment or investment decision in relation thereto (“Securities”) in Thailand, the United States or any other jurisdiction. Any recipient considering a purchase of Securities is hereby reminded that any such purchase should be made solely on the basis of the information contained in a final offering document (which may be different from the information contained in this presentation ) and subject to the selling restrictions set out therein. No public offering of the Securities will be made in the United States or in any other jurisdiction outside of Thailand where such an offering is restricted or prohibited. This presentation should not be construed as legal, tax, investment or other advice. The information contained herein does not take into consideration the investment objectives, financial situation or particular needs of any particular investor, and should not be treated as giving investment advice. In addition, this presentation contains certain financial information and results of operation, and may also contain certain projections, plans, strategies, and objectives of the Company, that are not statements of historical fact which would be treated as forward looking statements that reflect the Company's current views with respect to future events and financial performance. These views are based on a number of estimates and current assumptions which are subject to business, economic and competitive uncertainties and contingencies as well as various risks which are in many cases beyond the control of the Company, and which may change over time and may cause actual events and the Company's future results to be materially different than expected or indicated by such statements. No assurance can be given that future events will occur, that projections will be achieved, or that the Company's assumptions are correct. Such forward‐looking statements are not guarantees of future performance and accordingly, the actual results, financial condition, performance or achievements of the Company may differ materially from those anticipated by the Company in the forward looking statements. The recipient is cautioned not to place undue reliance on these forward looking statements. In providing this presentation, the Company does not undertake to provide any recipient with access to any additional information or to update the information contained in this presentation or to correct any inaccuracies herein which may become apparent. 2

  3. Consolidation Key Highlights • 2018 results shows moderate growth from early stage of project materialization; sale and EBITDA growth of around 25-30%, NI growth 41.8%, and COP growth 5.6%. • Contribution from 2 JP and 1 Thailand solar projects achieved COD during 2018 (Hidaka from Mar-18, Zouen from Aug-18 and WVO from 30 Nov-18) • Revenue contribution of JP solar project: approx. 21% for 2018. • Plant outage shutdown Hidaka project of approx. 3 days and 10 days effect from heavy snow during 4Q18. • November: 3 days, major maintenance. • December: 10 days, heavy snow effect • WVO solar started commercial operation (COD) in Q4-18 (30 Nov-18). • Seasonality effect for 4Q (heavy snow) on Japan solar projects. • SPN’s volume continued to be lower than last year: -3.3% for 2018 (for Q4: +1.0% QoQ, +3.0% YoY) • Khunsight Khundi project (Mongolia): construction completed, still on test run and commissioning (expected to COD within Q1-19 as planned) • SNNP3&4: under construction and expected to sold electricity to IU in Q1-19. • Propose dividend for shareholders approval at 40% COP (+/- 200 MTHB; 0.217 THB/share) 3

  4. Progress Report of Projects under Construction/Development 4

  5. Robust Portfolio Growth from High Quality Pipeline Future Project Pipeline Details Installed Capacity Project Location Status Expected COD (MW) Start Commercial Operation SPN 52.0 Q1 2015 (2 nd February 2015) Start Commercial Operation Hidaka 21.0 Q1 2018 (1 st March 2018) SNNP1 Complete 0.384 Q1 2018 0.998 Q1 2018 SNNP2 Complete Do Home 3.0 Q3 2018 Complete Start Commercial Operation Zouen 8.0 Q4 2018 (1 st August 2018) Start Commercial Operation Solar WVO 5.0 Q4 2018 (30 th November 2018) SNNP 3 & SNNP 4 0.7 Q1 2019 Under Construction 16.4 Q1 2019 Khunsight Kundi Under Construction Binh Nguyen Solar Under Construction 49.6 Q2 2019 Yamaga Under Construction 34.5 2020 5 Leo Under Construction 40.0 2021-2022

  6. Delivery timeline: short-medium timeframe 157.0 MW 107.4 MW 90.4 MW Binh Nguyen Solar 49.6 MW Khunsigh Kundi 16.4 MW 85.4 MW WVO 5 MW 74.4 MW 74.4 MW DoHome 3 MW SNNP3 and SNNP4 0.7 MW SPN 52 MW Zouen 8 MW Hidaka 21 MW SNNP1 and SNNP2 1.4 MW 6

  7. SSP Group Portfolio – Over 200 Equity MWp under Operation and Construction 7

  8. SS Solar WVO 5MW : COD in 30 November 2018 (Q4-18) 8

  9. TGC Khunsight Kundi (Mongolia) 16.4MW: Construction Progress As of Jan-19 New airport - Construction complete - test run and commissioning state 9

  10. TGC Khunsight Kundi (Mongolia) 16.4MW: Construction Progress 10

  11. GSSE Yamaga 34.5MW: Construction Progress As of Jan-19 - Site Preparation - Mounting Work - PV Panel Installation Work 11

  12. GSSE Yamaga 34.5MW: Construction Progress 12

  13. GSSE Construction Progress (Yamaga) As of Jan-19 Yamaga C Project S-curve 100.00% 90.00% 80.00% 70.00% 60.00% 50.00% 40.00% 30.00% Old Plan 20.00% Actual 10.00% Revised Plan 0.00% 13

  14. GSSE Current & Next Progress: Yamaga Current Progress (As of January 2019) Site Preparation : 85.85% Completed Grid-Connection Substation Work : TBD : 2.53% Completed Electrical Work High-Voltage Wiring Work : 0.45% Completed Inverter Installation Work : 0.68% Completed PV Panel Installation Work : 3.63% Completed Panel Wiring Work : 0.10% Completed Monitoring & Security System : TBD Mounting Work : 15.32% Completed Self-Operated Distribution Line Work : 1.09% Completed Material Delivery : 20.06% Completed Next Progress Site Preparation : 88.60% Completed by end of Feb 2019 Electrical Work : 5.18% Completed by end of Feb 2019 : 28.48% Completed by end of Feb 2019 Material Delivery 14

  15. Ashita Power 1 Leo (Ashita 1) 26MW: Construction Progress (Site Preparation) As of Jan-19 15

  16. Ashita Power 1 Leo (Ashita 1) 26MW: Construction Progress (Site Preparation) As of Jan-19 16

  17. Ashita Power 1 Construction Progress (Leo-Ashita 1) As of Jan-19 LEO1 Project S-curve 100.00% 90.00% 80.00% 70.00% 60.00% 50.00% 40.00% 30.00% Plan 20.00% 10.00% Actual 0.00% 17

  18. Ashita Power 1 Current & Next Progress: Leo-Ashita 1 Current Progress (As of January 2019) Site Preparation : 0.60% Completed Grid-Connection Substation Work : TBD : TBD Electrical Work Self-Operated Distribution Line Work : TBD Material Delivery : TBD Next Progress Site Preparation : 2.53% Completed by end of Feb 2019 18

  19. TTQN Binh Nguyen Solar (Vietnam) 49.6 MW: Construction Progress As of Feb-19 19

  20. TTQN Binh Nguyen Solar (Vietnam) 49.6 MW: Construction Progress As of Feb-19 20

  21. TTQN Construction Progress (Binh Nguyen) 21

  22. 2018 4 th th Quarter of 2018 and The Fis iscal Year of 2018 2018 Results 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend