Second Avenue Subway Quarterly Public Workshop October 21, 2015 1 Current Project Status Overall Construction Progress is 87.8% complete as of 10/1/2015. All 10 SAS Contracts have been awarded for Phase 1 5 Construction
2 MTA Capital Construction
- Overall Construction Progress is 87.8% complete as
- f 10/1/2015.
- All 10 SAS Contracts have been awarded for Phase 1
- 5 Construction Contracts Completed:
− Tunnel Boring Machine Tunneling − 86th St Excavation, Utility Relocation, and Road Decking − 96th St Site Work and Heavy Civil − 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14) − 86th St Cavern Mining & Heavy Civil (12/16/14)
Current Project Status
3
Station Renderings
72nd Street Platform Level 86th Street Mezzanine - South
Go to http://www.mta.info/SAS and click on Vision Gallery
96th Street Proposed Art Installation
Artist – Sarah Sze, MTA Arts & Design commissioned work
63rd Street Mezzanine Fare Array
3
4
Q-Line Service and Connections
- The Re-routed Q train will
travel from the new 96th Street Station south through Manhattan and into Brooklyn, terminating at Coney Island.
5 5
Community Information Center
Hours
Monday: 10AM - 6PM Tuesday: 11AM - 7PM Wednesday: 10 AM - 6PM Thursday: 11AM - 7PM Friday: 10AM - 6PM Saturday: 11AM - 3PM* Sunday: Closed Closed most public holidays *Open the second Saturday
- f every month.
- 14,100 visitors to date
- 85 presentations and events conducted, including 48 presentations to
school groups with over 1,600 students attending
- New exhibit coming next month
Opened July 2013
6
Second Avenue Subway Simulator Tournament
- First and second place winners from three age groups received $100
and $50 gift certificates
- Marianne Vera Salon, Le Tarte Flambée, The Penrose, Eneslow
Shoes, Beach Café, Grace’s Marketplace supplied the gift certificates
- Tournament covered by News 4 New York and Fox 5 News
7
Community Tours
86th Street Cavern Tour
October 11, 2014
- We have hosted 55 tours with 1,700 participants to date
- A marriage proposal took place in the 86th Street cavern
- Make sure you are on the SAS email list: outreach@2Avesubway.com
8 MTA Capital Construction
96th Street Station Area
9 MTA Capital Construction
Ancillary Building #2 Construction and Rendering
SW corner 97th Street and Second Avenue
10
Entrance 1 Escalator and Stair Installation
SW corner 94th Street and Second Avenue 9/4/2015
11 11
9/15/2015
Entrance 2 Escalators - NE corner of 94th Street and Second Avenue
12
??? 2015
Street utility work - west side of Second Avenue
Between 93rd and 92nd Streets looking south
13 13
Street restored after work moved to west side of Second Avenue
East side of Second Avenue at 97th Street looking north
14 MTA Capital Construction
86th Street Station Area
15 15 MTA Capital Construction
Installation of electrical, HVAC ducts and service carries continues
16 16
Escalator Installation – Platform to Mezzanine
17 MTA Capital Construction 17
Entrances at Yorkshire Building at 86th Street
looking East Elevator Construction
18 MTA Capital Construction
72nd Street Station Area
19 19 MTA Capital Construction
Ancillary 2/Entrance 2 at northwest corner
- f 72nd Street and Second Ave –
construction and rendering
20
72nd Street Station Area
20
Main Cavern – Mezzanine level service carrier frame installation
21 21
72nd Street Station Area
Main Cavern (platform level) – Granite floor tile installation
22 22
72nd Street Station Area
Entrance 1 (northeast corner of 69th Street and Second Avenue) incline viewed from main cavern
23 MTA Capital Construction
Lexington Ave / 63rd Street Station Area
24 MTA Capital Construction 24
North side of 63rd Street between Lexington and Park Avenue (in front of 123 and 125 E. 63rd Street) South side of 63rd Street between Lexington and Park Avenue (between 128 E. to 116 E. 63rd Street)
63rd Street Station Area
25 MTA Capital Construction
Entrance – Northwest corner of 63rd Street and Third Avenue – and rendering of adjoining plaza
63rd Street Station Area
26 MTA Capital Construction 26
Escalator installation at Entrance 1 – Southeast Corner of 63rd Street and Third Avenue
63rd Street Station Area
27 27
Station rehabilitation includes new track slide wall
Lower level platform – Q track June 2015
28 28
CONTRACT 3: 63rd Street Station
29
Second Avenue Subway