Scottish and Southern Energy Power Distribution Submarine - - PowerPoint PPT Presentation
Scottish and Southern Energy Power Distribution Submarine - - PowerPoint PPT Presentation
Scottish and Southern Energy Power Distribution Submarine electricity cables consultation Open door events were held: 9 th September 2015 Stornoway Oban 15 th September 2015 16 th September 2015 Campbeltown 28 th September 2015 Aberdeen 29 th
Open door events were held:
Stornoway 9th September 2015 Oban 15th September 2015 Campbeltown 16th September 2015 Aberdeen 28th September 2015 Kirkwall 29th September 2015 Lerwick 1st October 2015
Content
1. Background 2. What's changed? 3. Key stakeholders 4. Why are we consulting? 5. What's happened so far & project timeline 6. Installation methods 7. The Cost Benefit Analysis (CBA) method 8. Impact categories 9. The consultation
- 1. Background
- Fifty-nine Scottish islands are currently connected to the electricity
network that serves mainland Great Britain by the Scottish Hydro Electric Power Distribution network.
- They are connected by submarine electricity cables that supply
electricity to homes and businesses on the islands.
- The combined length of these submarine electricity cables is 454km –
with some sections having been in place for over 50 years.
- The cost of supplying electricity to the Scottish islands is supported by
electricity consumers across the north of Scotland as part of their energy bills.
- 2. What's changed?
A statutory National Marine Plan for all activities in Scottish waters out to 200 nautical miles was adopted and published in March 2015.
- Provides a single planning framework which will support the
sustainable use of the marine resource
- Includes policies on how submarine electricity cables are laid and
protected on the seabed to achieve seabed user co-existence.
- At present current installation practice is to lay cables directly on
seabed
- Changes to this practice and protecting cables will require significant
increases in capital expenditure.
- 3. Who is involved?
Ofgem
- SHEPD are regulated by Ofgem who are responsible for protecting the
interests of consumers and ensuring they have access to an affordable, secure and sustainable energy system.
- Ofgem set the amount of revenue that SHEPD can receive, from
consumers through their bill, in order to maintain the network.
- Major investment decisions, such as changing the way we lay
submarine cables, require approval from Ofgem
- Our engineering activities within the marine environment are regulated
by Marine Scotland.
- 3. Who is involved?
Marine Scotland
- SHEPD engineering activities within the marine environment are
regulated by Marine Scotland
- Marine Scotland is responsible for managing Scotland’s seas for
prosperity and environmental sustainability.
- It achieves this through its marine planning, licensing and other
functions.
- Marine Scotland produced Scotland’s National Marine Plan.
- 4. Why we are consulting
We are developing a cost benefit analysis model which will help us demonstrate (to ourselves, our regulators and all users of the marine environment) that the methods we propose to use for laying and protecting cables around the coast of Scotland:
- Satisfies current legislation
- Employs the most sustainable method when considering
economic, safety and wider social and environmental impacts We want to give our stakeholders a chance to shape the impacts and evidence we consider and our methodology
- 5. What’s happened so far?
July 2013
- SHEPD submit their business plan to Ofgem for the period April 2015-
March 2023
Nov 2014
- Ofgem and SHEPD agree the amount of revenue SHEPD can receive, from
customers through their electricity bills, in order to maintain the network
March 2015
- Scotland’s National Marine Plan adopted and laid before parliament
Sept – Oct 15
- Consultation live
- 5. Project timeline
- 6. Submarine cables – installation methods
Current practice
- Surface lay
Protection methods
- Ploughing
- Jetting
- Mass Flow Excavation (MFE)
- Mattressing
- Rock dumping
Source: subseaworldnews.com
- 6. Surface lay
- The is the current method of submarine
cable installation used by SHEPD
- This method involves laying the cable
directly on the seabed, above the surface, and therefore exposed to the surrounding elements
- At present 110 out of the 111 submarine
cables that SHEPD owns have been installed and are maintained using this method.
- 6. Ploughing
- Ploughshare reaches down to
the seabed and cuts a narrow channel
- The cable can be guided down
directly behind or guided through a hollow inside the plough
- Results dependent upon
suitable sediment coverage
Source: subseacablesuk.org.uk
- 6. Jetting
- Jetting tools consist of a row of water
nozzles, which are pushed down into the seabed
- Jetting relies on a high pressure water
flow from nozzles, which fluidises the seabed
- As the jetting tool is moved along the
cable, the cable sinks down into the fluidised seabed, which re-solidifies with settlement
Source: hudsonproject.com
- 6. Mass Flow Excavation (MFE)
- Burial is achieved by passing over the
cable route after installation and clearing sediment away from below the cable allowing the cable to bury naturally utilising the same sediment to back fill
- As the sediment is liquefied, the cable is
buried during the initial pass – this is an established industry method of burial.
Source: subseaworldnews.com
- 6. Mattressing
- Concrete mattress placement is
mainly used for cable protection at localised areas of cable movement where burial is not achievable
- Each mattresses weight is
significant enough as not to be move by tidal flow
- Edges are graded at an angle to
reduce the impact upon fishing gear and/or anchors snagging
Source: offshorewind.biz
- 6. Rock dumping
- Rock dumping is used to protect the
cable from third party hazards and not to protect marine users from the cable
- Rock dumping creates an unnatural
seabed feature that not only increases the surface area of the cable, and may reduce water depths by a few meters nearer the shore
- This method increases the surface area
and which maybe an additional hazard to mariners
- Due to the nature of rock dumping it
cannot necessarily be graded as well as prefabricated concrete mattresses
Source: offshorewind.biz
Impacts included into CBA model
Stakeholder Engagement
- To estimate the costs and benefits associated with different installation methods and to
compare these with current practices for installing submarine cables
- The four cost and benefit impact categories that will be considered are health and
safety, socio-economic, environmental and engineering and wider economic
- We will, with your help, calculate the value of each of the impacts in monetary terms, so
they can be compared on an equivalent basis
- The installation method with the greatest overall benefits (or least drawbacks) will be
identified as best value
- We define best value as the method(s) of installation which satisfy all current legislation
and provide a sustainable balance of economic, safety, environmental and wider social and economic impacts
- 7. Purpose of the Cost Benefit Analysis Assessment
CBA Development Process
- 8. Health and safety impact pathway
Activity
- Risks of snagging on surface laid cables and rock-protected cables
Impact
- Damage to fishing nets, anchors, vessels, and machinery
Receptors
- Fishery operators
Effects
- Loss of catch in entangled nets
- Damage to machinery or vessels
- Down time during which fishing cannot occur
Valuation
- Market value of lost catch
- Damage costs to machinery or vessels
- Opportunity cost of loss of fishing time
- No. of
power
- utages
from faults Cost of
- utages
Total value (£)
- No. of
snagging events Cost of snagging events Total value (£) Volume of GHG emissions Cost of GHG emissions Total value (£) Type of cable installation Cost of cable installation Total value (£)
Total (net) cost of installation method 1
- 8. Total installation method impact valuation
Health and safety Socio-economic Environmental Economic & Engineering
- 8. Survey Data
Surveying work has commenced on 8 cable routes:
- Harris - Scalpay
- Kintyre - Gigha
- Mainland Orkney - Shapinsay
- Mossbank - Yell
- Shapinsay - Sronsay
- Westray - Rousay
- Yell – Unst (1)
- Yell – Unst (2)
Planned completion of survey work is February 2016
- 8. Survey Data
Impacts included into CBA model
- 800
- 600
- 400
- 200
200 400 600 Costs Benefits Costs Benefits Costs Benefits Baseline Installation method 1 Installation method 2 £'000
Costs and benefits of different submarine cable installation techniques
Health and safety Socio-economic Environmental Engineering & wider economic
- 8. Output of Cost Benefit Assessment
- 9. Getting involved
We are seeking views on:
- The cable installation methods we are considering
- The potential benefits and costs of cable installation
methods
- If we have captured the impacts associated with
different cable installation methods or if there are
- thers we should consider
- If there is any pre-existing data which would help
demonstrate the impact of a cable installation method Consultation will close on 13 October 2015.
- 9. Overview of consultation
Consultation paper Stakeholder survey Consultation website
- 9. Contact us