SCE-Proposed QF PPA for Firm Power Contracts (Qualifying Facilities - - PowerPoint PPT Presentation

sce proposed qf ppa for firm power contracts
SMART_READER_LITE
LIVE PREVIEW

SCE-Proposed QF PPA for Firm Power Contracts (Qualifying Facilities - - PowerPoint PPT Presentation

SCE-Proposed QF PPA for Firm Power Contracts (Qualifying Facilities with Expiring Contracts) CPUC Workshop November 15, 2007 Introduction This presentation provides a summary level overview of key contract attributes contained in SCEs


slide-1
SLIDE 1

SCE-Proposed QF PPA for Firm Power Contracts

(Qualifying Facilities with Expiring Contracts)

CPUC Workshop November 15, 2007

slide-2
SLIDE 2

Page: 1

Introduction

This presentation provides a summary level

  • verview of key contract attributes contained in

SCE’s proposed Standard Offer PPA for QFs with expiring contracts SCE welcomes feedback from workshop participants on these key terms Terms for “as available” and new QFs will build from these terms and key attributes

slide-3
SLIDE 3

Page: 2

Proposed QF PPA Structures

Term: 1-10 years Capacity Pmt: $91.97/kW-yr Energy Pmt: MIF on all metered energy Performance Requirements: 95% / 90% Capacity Penalties: Applicable Compliance with CAISO Tariff Term: 1-5 years Capacity Pmt: $32.53/kW-yr Energy Pmt: MIF on all metered energy Performance Requirements: None Capacity Penalties: Not Applicable Compliance with CAISO Tariff Above, plus: Development-Period Security Development-Period Milestone Info Operating-Period Security Above, plus: Development-Period Security Development-Period Milestone Info Operating-Period Security

FIRM AS AVAILABLE EXISTING NEW

slide-4
SLIDE 4

Page: 3

KRCC contract is used as the starting point for the following reasons:

Contract is a single, stand-alone PPA appropriate for 1-to-10 year deal structures

contemplated in D.07-09-040

Contract contains commercially proven & contemporary terms Formed as an arms-length transaction Approved by the CPUC

Certain revisions have been applied to the KRCC contract:

Revised as well as added new provisions to be compliant with

D.07- 09-040

Alterations applied to remove non-applicable technology and commercial

specifications (e.g., removal of dispatchability-related provisions)

Exploring impact of AB 1613 and will incorporate provisions as appropriate This presentation includes some contract attributes not included in submission of

IOU draft contract

Background

slide-5
SLIDE 5

Page: 4

Product & Commercial Terms/Structure

Product (exclusively dedicated to Utility)

Electric energy net of station use and site host load Capacity attributes (Resource Adequacy) Green & other environmental attributes

Commercial Terms/Structure

Conditions precedent prior to term start date Monthly payments to seller (as per D.07-09-040)

Energy, Capacity and VOM prices

Performance requirements Operational/scheduling requirements Utility as scheduling coordinator (preferred) Termination provisions Legal and financial provisions

slide-6
SLIDE 6

Page: 5

Conditions Precedent

FERC certification of QF status obtained and maintained Grid connection established and grid connection agreements executed CAISO operational agreements (PGA, MSA, etc.) executed ISO approved metering installed Scheduling coordinator assigned Capacity testing completed Systems configuration for telemetry link, forecast reporting, and scheduling completed

slide-7
SLIDE 7

Page: 6

Monthly Payments to Seller

TOD Energy Payment

Function of: Metered energy Gas Index CPUC-approved heat rate CPUC-approved energy payment allocation factors Seller receives payments for all metered energy (including MWs in

excess of final net contract capacity)

TOD Capacity Payment

Function of: CPUC-approved capacity price ($91.97/kW-year as per D.07-09-040) CPUC-approved capacity payment allocation factors Performance requirements apply (see next slide) Seller receives capacity credit at net contract capacity (if delivered at

net contract capacity or above) for metered energy delivered during each settlement interval – no credit for settlement interval where metered energy is below net contract capacity

Variable Operations & Maintenance Payment (as per D.07-09-040)

slide-8
SLIDE 8

Page: 7

Performance Requirements

In compliance with D.07-09-040, capacity payment penalty for failure to deliver 95% of the net contract capacity during on-peak months and 90% power during

  • ff-peak months

Monthly capacity payment penalty evaluated per TOD period Capacity payment penalty exceptions for:

Scheduled outages (limitations apply) CAISO or SCE curtailment

No capacity payment penalty exceptions for:

Outages due to force majeure Forced outages

slide-9
SLIDE 9

Page: 8

Operational Requirements

Initial Demonstration Testing

For final net contract capacity Resource adequacy requirements CAISO resource parameters (PMAX, PMIN)

Annual Demonstration Testing

Resource adequacy requirements CAISO resource parameters (PMAX, PMIN)

Daily Forecast Submittal

30-day rolling forecast Updated as appropriate before operating hour for accurate

energy schedule submittal

QF financially responsible for continued & significant

discrepancy between forecast and actual generation

slide-10
SLIDE 10

Page: 9

Utility as Scheduling Coordinator (SC)

As SC, the Utility shall be responsible for:

Submitting bids and schedules to CAISO Reporting outages and unit status to the CAISO All settlement functions with the CAISO CAISO costs and charges, unless costs or charges are due to actions

  • r inactions of seller

Operations Training

Day-to-day ops (e.g., forecast & schedule submittal, derate reporting) MRTU basics PGA, MSA assistance

Commercially reasonable fees for SC services

Start-up fee (training, registration, systems configuration) Monthly fee (volumetric and flat payment options considered)

slide-11
SLIDE 11

Page: 10

Utility as SC (continued)

Scheduling and Delivery Deviation Charges

SDD charges shall be in lieu of assessing all generator-specific

CAISO charges to Seller

“SDD Charge”

Assessed to seller if metered energy is less than schedule (3%

tolerance band)

Calculated as deviated quantity times CAISO real-time price

SDD Administrative Charge

Assessed to seller if metered energy is less than or greater than

Schedule (±3% tolerance band)

Calculated as deviated quantity times GMC rate

SDD charges limited to CAISO settlement interval following

receipt of QF’s derate notification

slide-12
SLIDE 12

Page: 11

Termination Provisions

Rights of Non-Defaulting Party

Designation of termination date Ability to suspend performance Calculation of termination payment

Termination Payment

Calculated as gains minus losses minus costs Traditional two way termination payment calculation

Right to terminate permissible if QF is selected pursuant to native utility RFO solicitation

slide-13
SLIDE 13

Page: 12

Legal and Financial Provisions

Reps and Warranties

Appropriate to D.07-09-040 deal structure

Assignment & Indemnification Mandatory Dispute Resolution

Informal Mediation Binding Arbitration

Seller obligation to provide necessary financial statements

Fin 46 compliance

slide-14
SLIDE 14

Questions/Discussion

Forward feedback to: Mike Marelli Manager of Origination and Analysis Southern California Edison mike.marelli@sce.com 626-302-3408