SCE 2018 GRC – Deep Dive on SCE T estimony on Poles
November 2, 2016
1
SCE 2018 GRC Deep Dive on SCE T estimony on Poles November 2, - - PowerPoint PPT Presentation
SCE 2018 GRC Deep Dive on SCE T estimony on Poles November 2, 2016 1 Summary Pole inspection, assessment, maintenance, and replacement continue to be a major focus for SCE given: Their impact on public and worker safety Their
1
Their impact on public and worker safety Their essential role in service reliability for customers The amount of resources needed to maintain the asset base while meeting compliance The operational complexities associated with
Assets distributed across the territory with regional environmental impacts Joint ownership
Inspection criteria and schedule Replacement standards Technology improvements Risk analysis using probabilistic methods
2
3
– Beginning in 1998, required all poles over 15 years old be intrusively inspected within 10 years, and then at least once every 20 years – SCE completed initial inspections of all poles in 2007 – Poles requiring replacement are replaced through SCE’s Deteriorated Pole Replacement Program
– Sets pole design safety factor of 4.0 for new grade A wood poles – Sets pole design safety factor minimum of 2.67 at 6 or 8 lbs for in-service grade A wood poles – Requires a ‘pole loading’ calculation to evaluate safety factor – Requires retention of pole loading records for life of the pole (added to G.O. 95 by D.12-01-032) – GO 95 safety factor compliance drives SCE’s Pole Loading Program
4
5
current Cycle (2007-current)
6
– What:
– Why:
– Current status:
inspections and compliance poles
7
Inspection Year Aggregate Failure Rate (Distribution and Transmission)
2013‐2015 8% 2008‐2012 7% 2001‐2007 17%
8
*Not to exceed time frames, poles may be replaced earlier due to operational circumstances, environmental clearances, or opportunities to reduce customer impact.
Determinants of Priority SCE‐Driven Remediation Timeframe* Remaining Section Modulus (RSM), other visible damage, location, size, etc. 72 hrs / 45 days 1 Year 2 Years 3 Years
better alignment with peer companies
assess impact of changes and identify new criterion
require replacement
versus replace poles
9
Utility RSM pass with no action RSM failure & become restoration candidate RSM failure & become replacement candidate SCE 100% N/A N/A 1 70% 69.90% 40% 2 100% N/A N/A 3 >67% <67% <67% 4 66% 66% 66% 5 100% 99% 99% 6 80% 67‐80% 67% 7 71% 41‐70% 70% 8 67% 66% 50% 9 66% 66% 66% 10 >67% <67% <67% 11 >67% <33% <33% 12 67% 14‐67% 0‐13% 13 >88% 34‐87% <33% 14 >81% 34‐80% <33%
10
Dates Remediation Anticipated Failure Rates Transmission Distribution
2015 Reject Rate (Before SPEC Change) Pole Replacement 12.50% 7.63% Estimated 2016 Reject Rate (After SPEC Change) Restoration 2% 2% Pole Replacement 4.23% 3.75%
11
2013 2014 2015 Total, 2013- 15 2015 GRC Forecast Replacements PLP 3,000 25,000 28,000 Det Pole 7,500 7,600 8,102 23,202 Total, All Programs 7,500 10,600 33,102 51,202 Recorded Replacements PLP
10,690 10,989 Det Pole 12,251 14,065 23,198 49,514 Total, All Programs 12,251 14,364 33,888 60,503 Forecast vs. Recorded Variance PLP
(14,310) (17,011) Det Pole 4,751 6,465 15,096 26,312 Total Variance 4,751 3,764 786 9,301
12
Process Overview:
– Experienced assessor accesses pole to gather information for pole loading calculation:
– Desktop analysis completed to integrate data from the field assessment, design standards, and other data associated with the pole – Measurements are entered into the pole loading software (SPIDACalc), appropriate wind loading case is selected, and safety factors are calculated – Poles that are not compliant with G.O. 95 safety factors or SCE internal standards are identified and the appropriate remediation is designed and implemented. – Remediation requires replacement or repair of the pole, including removal and reinstallation of all attachments. – SCE began systematic assessment, evaluation, and remediation of poles in 2014
13
14
grouped and work order number is assigned
Joint Pole Agreements initiated, environmental, rights checks/railroad request submitted
construction based on all constraints being cleared
in scheduling process for final execution
useful”
15
*Not to exceed time frames, poles may be replaced earlier due to operational circumstances, environmental clearances, or opportunities to reduce customer impact.
Determinants of Priority SCE‐Driven Remediation Timeframe* Safety factor, location in high fire zones, presence of internal / external damage, etc. 72 hrs / 45 days 150 days 1 year 59 months
– SCE implemented new wind ratings across the service territory based on REAX wind study and historical information
12 psf and 18 psf areas
– Enhancements to SpidaCalc Pole Loading Software
various loads. (See workpaper pages 120-122)
– 2018 GRC forecast reflects the changes
16
17
Mid‐2014, review of field personnel feedback indicated concerns about size
In Q4 of 2014, Engineering and Pole Program Management undertook verification of the pole loading methodology and root cause analyses Subsequent technical evaluation determined a more robust ‘pole loading’ calculation method would more accurately calculate safety factors, and developed an updated methodology During the remainder of 2015 and in 2016, SCE undertook the following:
methodology
that were previously identified for replacement
18
19
Transmission “combo” pole Transmission
Distribution
Transmission portion Distribution underbuild
20
21
Row # Unit Cost Component 2012 Unit Cost (2015 $) 2015 Recorded (2015 $) Variance in 2015 $ Variance as % of 2012 total unit cost Summary of Drivers (See following testimony for details) 1 Contractor $ 10,157 $ 11,970 $ 1,813 9% Increased work volume required increased utilization of contractors and premium time 2 Labor $ 2,837 $ 3,077 $ 240 1% 3 Material $ 4,000 $ 4,090 $ 90 0% Larger poles required by updated pole loading methodology 4 Other $ 1,008 $ 792 $ (216)
5 Overhead $ 2,828 $ 2,137 $ (692)
Capital spending increased while total overhead remained constant resulting in a lower allocation to pole spend 6 Totals $ 20,830 $ 22,065 $ 1,236 6% 7 Corporate Overhead $ 3,324 $ 3,726 $ 402
22
1. SCE will provide a review of its efforts on recovery of costs from other companies that either jointly own or rent space on poles that must be replaced or repaired. 2. SCE will provide information on the number of jointly owned poles, the number of pole renters, and describe the arrangements for cost sharing with other parties. 3. SCE will provide additional analysis on options to remediate overloaded poles in ways other than repair or replace, and will specifically address the issues of removing attachments, strengthening poles, and increasing the recovery of costs from pole users. 4. SCE will address unauthorized attachments by providing quantitative information and describing their efforts to minimize their impact. 5. If SCE believes a Commission proceeding is needed to address issues raised by joint ownership and renters, SCE need not wait for its next GRC. SCE will address (1)-(4) in detail in the following slides; (5) is addressed in testimony
23
24
(Figure V-8)
25
– “Top-down” approach relied on total capital credit dollars recorded – Divided total joint pole capital credit dollars recorded by poles replaced in all programs and activities – Average for 2008-2012 was $840 per pole – 2015 total forecast was $34m (in 2015 $)
– “Bottoms-up” approach focuses on joint pole billing data – 2015 programmatic pole replacement credits resulted in $2,216 per pole replacement – 2018 total forecast is $57m (in 2015 $) – Total forecast based on
26
SCE Pole Occupancy and Ownership (Table V‐26) Ownership Joint Sole Total Renters Yes 11% 8% 19% No 52% 29% 81% Total 63% 37% 100%
27
28
Steel Stub Installs & Expenditures 2017 – 2020 (Tables III – 12 and III – 13) 2017 2018 2019 2020 Count 720 1,608 2,472 2,547 Total Cost (Constant 2015 $000) $ 1,698 $ 3,771 $ 5,821 $ 5,983
29
30
31
32