Sarpy County Wastewater Project Summary financial and commercial - - PowerPoint PPT Presentation
Sarpy County Wastewater Project Summary financial and commercial - - PowerPoint PPT Presentation
Sarpy County Wastewater Project Summary financial and commercial analysis January 2019 Underpinning financial and commercial structure Service users Payments A concession type structure appears to County Cities offer the most appropriate
Page 2
Underpinning financial and commercial structure
Traditional Delivery DBFOM P3
Agency pays contractor on a milestone basis for construction phase Agency pays pre-agreed monthly payment over the life of the contract Separate contracts for design and construction with Agency holding interface risk P3 Developer delivers fixed price / date certain construction and holds interface risks Agency performs itself or contracts out to 3rd party Delivered by P3 developer, potentially through subcontract supported by guarantees Municipal debt Combination of public/private debt and private equity
O&M Design & Construction Financing Payment
HART/City P3 Developer O&M Provider Debt and Equity Providers
Debt Service and Equity Return Funding
DB Contractor
Construction Progress Payments Payments Operating Payments
County Agency Cities Service users
Payments P3 agreement
A concession type structure appears to
- ffer the most appropriate balance of
lower transaction costs, risk pricing and competition for subsequent phases’ Capexand (potentially)O&M.
Page 3
Summary
- Est. required revenue
Profile
- Est. revenue from users
- Est. Agency contribution
- =
A B C A B C
- A ‘required revenue’ profile was developed based on the capital and O&M assumptions provided by HDR. The projected $240 million in
capital costs in 2018$’s ($475 million in cash terms) was used to develop a financing structure using debt and equity. The annual required revenue profile was developed on a basis consistent with the required return under a DBFOM P3 commercial structure.
- Omaha+2%: Assumes a rate comparable to Omaha’s in 2015
(~$50) and grows at of inflation (3%) plus 2%, which remains below Omaha’s projected rate profile in the near future
- Omaha+: Assumes a rate comparable to Omaha’s in 2015 (~$50)
and grows at inflation (3%)
- The project is financially viable in the medium to long term, but analysis suggests that revenue from rate payers will not
cover the required revenue for the first 7-8 years of Phase 1A. The cumulative shortfall is estimated to be between $12.5 million and $18.5 million, where the Agency is likely to be required to pay the P3 Developer more than is earned from system users.
Avg.Monthly Bill (7,500 Gallons) 2015 2019 2024 Sarpy (O+2%) $49.37 $60.01 $76.59 Omaha $50.28 $66.23 $85.54
Page 4
Estimate of required vs user revenues
- 10,000
20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 2042 2044 2046 2048 2050 2052 2054 2056 2058 2060 2062 2064 2066 2068 2070 2072 2074 O&M (Fixed) O&M (Variable) Debt Service & Equity Return Required Revenue Projected Revenue (Omaha +) Projected Revenue (Omaha +2%) ($000)
B
P1A Open P1B Open P2 Open P3 Open
Capacity Met
A
For the user growth profile underpinning the analysis, increases in user rates of approximately 5% per year until the early 2040’s are required to create an economicallyviable system
Page 5
- 2,000
4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Omaha+ Omaha+ 2%
Estimated shortfall between required and user revenues
P1A Open P1B Open P2 Open P3 Open
Capacity Met
($000)
C
Omaha+2% case requires $18.5 million in total support in the early years (approximately $2.3 million/year).
Estimated shortfalls in revenue occur during the majority of Phase 1A, and thereafter in the years immediately following Phase 2 becoming
- perational
Page 6
C
Estimated cash balances and impact of demand risk
(40,000) (20,000)
- 20,000
40,000 60,000 80,000 100,000 120,000 140,000 160,000 Omaha +2% Omaha +2% (10% Decrease)
P1A Open P1B Open P2 Open
($000)
Estimated shortfalls in revenue translate into cash deficits during Phase 1A. The project becomes cumulative cash positive by the time Phase1B opens, and remainspositive thereafter providing user growth and rate increasesare as projected.
Page 7
- 500
1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 Omaha + 2% (P1A SRF) Omaha + 2% Total Shortfall ~ $18.5 million over 8 years ~ $12.5 million over 7 years
A
Other Considerations: SRF Funding’s Impact on Early Year Shortfalls
($000)
P1A Open
The analysis below shows the potential to reduce estimated required revenue shortfalls by approximately $6m connected to the financing
- f Phase1A. The analysisassumesthat the loan is signed in [2021], and repaymentcommencesin [2024].
Notes: Analysis assumes SRF loan signed in 2021 for Phase 1A with repayment commencing in 2024. Financing of ROW and other costs incurred prior to 2021 excluded from the analysis.