Public Information Meeting
September 7, 2017
Route 28 Corridor Feasibility Study
.
Route 28 Corridor Feasibility Study . Public Information Meeting - - PowerPoint PPT Presentation
September 7, 2017 Route 28 Corridor Feasibility Study . Public Information Meeting Project Team and Study Committees Route 28 Corridor Feasibility Study Agency Involvement The study is fully funded by the Northern Virginia Transportation
September 7, 2017
.
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Steve Burke
City of Manassas Co-Project Manager
Randy Boice
JMT Project Manager
Brian Curtis
JMT Deputy Project Manager
Rodney Hayzlett
JMT Senior Advisor
Rick Canizales
Prince William County Co-Project Manager Route 28 Corridor Feasibility Study
Sujith Racha
JMT Senior Traffic Engineer
Ian Frost
JMT Senior Environmental Lead
Route 28 Corridor Feasibility Study
Prince William County City of Manassas City of Manassas Park Fairfax County Northern Virginia Transportation Authority (NVTA) Virginia Department of Transportation (VDOT) Virginia Railway Express (VRE) Potomac and Rappahannock Transportation Commission (PRTC) Bull Run Regional Park Virginia Department of Rail and Public Transportation (DRPT) Federal Highway Administration (FHWA) Prince William County Service Authority
Route 28 Corridor Feasibility Study
Senator George Barker Virginia General Assembly Senator Richard Black Virginia General Assembly Senator Jeremy McPike Virginia General Assembly Delegate Tim Hugo Virginia General Assembly Delegate Randy Minchew Virginia General Assembly Delegate Bob Marshall Virginia General Assembly Delegate Jackson Miller Virginia General Assembly Chairman Corey Stewart Prince William County Supervisor Martin Nohe Prince William County Mayor Hal Parrish City of Manassas Council Member Pamela Sebesky City of Manassas Mayor Jeanette Rishell City of Manassas Park Councilman Preston Banks City of Manassas Park Chairman Sharon Bulova Fairfax County Supervisor Kathy Smith Fairfax County - Sully District Supervisor Pat Herrity Fairfax County – Springfield District Chris Price Prince William County Monica Backmon NVTA Helen Cuervo VDOT Renee Hamilton VDOT Maria Sinner VDOT Todd Horsley DRPT Scott Kasprowicz CTB Mary Hughes Hynes CTB Gary Garczynski CTB Chief Executive Officer Doug Allen VRE Paul Gilbert Northern Virginia Regional Parks Authority
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Manassas)
Compton Rd)
Modes of Travel
Consensus
Environmental Impacts
Existing Conditions Impacts
Route 28 Operations
Key Objectives Summary
Route 28 Corridor Feasibility Study
Step 1: Route 28 Corridor Feasibility Study
goals and objectives
Step 2: Complete National Environmental Policy Act (NEPA) Process.
accordance with FHWA implementing regulations
Step 3: Final Design of the Preferred Alternative Step 4: Construction
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
County line
Route 28 Corridor Feasibility Study
Route 28 Average Daily Traffic (ADT)
2016 21,300 2040 No-Build 29,200
2040 No-Build 60,800
2016 57,300 2040 No-Build 76,200
1.4% Annual Growth Rate
Route 28 Corridor Feasibility Study
* Travel time in the northbound direction remains essentially the same compared to the existing conditions due to the Route 28 widening in Fairfax County mitigating the northbound delays. Southbound delays increase due to no-build condition south of Compton Road. 48 46* 19 23 22 37 27 54
Route 28 Corridor Feasibility Study
either AM or PM peak hour: 2016 - 4 out of 29 – 14% 2040 No-Build - 16 out of 29 – 55%
* Queuing along the corridor causes additional intersections to operate at capacity (LOS E) Queueing
Route 28 Corridor Feasibility Study
Preliminary Alternatives
03 02
Criteria: Meeting study goals objectives Environmental Impacts Property Impacts Traffic Benefits Policy Considerations/ Long Term Solution
Four Advanced for Further Evaluation and Study
Feasible Alternatives Alternatives Evaluation
01 01 01
03 03 04 05
Highest Ranked Alternative
Criteria: Project Cost Project Benefits Environmental Impacts Socioeconomic / Right of Way Impacts
c
01 01 01
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Bull Run
Compton Road crossing (the former Tri-County Parkway alignment)
Avenue and the Fairfax County line
and the Fairfax County Line
length
reversible facility
along the corridor (Not Shown)
Drive)
Drive)
Drive)
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Access Points:
Access Points:
Route 28 Corridor Feasibility Study
between Liberia Avenue and end of Fairfax County widening.
Build Project south of Compton.
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Screening Criteria established to attain study objectives
Manassas)
Compton Rd)
Modes of Travel
Consensus
Environmental Impacts
Existing Conditions Impacts
Route 28 Operations
Key Objectives Summary
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
2017 Planning Level Costs
Construction Cost – using VDOT Project Cost Estimating System (PCES) ROW Costs Utility Costs Environmental Mitigation Costs Contingency – 10% (applied to total) Rounded up to Nearest $5 Million 2040 No-Build N/A Alt 2A 4.25 $240 M Alt 2B 4.0 $190 M Alt 4 3.5 $245 M Alt 9 4.75 $265 M Conceptual Alternative # Alignment Color Length in Miles 2017 Planning Level Costs
Estimated costs subject to change as the project progresses through the project development process and costs are inflated for future construction years.
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Capacity Multimodal Compatibility
Change in 2040 ADT in Historic Downtown Manassas 2040 ADT Served by Alternative + Route 28 Ratio of 2040 ADT to Planning Level Cost Peak Hour Travel Time in 2040 using Alternative Peak Hour Travel Time Savings in 2040 on Route 28
1 2 3 X
Key Objective Attainable 4,5 2,3 1, 2,3 1, 2,3
Manassas)
Compton Rd)
Modes of Travel
Route 28 Corridor Feasibility Study
Bypass Alt Route 28
2 Current Volume
57,200 57,200
2040 No-Build
76,200 76,200
Alt 2A
37,200 59,300 96,500
Alt 2B
37,200 59,400 96,600
Alt 4
2,700 6,200 82,400 82,400
Alt 9
3,400
35,000 51,900 86,900
Change in 2040 ADT on Route 28 (Liberia Ave to Compton Rd)
Key Objectives Attainable 1 1 2
Change in 2040 ADT on route 28 in Historic Downtown Manassas3 2040 ADT Served by Alternative + Route 28 (Liberia Ave to Compton Rd)4 Total Conceptual Alternative # Alignment Color Traffic Benefits (when compared to 2040 No-Build)
Travel Times on Alternative Routes (min)
Route 28 Corridor Feasibility Study
Travel Paths
Alt 2A Alt 2B Alt 4 Alt 9
A B
Alternative # NB AM Peak Hr SB PM Peak Hr Total
2040 No-Build
47 55 102
Alt 2A
20 31 51
Alt 2B
18 31 49
Alt 4
35 43 78
Alt 9
30 36 66
Travel Time Savings on Business Route 28 (min)
Alternative # NB AM Peak Hr SB PM Peak Hr Total
Alt 2A
24 15 39
Alt 2B
24 17 41
Alt 4
12 12 24
Alt 9
20 19 39
Godwin Drive Route 29
Route 28 Corridor Feasibility Study
Environmental Impacts
4f Properties / Historic Sites / Public Recreation Areas / Wildlife or Waterfowl Refuges
Floodway / Floodplains Streams / Wetlands Hazardous Materials Environmental Justice Concern Noise Impacts
7 7
Route 28 Corridor Feasibility Study
7 7 7 7
X
Key Objective Attainable
Improvement Projects with Minimal Environmental Impacts Improvement Projects with Minimal Existing Conditions Impacts
Reduce Congestion (Historical Downtown Manassas) Key Objectives Summary
Route 28 Corridor Feasibility Study
2040 No-Build 0 / 0 / 0
0 / 0
0 / 0
Alt 2A 7.0 / 16.4 / 0
23.4 / 66.7
7370 / 5.4
9
Alt 2B 0.7 / 30.3 / 0
21.2 / 55.7
7050 / 6.2
1
Alt 4 3.9 / 1.1 / 0
5.0 /9.3
2050 / 0.9
50
Alt 9 0.6 / 8.3 / 0
16.9 / 47.8
2030 / 2.8
16
Key Objectives Attainable 3 7 7 7 7
4f Properties: Historic Sites (acres) / Public Recreation Areas / Wildlife or Waterfowl Refuges Floodway (Acres) / Floodplains (Acres) Streams (Linear Feet) / Wetlands (Acres) Hazardous Materials (# Sites) Conceptual Alternative # Alignment Color Environmental Impacts
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Socioeconomic/ROW Impacts
Relocations - Businesses Relocations to Residential / Churches / Schools Conservation Easements
8 8 8 X
Key Objective Attainable
Improvement Projects with Minimal Environmental Impacts Improvement Projects with Minimal Existing Conditions Impacts
Reduce Congestion (Historical Downtown Manassas) Key Objectives Summary
Route 28 Corridor Feasibility Study
2040 No-Build
0 / 0 / 0
Alt 2A 13
112 / 0 /0
Alt 2B
70 / 0 /0
Alt 4 96
5 / 0 / 0
Alt 9 24
51 / 0 / 0
Socioeconomic / Right of Way Impacts
Key Objectives Attainable 3 8 8
Relocations to Businesses (#) Relocations to Residential (#) / Churches (#) / Schools (#) Conceptual Alternative # Alignment Color
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study Rounded up to Nearest $5 Million Ranking* Points Ranking* Points Ranking* Alt 2A $240 M 2 19 pts. 2
4
2.7
Alt 2B $190 M 1 20 pts. 1
2
1.3
Alt 4 $245 M 3 8 pts. 4
1
2.7
Alt 9 $265 M 4 12 pts. 3
3
3.3
* Ranking Best (1) to Worse (4) Highest Ranked Alternative by Technical Committee Conceptual Alternative # Alignment Color 2017 Planning Level Costs Project Benefits Environmental / Socioeconomic / ROW Impacts Average Ranking*
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study
Dates subject to change as the project progresses through the project development process.
Route 28 Corridor Feasibility Study
Route 28 Corridor Feasibility Study