rock island storage building
play

Rock Island Storage Building Board of Commissioners June 26, 2017 - PowerPoint PPT Presentation

Rock Island Storage Building Board of Commissioners June 26, 2017 T ODAY Current Project Status Board Action Requested This Afternoon Approval to Advertise for Bids to construct a new 20,000 square foot storage building 2 P ROBLEM D


  1. Rock Island Storage Building Board of Commissioners June 26, 2017

  2. T ODAY • Current Project Status • Board Action Requested This Afternoon – Approval to Advertise for Bids to construct a new 20,000 square foot storage building 2

  3. P ROBLEM D ESCRIPTION • Covered storage at Rock Island is very limited Using limited space in both powerhouses • • Most existing storage buildings date to 1970 • Inefficient, congested & unsafe 3

  4. P ROBLEM D ESCRIPTION • Storage is needed for the next 15 years and beyond as part of modernization Identified in the Strategic Facilities Plan as critical • 4

  5. S TRATEGIC F ACILITIES G OAL Previously Today • Reactionary • Proactive, long-range plan: – Short-term, just-in-time, – Productivity: Maximum cheap efficiency – Hodge-podge of facilities – Service: Optimum service & customer experience – Barriers to efficiency – Value: cost stability & – Unpredictable costs to predictability maintain & operate – Safety: enhance customer & – Increasingly unsafe employee safety 5

  6. O BJECTIVE Build a climate controlled storage building on the hill • above Powerhouse 2 • Create safer work areas by reducing congestion in both powerhouses • Reduce risk of damage to critical replacement parts Improve the water supply system to meet current • fire codes Consistent with the Strategic Facilities Plan • 6

  7. P ROJECT S CHEDULES • Storage Building – Fall 2017 – Designs Complete – July/August, 2017 – Bid Opening – September, 2017 • Fire Protection - Fall/Winter 2017 – New Sprinklers and Hydrants – Increased Fire Flow Capacity • Existing 50,000 gallon water reservoir • Additional pumps needed to meet flow requirements • Upsized piping to the building • Design will meet the Facilities Plan buildout 7

  8. R EQUESTED A CTION Resolution to Advertise for Bid 17-53 Rock Island Storage Building 8

  9. N EXT S TEPS • September: – Resolution to Award after receiving bids – Resolution Approving Budget Revision – Financial Project RI170009 for Storage Bldg. incl. Fire Prot. Sys • Current Budget = $1,100,000  Based on Just-in-Time philosophy • Estimated Total Project Costs = $6,300,000*  Storage Building = $5,300,000  Fire Protection System = $1,000,000 *In line with Strategic Facilities Plan estimate 9

  10. Q UESTIONS 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend