ROADW AY LI GHTI NG PROGRAM Public W orks Departm ent February 6 , 2 0 1 8
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Future Lighting Needs • Sum m ary
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Future Lighting Needs • Sum m ary
Background County Roads Arterial/ Collec tor, 2 2 % Local, 7 8 % 2 6 0 0 m iles
Background Arterial/ Collector Roads Unlit 4 4 % Lighted 5 6 %
Background Roads Lighted since 2 0 0 0 3 3 0 Miles
Background Benefits Neighborhood Safety • Com m unity Spirit • Accident Reduction •
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Next Steps
Standards • Duke Energy • Orlando Utilities Com m ission ( OUC)
Standards Light Poles • Existing W ood Poles • Concrete Poles • Alum inum Poles
Standards Light Poles • Existing W ood Poles • Concrete Poles • Alum inum Poles
Standards Light Poles • Existing W ood Poles • Concrete Poles • Alum inum Poles
Standards LED Light Fixtures
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Future Lighting Needs • Sum m ary
Current Program 8 5 Miles 2 0 1 4 - 2 0 1 9
Current Program Roadw ay Lighting Evaluation Criteria • Continuity of roadw ay lights • Num ber of night tim e accidents • Crim e rate • Activity centers - bus routes, churches & schools • Speed lim it and traffic volum es
Current Program Status • 3 0 of 8 5 m iles have been lighted • 9 m iles are under construction or pending construction • 4 6 m iles under design or rem aining to be designed
Current Program Challenges • County relies on utility com panies for schedule and costs • Utility com panies com plete the design and construction
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Future Lighting Needs • Sum m ary
Future Lighting Needs • 1 6 6 m iles of unlit county collector and arterial roads – 1 5 5 m iles of 2 lane roads – 1 1 m iles of 4 & 6 lanes • 2 4 additional m iles are planned w ith future CI P w idening projects
Future Lighting Needs
Future Lighting Needs District 1 4 4 Miles Unlit
Future Lighting Needs District 2 5 2 Miles Unlit
Future Lighting Needs District 3 7 Miles Unlit
Future Lighting Needs District 4 1 7 Miles Unlit
Future Lighting Needs District 5 4 3 Miles Unlit
Future Lighting Needs District 6 3 Miles Unlit
Future Lighting Needs Roadw ay Lighting Evaluation Criteria • Continuity of roadw ay lights • Num ber of night tim e accidents • Activity centers, such as, bus routes, churches & schools • Speed lim it and traffic volum es
Future Lighting Needs Next Steps • Review roadw ays and rankings based on criteria • Develop program for 1 6 6 m iles of collector and arterial roads • $ 1 6 M program – $ 2 M per year for 8 years – Average 2 1 m iles per year • $ 1 .7 M Annual Maintenance
Presentation Outline • Background • Standards • Current Roadw ay Lighting Program • Future Lighting Needs • Sum m ary
Sum m ary • 2 0 0 0 -2 0 1 4 – 3 0 3 Miles Lighted • 2 0 1 4 Program – 8 5 Miles • Future Needs - 1 6 6 Miles
ROADW AY LI GHTI NG PROGRAM Public W orks Departm ent February 6 , 2 0 1 8