roadshow tariff application 2020 21
play

Roadshow - Tariff Application 2020/21 Programme Date: 7 August 2019 - PowerPoint PPT Presentation

Roadshow - Tariff Application 2020/21 Programme Date: 7 August 2019 Time: 9h00 12h00 09:00 - 09:15 Opening and Welcome 09:15 - 09:30 CEO's Remarks 09:30 - 10:30 National Port Authority Tariff Application Presentation 10:30 - 10:50 Tea


  1. Roadshow - Tariff Application 2020/21 Programme Date: 7 August 2019 Time: 9h00 – 12h00 09:00 - 09:15 Opening and Welcome 09:15 - 09:30 CEO's Remarks 09:30 - 10:30 National Port Authority Tariff Application Presentation 10:30 - 10:50 Tea Break 10:50 - 11:20 PRSA Presentation 11:20 - 12:00 Questions and Comments 12:00 - 12:30 Closing Remarks and Lunch thereafter Submission of Feedback forms

  2. Tariff Application 2020/21 07 August 2019 Cape Town

  3. Overview • Weighted Efficiency Gains from Operations (WEGO) update • Port Tariff Incentive Program (PTIP) update • Review of the Tariff Methodology • Tariff Application 2020/21 • Capex implementation . • Valuation of Regulatory Asset Base – VoA Methodology and Corporatisation process • Comments due – focus areas • The process going forward

  4. WEGO Update • There was R154 million in the WEGO “kitty” for 2018/19 tariff year. • Unaudited non-verified results show a R131 million benefit to the NPA. • Is it starting to make a difference? • New problems identified - time lag to consider • PCC KPI subcommittee (including NPA) looking at verification of data • 2019/20 KPI’s published by the Regulator

  5. Port Tariff In Incentive Programme (P (PTIP) • Supporting beneficiation, industrialisation, and localisation through port tariff regulation • The process is intended to serve as a mechanism by which beneficiation, in the form of cross- subsidies (which are in “ the interest of the public ”) may be introduced into the port tariff system • Developed in conjunction with the Department of Transport, the Department of Trade and Industry, and the National Ports Authority and was launched in 2017 • Results in an amendment to a tariff line(s) within the tariff book • Relevant documents are available on the Regulator’s website www.portsregulator.org 5

  6. Port Tariff In Incentive Programme • Applications for the next round closes 31 January 2019 • PTIP available in the published Framework that has been handed out • Contact us for more information or email ptip@portsregulator.org

  7. Review of f the Tariff Methodology • Second Multi-year Tariff Methodology coming to an end next year. • Public consultation process to “dove - tail” with tariff process • Call for public comments will be made in September 2019 • First round of comments close: 04 November 2019 • Regulator to publish a draft methodology for comment on 29 November 2019 • Will include further public engagements • Final Methodology due March 2020

  8. Outcome of Regulation thus far… The correct Tariff Methodology allows the Regulator the space to ensure price stability and system sustainability… 230 210 209 8.5% Ave annual growth 206 10.4% Ave annual growth 201 190 186 184 177 5.0% Ave annual growth 170 163 164 155 150 147 139 108 130 130 129 124 105 117 115 112 111 110 107 106 106 102 100 100 100 107 96 90 105 1.6% Ave annual growth 1.5% Ave annual growth 70 10/11 11/12 12/13 13/14 14'15 15/16 16/17 17/18 18/19 19/20 Inflation index Revenue Tariff Index www.portsregulator.org 11

  9. Observ rvations on the Application • Capex Implementation • Implementation of the Valuation of the Regulatory Asset Base (VoRAB) Methodology – The Corporatisation process We will briefly deal with each separately…

  10. Concerns on the Application Capex Implementation • Is the PCC process providing sufficient CAPEX input and implementation oversight? • Stronger tariff incentivization for CAPEX? Methodology review 120% 6000 100% 5000 80% 72,97% 4000 100,00% 82,62% 87,64% 31,12% 59,64% 49,06% 60% 3000 22,85% 33,32% 29,48% 40% 2000 20% 1000 0% 0 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 Applied for CAPEX interim estimate Actual / implemented CAPEX % Spend

  11. Valuation of f Regulatory ry Asset Base • In March 2018, the Regulator published a Methodology for the Valuation of the NPA Regulatory Asset Base (RAB) • Previously the PRSA accepted the Depreciated Optimised Replacement Cost (DORC) method used by the NPA to determine the value of a starting RAB • This gave rise to a steep increase in asset values. • However, at the time, regulatory certainty was required, and in the absence of any alternative valuation methodology, the NPA’s RAB valuation was previously accepted • The Regulator approved the new VoRAB Methodology in 2018 and determined that a “financial capital maintenance” approach will be applied to all future tariff assessments rather than a “physical capital maintenance”.

  12. Valuation of f Regulatory ry Asset Base • After consultation, the Regulator deemed it appropriate (for the 2019/20 tariff application) to amend the specific application of the “FCM” approach on all assets included on the RAB prior to 1990 as well as those capitalised post 1990. • Specifically: historical cost (HC) applied to all assets capitalised pre 1990. • However, the Regulator opted to use a Trended Original Cost (TOC) methodology applied to all assets in its application of the ‘FCM’ principle. • This approach was retained for the 2020/21 tariff year.

  13. Valuation of f Regulatory ry Asset Base: Why Not a Full Im Implementation? • PRSA is because it is aware of the intention of the state, to incorporate the NPA into a wholly owned subsidiary of Transnet in fulfilment of Section 3(2) of the National Ports Act. • As such, the NPA is likely to be assessed on a standalone basis from a credit rating perspective rather than as a division, giving credence to its sustainability concerns. • The Regulator will: • over the 2019/20 financial year, re-assess the impact of the specific approach adopted in the valuation of the RAB in relation to the sustainability concerns expressed by the NPA • consult further with port stakeholders as well as the NPA on the applicability of the historical cost component of the RAB valuation in the context of the implementation of S3(2) of the National Ports Act • assess the actual progress of the implementation of S3(2) of the National Ports Act • finalise the specific approach of RAB valuation within the next multi-year tariff methodology (MYM3) which the Regulator will be conducting in 2019/20. • The Regulator however retains the right to implement the HC approach pending a detailed assessment of all the historical pre- 1990 assets as well as the full impact thereof on the NPA’s financial position in relation to its corporate structure.

  14. From the Application: Table 1 2019/20 % 2020/21 % 2021/22 % 2022/23 % Return on 4570 36.5% 5175 39.4% 5489 35.8% 6223 37.1% Capital Depreciation 2074 16.5% 2331 17.7% 2369 15.5% 2465 14.7% OPEX 6219 50.1% 6149 46.8% 6769 44.1% 7414 44.2% TAX 509 4.1% 555 4.2% 591 3.9% 665 4% WEGO 0 0% 154 1.2% 0 0% 0 0% ClawBack -1419 -11.3% -1219 -9.3% 115 0.8% 0 0% ETIMC 539 4.3% 0 0% 0 0% 0 0% Revenue 12564 100% 13145 100% 15333 100% 16767 100% Allowed Return + Dep 6644 52.9% 7506 57.1% 7858 51.2% 8688 51.8%

  15. The Application: Comments Please focus your comments on the following: • Volume forecast o Cargo and vessel numbers and trends • Inflation expectation • Strategic use of the ETIMC o A facility created for Port users o Regulator utilizes it in case of tariffs in excess of inflation o ..or to support the NPA o Smoothing mechanism

  16. The Application: Comments (c (continued) Tariff Book Amendments • Please note that application includes some changes to wording etc. This may impact you business-we need to hear about it (Annexure E) • WEGO • PTIP • Any cross subsidy allowed (or even just accelerated tariff correction) will see everyone else pay slightly higher – we need to hear your views – including your thoughts on the process • CMTP envisaged opportunities for incentives

  17. Tariff Process • 01 August 2019: Tariff Application received by the Regulator • 02 – 07 August 2019: Stakeholder Engagement Roadshows • 2 August 2019: Durban Garden Court Marine Parade • 5 August 2019: Johannesburg Southern Sun OR Tambo • 6 August 2019: Port Elizabeth Garden Court Kings Beach • 7 August 2019: Cape Town Southern Sun Cape Sun • 16 September 2019: Written Comments due (from stakeholders) • 29 November 2019: Port Regulator Tariff Record of Decision

  18. Q & A

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend