2009 Tariff Structure and Works Schedule
Meeting February 13, 2009
2009 Tariff Structure and Works Schedule Meeting February 13, 2009 - - PowerPoint PPT Presentation
2009 Tariff Structure and Works Schedule Meeting February 13, 2009 Contents New tariff structure Summary of principles Shipper feedback on the new tariff structure Interruptible capacity Engineering works Principles
Meeting February 13, 2009
Ne Network Interconne twork Interconnecti ction
Point Entry Entry Poi Point from nt from an LNG terminal an LNG terminal Transmission Storage Transmission Storage Interface Poi Interface Point Title Transfer Poi Title Transfer Point nt
Sud Sud Nord Nord
Liaison Nord-S Liaison Nord-Sud ud Mid Midi (int (interconnection wit connection with TIGF) IGF) Dunkerque Dunkerque Taisnière Taisnières H s H Taisnière Taisnières B* s B* Obergailbac bergailbach Oltingue Oltingue PITS Sediane PITS Sediane PITS Sediane Littoral PITS Sediane Littoral PITS Saline PITS Saline PITS Sediane B PITS Sediane B PITS Serene Nord PITS Serene Nord Mon Montoir
Fo Fos PEG Sud PEG Sud PEG Nord (H+L) PEG Nord (H+L) PITS Serene S PITS Serene Sud
Sediane
(Ile de France Sud)
Sediane Littoral
(Centre)
Sediane B
(Picardie)
Serene Nord
(Ile de France Nord et Lorraine)
Saline
(Salins Sud)
Saline Multi Serene Sud
(Centre)
Zone Nord Zone Sud Sediane
(Ile de France Sud)
Sediane Littoral
(Centre)
Sediane B
(Picardie)
Serene Nord
(Ile de France Nord et Lorraine)
Saline
(Salins Sud)
Saline Multi Serene Sud
(Centre)
Zone Nord Zone Sud
* Taisnières B = L-gas
Automatic allocation on the basis of the storage capacity (firm + conditional) allocated by Storengy Any capacity allocated (entry and exit) is partly firm, party interruptible, proportionally to total marketable firm and interruptible capacity Exit capacity (injection) Entry capacity (withdrawal) PITS 130 200 70 300 Serene Sud 185 170 50 430 Sediane Littoral Interruptible (GWh per day) Firm (GWh per day) Interruptible (GWh per day) Firm (GWh per day)
South South North North
North-South L North-South Link nk PITS Centre PITS Centre
South South North North
North-South L North-South Link nk PITS Sediane Littoral PITS Sediane Littoral PITS Serene S PITS Serene Sud
Nomination on PITS Centre-Nord and PITS Centre-Sud One nomination in the Storage operator’s IT system Nomination in the same direction for “Centre-Nord” and “Centre-Sud”: injection (Delivery) or
(Reception) Nomination on PITS Sediane Littoral and PITS Serene Sud Nomination in the same direction for both points: injection (Delivery)
On every PITS, possibility of obtaining additional capacity on top of annual allocation associated with your rights. This capacity his available if one shipper doesn’t use all its capacity. This capacity is obtained by means of nominations on top of annual allocations associated with your rights. Consistent with Storengy day-ahead offer In addition, in the event of capacity reduction or interruption, UIOLI rules, as on PIRs, in order to reallocate capacity
Availability of interruptible capacity published at 3.30 p.m. on D-1 Information sent by fax
Availability of interruptible the capacity forecast and published on D-3, updated on D-2, and finally published at 3.30 p.m. on D-1 Availability forecasts will take into account your own forecasts and nominations
Publication on the ECT website
Please give us your feedback on the implementation of the new tariff on your side …
For example on:
soon, clear / confused, inadequacy on specific points…)
Climatic parameter Climatic parameter = Demand for gas or consumption levels Shippers’ Shippers’ Scheduling cheduling parameter arameter = Network configuration Maintena Maintenance work nce work
Delivery (Del) Delivery (Del)
Recepti Reception (Rec)
PITS LINK PIR
Average daily temperature = Main consumption indicator Below a given temperature = Tthreshold: interruptible capacity increases in linear proportion to temperature fall Above Tthreshold: interruptible capacity depends on average monthly consumption
The availability of interruptible capacity at one point on the network can increase as a result of quantities scheduled at other points on the network
Sche hedule duled qua d quantities at ntities at Montoir Montoir LNG ter NG terminal inal make interruptible capacity available for the North > South link: depends on scheduled entry quantities on PITS Centre to the South zone depends on scheduled quantities on PIR MIDI up to 190 GWh per day of interruptible capacity Climatic conditi Climatic conditions
additional available interruptible capacity of up to 30GWh per day
Sche hedule duled qua d quantities at ntities at Montoir Montoir LNG ter NG terminal inal make interruptible capacity available for the North to South link: 40% of the first 150 GWh per day at Montoir are dedicated to the N-S link (60% dedicated to extra capacity from PITS Sediane Littoral) 100% of the next 50 GWh per day at Montoir any unused interruptible exit capacity from the PITS Sediane Littoral can be re-allocated to the N-S link on day D-1 depending on aggregate nomination up to 190 GWh per day of interruptible capacity Climatic conditi Climatic conditions create
additional interruptible capacity of up to 30GWh per day
Scheduled quantities at Montoir LNG terminal make interruptible exit capacity from from the Nort the North zone h zone available on PITS Sediane Littor
al: 60% of the first 150 GWh per day at Montoir any unused interruptible capacity on the N-S link can be re-allocated to the PITS Sediane Littoral on day D-1 depending on aggregate nomination up to 185 GWh per day Interruptible entry capacity from from PITS Sediane Litt PITS Sediane Littoral to t
e North zone interruptible capacity up to 50 GWh per day is available when capacity scheduled at Montoir is less than 150 GWh per day
Interruptible entry capacity from PITS Centre Sud from PITS Centre Sud to the South zone
Interruptible capacity is available if temperature is below 15.5°C in Lyon = (15.5-T) x 7.9 GWh per day Additional Interruptible capacity depends on the scheduled exit quantities at PIR Midi up to 70GWh per day Interruptible exit capacity from t from the South zone for PITS Centre e South zone for PITS Centre Sud Sud depends on the use of the South to North link: unused capacity on the South to North link can be used on the South to PITS Centre
Similar rules apply
Firm capa rm capacity city re reductions on N ductions on N > S a > S and e d exit from N it from North z rth zone to Se
diane Littoral published are based only on minimal out published are based only on minimal output at t put at the Montoir e Montoir LNG terminal ( NG terminal (restrictive restrictive scenario scenario) Possibly increase in available capaci Possibly increase in available capacity if t ty if the Montoir e Montoir output is higher utput is higher
Sediane Littoral
North - South zones boundary
Beauce Maine Seine B
r g
n e S
n e Vendômois Centre
Montoir
Reducti Reductions in published firm ca
pacity on N > S and exit from North z
ne Littoral are based onl ttoral are based only on mi y on minimal output nimal output at Montoir at Montoir LNG terminal (rest NG terminal (restrictive ictive scenario) scenario) Po Possib ssible le increase in increase in available capacity only for N > S available capacity only for N > S if Montoir if Montoir is is higher higher
Montoir Sediane Littoral
North - South zones boundary
Beauce Maine Seine B
r g
n e S
n e Vendômois Centre
10 years
The restriction his higher than expected
The published works schedule was maintained more closely in
The data supplied in March is reliable
2.5% Case where capacity is reduced below forecast levels Trend 2008 2008 2007 2007
June GRTgaz collects all engineering work by its contractors. July-August Consolidation of ongoing engineering work Autumn Calculation of capacity reductions Publication of an indicative works schedule for year n Ye Year n- n-1 December Coordination with adjacent operators January Publication of the works schedule for year n Publication of associated restrictions Presentation to shippers February Bilateral meetings with interested shippers March 1 Publication of the finalised works schedule Ye Year n n April 1 Beginning of engineering works for year n
One of the largest One of the largest transmission systems in Europe with: 31,600 km 31,600 km of pipelines:
6,800 km on the main transmission system,
,300 delivery stations,
interconnections at border points,
with LNG terminals,
with storage facilities
Main works in 2009 (H-gas network)
INSPECTIONS - INSTRUMENTED PIGGINS SAFETY GROUNDWORK & LAND RESTORATION MAJOR NATIONWIDE PROJECTS COMPRESSOR MAINTENANCE
A few figures:
602 interventions as of March 1, 2008 (5,504 days) 221 interventions deemed as having an impact as of March 1, 2008 (1,786 days)
607 interventions as of Feb 13, 2009 (6,210 days) 211 interventions deemed as having an impact as of Feb 13, 2009 (1,655 days) Conclusion: Works schedule as significant as in 2008, with the introduction of a new tariff structure based on two zones.
Restrictions shall only apply to PIRs and links within the infrastructure’s perimeter Impact on PIRs and links that are geographically close shall be considered primarily
(as far as possible)
The sum N > S + injection Sediane Littoral shall be restricted to the pro-rata proportion
(same physical infrastructures!)
Comparison of availibility rates of PIR capacities between 2008 and 2009
86,8% 87,5% 90,2% 77,6% 85.2% 97,0% 96,2% 81,4% 93,1% 79.7% 52.0%. 98,4%
0,0% 10,0% 20,0% 30,0% 40,0% 50,0% 60,0% 70,0% 80,0% 90,0% 100,0% Offtake Dunkerque Offtake Obergailbach Offtake Taisnières B Offtake Taisnières H Delivery Midi Delivery Oltingue
Apr 1, ‘09 to Oct 31, ‘09 Apr 1, ‘08 to Oct 31, ‘08
Comparison of availibility rates of PITM capacities between 2008 and 2009
96.6% 85.1% 84.68% 90.55%
0,0% 10,0% 20,0% 30,0% 40,0% 50,0% 60,0% 70,0% 80,0% 90,0% 100,0%
Fos Montoir
All the year 2009 All the year 2008
North zone to South zone 2009: Injection Storage Group Sediane Littoral
71.6% 111.1% 73.1% 115.2%
0,0% 20,0% 40,0% 60,0% 80,0% 100,0% 120,0% 140,0%
Availibility rate of major links and PITS
Apr 1, ‘09 to Oct 31, ‘09
Firm
Apr 1, ‘09 to Oct 31, ‘09
Firm + Interruptible
Contractual path
PIR ENTRY DUNKERQUE firm capacity with GRTgaz works - 2009
100 200 300 400 500 600 01/01/2009 15/01/2009 29/01/2009 12/02/2009 26/02/2009 12/03/2009 26/03/2009 09/04/2009 23/04/2009 07/05/2009 21/05/2009 04/06/2009 18/06/2009 02/07/2009 16/07/2009 30/07/2009 13/08/2009 27/08/2009 10/09/2009 24/09/2009 08/10/2009 22/10/2009 05/11/2009 19/11/2009 03/12/2009 17/12/2009 31/12/2009
Date Capacities GWh/day
Firm Capacity with works Firm Capacity
500 Villiers le Bel
Artère du Nord 2 Test Cuvilly
Artère du Nord 2
Villiers le Bel
Artère de Seine
Artère du Nord 2
and Fontenay Stopple welding Artère du Nord 1 Upgrade Férolles DN 500 Workshop Repairs Cuvilly Preventive mainten. Cuvilly
Contractual path
PIR ENTRY TAISNIERES H firm capacity with GRT-Gaz works - 2009
100 200 300 400 500 600 700 1 / 1 / 2 9 1 5 / 1 / 2 9 2 9 / 1 / 2 9 1 2 / 2 / 2 9 2 6 / 2 / 2 9 1 2 / 3 / 2 9 2 6 / 3 / 2 9 9 / 4 / 2 9 2 3 / 4 / 2 9 7 / 5 / 2 9 2 1 / 5 / 2 9 4 / 6 / 2 9 1 8 / 6 / 2 9 2 / 7 / 2 9 1 6 / 7 / 2 9 3 / 7 / 2 9 1 3 / 8 / 2 9 2 7 / 8 / 2 9 1 / 9 / 2 9 2 4 / 9 / 2 9 8 / 1 / 2 9 2 2 / 1 / 2 9 5 / 1 1 / 2 9 1 9 / 1 1 / 2 9 3 / 1 2 / 2 9 1 7 / 1 2 / 2 9 3 1 / 1 2 / 2 9
Date Capacities GWh/day
Firm Capacity with works Firm Capacity Quality Conversion L to H with works Quality Conversion L to H A12 : Cherré
Artère de Seine
Artère du nord 2
Villiers le Bel A12: Cherré MSU overhaul Taisnières Comp. Manifold conn. No.3 Morelmaison
Inspection
EKOFISK Valve tightness Artère du Nord 2 Repair work on valves Taisnières Compr. Inspection TROLL E37 Conn. Nord 1 Taisnières
Artère du Nord 2 Test Artère Nord 1 Switchover Laneuvelotte (F33) MSU overhaul Laneuvelotte Eng.w. Fontenay + test PVX Upgrade Ferolles DN500 Maintenance Cuvilly Overhaul Taisnières
Cuvilly
Artère du Nord 2
Contractual path
PIR ENTRY OBERGAILBACH firm capacity with GRTgaz works - 2009
100 200 300 400 500 600 700 1 / 1 / 2 9 1 5 / 1 / 2 9 2 9 / 1 / 2 9 1 2 / 2 / 2 9 2 6 / 2 / 2 9 1 2 / 3 / 2 9 2 6 / 3 / 2 9 9 / 4 / 2 9 2 3 / 4 / 2 9 7 / 5 / 2 9 2 1 / 5 / 2 9 4 / 6 / 2 9 1 8 / 6 / 2 9 2 / 7 / 2 9 1 6 / 7 / 2 9 3 / 7 / 2 9 1 3 / 8 / 2 9 2 7 / 8 / 2 9 1 / 9 / 2 9 2 4 / 9 / 2 9 8 / 1 / 2 9 2 2 / 1 / 2 9 5 / 1 1 / 2 9 1 9 / 1 1 / 2 9 3 / 1 2 / 2 9 1 7 / 1 2 / 2 9 3 1 / 1 2 / 2 9
Date Capacities GWh/day
Firm Capacity with works Firm Capacity
Restoration of DN 600 Artère de Lorraine F33 Project Laneuvelotte – Phase2 F33 Project Laneuvelotte – Phase2 Smart pig DN900 Artère du Nord Est Smart pig DN900 Artère du Nord Est Restoration of DN 750 Artère de Seine Overhaul HV-LV station Laneuvelotte Restoration w. Obergailbach Restoration w. DN900 Artère du Nord
Contractual path
NORTH > SOUTH Link firm capacity with GRTgaz works - 2009
50 100 150 200 250 300 350 400 450 500 1 / 1 / 2 9 1 5 / 1 / 2 9 2 9 / 1 / 2 9 1 2 / 2 / 2 9 2 6 / 2 / 2 9 1 2 / 3 / 2 9 2 6 / 3 / 2 9 9 / 4 / 2 9 2 3 / 4 / 2 9 7 / 5 / 2 9 2 1 / 5 / 2 9 4 / 6 / 2 9 1 8 / 6 / 2 9 2 / 7 / 2 9 1 6 / 7 / 2 9 3 / 7 / 2 9 1 3 / 8 / 2 9 2 7 / 8 / 2 9 1 / 9 / 2 9 2 4 / 9 / 2 9 8 / 1 / 2 9 2 2 / 1 / 2 9 5 / 1 1 / 2 9 1 9 / 1 1 / 2 9 3 / 1 2 / 2 9 1 7 / 1 2 / 2 9 3 1 / 1 2 / 2 9
Date Capacities GWh/day
Firm Capacity with works Firm Capacity Interruptible Capacity A12 Project Cherré Inverter maintenance Saint Victor Regulatory checks Evry Block valve checks Grande Ceinture Parisienne Pigging Cherré Block valves 752 Grande cein. Paris. Unavail., restor. 900 Artère de Beauce Calibration Maintenance Vindecy Restor. Artère de Bourgogne 2nd regulatory check Evry 2nd Unavail., restor. 900 Artère de Beauce Station filter overhaul Cherré MSU annual overhaul Cherré Safety groundwork Artère du Charolais MSU without Decomp. Beynes Ligne Workshop overhaul Beynes
Gassco: Dunkerque shutdown on June 2-3-4, 2009 shutdown of Zeebrugge terminal in Week 22. Eon GasTransport / Gaz de France Deutschland Transport: Coordination at Obergailbach. Fluxys: Coordination at Taisnières Transitgas: Ruswill compression work in Week 35 with impact on Oltingue TIGF: Establishment of a reference schedule. Storengy and Elengy: Regular coordination meetings
Study carried out for each day from April 1 to October 31, 2009 with: Average monthly consumption. Average monthly delivery to TIGF and OLTINGUE recorded in the last 3 years. Inclusion of the ELENGY output schedule at Montoir and Fos and the performances
maintenance schedule. History of inventory levels and target levels provided by STORENGY. Inclusion of restrictions due to GRT engineering works. Maximisation of the N > S Link and the Sediane Littoral PITS including the interruptible proportion generated by Montoir in accordance with the rules set and published on GRTgaz.com
In February 2009, the works schedule is in its consultation and adjustment phase (bilateral meetings would be a possibility). Publication of the reference works schedule in March 2009. 2009 works schedule comparable with 2008 with increased complexity as a result of the new tariff structure. In putting together its maintenance programme, GRTgaz has included the problem of filling the storage plants on the basis of previous assumptions. GRTgaz is doing its best to optimise its work schedule in cooperation with the Regions and adjacent operators (concealed work).