Riverview Heights Darren K. Howard Structural Option Architectural - - PowerPoint PPT Presentation
Riverview Heights Darren K. Howard Structural Option Architectural - - PowerPoint PPT Presentation
Riverview Heights Darren K. Howard Structural Option Architectural Engineering Spring Thesis 2005 Advisor: Dr. Ali Memari Riverview Heights Darren K. Howard Structural Option Table of Contents: 1.0 Project Background 2.0 Problem
Riverview Heights
Darren K. Howard Structural Option
1.0 Project Background 2.0 Problem Statement 3.0 Solution Overview 4.0 Structural Redesign 5.0 Mechanical Issues 6.0 Acoustical Issues 7.0 Cost Estimates 8.0 Conclusions and Recommendations Acknowledgements Questions
Table of Contents:
Riverview Heights
Darren K. Howard Structural Option
1.0 PROJECT BACKGROUND
Riverview Heights
Darren K. Howard Structural Option 1.0 Project Background:
- Conshohocken, Pennsylvania
- 4 apartment levels
- 2 levels of partially underground parking
Riverview Heights
Darren K. Howard Structural Option 1.1 Apartment Structural Systems:
- Bearing Walls: Wood stud walls
- Floor: 20” deep, floor trusses
- Lateral System: Wood Panel Shear Walls
Riverview Heights
Darren K. Howard Structural Option 1.1 Parking Structural Systems:
- Elevated Two-Way concrete slab with drop panels
- Top slab is a 11” thick “transfer slab”
- “Transfer slab” picks up random bearing wall loads
- Concrete columns send loads to spread footings
Riverview Heights
Darren K. Howard Structural Option
2.0 PROBLEM STATEMENT
Riverview Heights
Darren K. Howard Structural Option 2.0 Problem Statement
- Lumber is a renewable, but not unlimited resource
- New building materials will eventually become necessary
- Alternative materials and methods must be found
Riverview Heights
Darren K. Howard Structural Option
3.0 SOLUTION OVERVIEW
Riverview Heights
Darren K. Howard Structural Option 3.0 Solution Overview
- Cold-formed steel buildings are growing in popularity
- Recyclable material
- Not susceptible to termite damage
- Will not burn or harbor mold
- Will not rot, shrink, warp or split
- Prices for cold-formed steel have been more stable than
lumber
- Construction methods are very similar to wood framing
Riverview Heights
Darren K. Howard Structural Option
4.0 STRUCTURAL REDESIGN
Riverview Heights
Darren K. Howard Structural Option 4.0 Structural Redesign
- Replace existing bearing walls with cold-formed studs
- Replace wood floor trusses with cold-formed joists
- Investigate the use of possible lateral systems:
Wood panel shear walls over cold-formed studs Lateral strap bracing
Riverview Heights
Darren K. Howard Structural Option
4.1 BEARING WALLS
Riverview Heights
Darren K. Howard Structural Option 4.1 Bearing Wall Redesign
- Existing bearing walls and unit separation walls:
Riverview Heights
Darren K. Howard Structural Option 4.1 Bearing Wall Redesign
- Design Considerations:
Replace existing unit separation walls with a single cold-formed stud wall Set studs at a spacing of 24” o.c. rather than 16” o.c.
Riverview Heights
Darren K. Howard Structural Option 4.1 Bearing Wall Redesign
- Redesigned Walls:
Unit separation walls: 6” wide studs @ 24” o.c. Interior bearing walls: 3-5/8” studs @ 24” o.c. Gauge of stud varies from floor to floor
Riverview Heights
Darren K. Howard Structural Option 4.1 Bearing Wall Redesign 11.51 8-11 6SW-12@24” 1 11.51 6-8 6SW-12@24” 2 7.56 5.3-6.6 6SW-14@24” 3 5.73 3.2-4.4 6SW-16 @24” 4 Allowable (kips) Load (kips) Stud Floor Unit Separation Walls
Riverview Heights
Darren K. Howard Structural Option 4.1 Bearing Wall Redesign
7.32 5-6 358SW-12@24” 1 5.12 4-4.48 358SW-14@24” 2 4.05 3-3.6 358SW-16@24” 3 2.75 2-2.4 358SW-18 @24” 4
Allowable (kips) Load (kips) Stud Floor Interior Unit Bearing Walls
Riverview Heights
Darren K. Howard Structural Option
4.2 FLOOR SYSTEM
Riverview Heights
Darren K. Howard Structural Option 4.2 Floor System Redesign
- Existing Floor: 16’ to 25’ interior spans
Riverview Heights
Darren K. Howard Structural Option 4.2 Floor System Redesign
- Design considerations:
Cold-formed steel joists should require less depth This will add additional floor-to-floor height in units
Riverview Heights
Darren K. Howard Structural Option 4.2 Floor System Redesign
- Redesigned Joists: 14j10 Marino/Ware Joists
14” deep, 10 gauge joists @ 24” o.c. Allowable p.l.f. = 130 p.l.f. ( δ < L/360) An additional 6” of floor-to-floor height is achieved
Riverview Heights
Darren K. Howard Structural Option
4.3 LATERAL RESISTANCE
Riverview Heights
Darren K. Howard Structural Option 4.3 Lateral System Redesign
- Existing Lateral System: Wood Shear Panel Walls
Riverview Heights
Darren K. Howard Structural Option 4.3 Lateral System Redesign
- Design Considerations:
Riverview Heights
Darren K. Howard Structural Option 4.3.1 Lateral System Redesign
- Alternative #1: Wood shear panels over cold-formed studs
Greater strength = fewer shear walls required
36 36 1 33 36 2 25 36 3 22 36 4 CF Steel Wood Floor # of Shear Walls Required
Riverview Heights
Darren K. Howard Structural Option 4.3.2 Lateral System Redesign
- Alternative #2: Lateral Strap Bracing
Riverview Heights
Darren K. Howard Structural Option 4.3.2 Lateral System Redesign
- Alternative #2: Lateral Strap Bracing
- STAAD frame model of tension braces
Riverview Heights
Darren K. Howard Structural Option 4.3.2 Lateral System Redesign 7.14 4” x 18ga (both sides) 1 7.14 4” x 18ga (both sides) 2 3.56 2” x 18ga (both sides) 3 3.56 2” x 18ga (both sides) 4 Allowable Load (kips) Lateral Strap Sizes Floor
Riverview Heights
Darren K. Howard Structural Option
5.0 MECHANICAL
Riverview Heights
Darren K. Howard Structural Option 5.0 Mechanical Issue
- Major disadvantage of cold-formed steel
Thermal conductivity
HOT COLD
Riverview Heights
Darren K. Howard Structural Option 5.0 Mechanical Issue
- Add a thermal break between the exterior and interior space
- An additional layer of 1” rigid insulation must be installed
Riverview Heights
Darren K. Howard Structural Option 5.0 Mechanical Issue
10.2 13.3
CF Wall (thermal break)
3 ½” steel studs, 24” o.c., R-11 batts, ½” ext. plywood, ½” int. gypsum, 1” rigid insulation over ext. plywood
7.1 9.4
CF Wall (no thermal break)
3 ½” steel studs, 24” o.c., R-11 batts, ½” ext. plywood, ½” int. gypsum
9.6 10.6
Existing Wall:
2x4 Studs, 16” o.c., R-11 batts, ½”
- ext. plywood, ½” int. gypsum
Whole-Wall R-Value Clear-Wall R-Value Wall Assembly
Riverview Heights
Darren K. Howard Structural Option
6.0 ACOUSTICS
Riverview Heights
Darren K. Howard Structural Option 6.0 Acoustics
- Cold-formed studs have lower acoustical properties
- Riverview Heights was designed as an “average” site
- Unit separation walls and floors need to meet an STC
rating of 52
Riverview Heights
Darren K. Howard Structural Option 6.0 Acoustics
- An additional 5/8” of gypsum is required on both sides
- f walls to meet acoustical requirements
- Existing wood floor trusses and the redesigned joists
required resilient channels on the ceiling side
Riverview Heights
Darren K. Howard Structural Option 6.0 Acoustics 57 Existing Floor 56 CF Floor Assembly 53 Existing Walls 57 CF Unit Separation Walls and Corridor Walls STC rating System
Riverview Heights
Darren K. Howard Structural Option
7.0 COST ESTIMATES
Riverview Heights
Darren K. Howard Structural Option 7.0 Cost Estimates Estimate of Wood Framing $780,340.20 Total Cost $241, 647.00 Floor Trusses $553, 316.40 2x4 Stud Walls $70,502.40 Wood Panel Shear Walls Cost System
Riverview Heights
Darren K. Howard Structural Option 7.0 Cost Estimates Estimate of Cold-Formed Framing $1,146,830.20 Total with Either Lateral System $383,875.92 Cold-formed Stud Walls $710,955 Cold-formed Joists $51,984.00 Lateral Strap Bracing $52,387.20 Wood Panel Shear Walls Cost System
Riverview Heights
Darren K. Howard Structural Option 7.0 Cost Estimates Cold-Formed Framing Additional Costs $1,227,538.60 Total Cold-Formed Cost $80,707.68 Total $53.707.68 Additional layer of 5/8” drywall on walls $27,000 1” rigid insulation Cost System
Riverview Heights
Darren K. Howard Structural Option 7.0 Cost Estimates Total Costs
- $447,198.40
Difference in cost $1,227,538.60 Cold-Formed Framing $780,340.20 Wood Framing Cost System CF joists are more than twice the cost of wood floor trusses!!
Riverview Heights
Darren K. Howard Structural Option 7.0 Cost Estimates Total Costs without Floor Systems + $22,109.60 Difference in Cost $516,583.60 Cold-Formed Framing minus Floor System $538,693.20 Wood Framing minus Floor System Cost System
Riverview Heights
Darren K. Howard Structural Option
CONCLUSIONS AND RECOMMENDATIONS
Riverview Heights
Darren K. Howard Structural Option 8.0 Conclusions and Recommendations
- Cold-formed framing is a viable solution if the redesigned
floor framing is not included
- Cost of the cold-formed floor framing was more than twice
the cost of wood trusses
- Cold-formed framing used less material in walls and in
lateral systems
- Using less material translated into lower costs
- Promising conclusion as the need for alternative building
materials becomes greater in the next century
Riverview Heights
Darren K. Howard Structural Option Acknowledgements
- My family and friends
- A.E. faculty
- Staff of Cates Engineering
- Trammel Crow Residential
- Minno & Wasko Architects
- Marino/Ware
- Images courtesy of Marino/Ware, Cates Engineering, and