RESIN BOLT PROJECTILES Hazard control, Rosebery Mine March 2015 - - PowerPoint PPT Presentation

resin bolt projectiles
SMART_READER_LITE
LIVE PREVIEW

RESIN BOLT PROJECTILES Hazard control, Rosebery Mine March 2015 - - PowerPoint PPT Presentation

RESIN BOLT PROJECTILES Hazard control, Rosebery Mine March 2015 PROJECTILE FAILURE? Projectile failure samples from lower mine Typical projectile failure 2 PRESENTATION OVERVIEW The mine Projectile failures Hazard control


slide-1
SLIDE 1

RESIN BOLT PROJECTILES

Hazard control, Rosebery Mine

March 2015

slide-2
SLIDE 2

PROJECTILE FAILURE?

2

Projectile failure samples from lower mine Typical projectile failure

slide-3
SLIDE 3
  • The mine
  • Projectile failures
  • Hazard control methods
  • MSR Development
  • Current status
  • Summary

PRESENTATION OVERVIEW

3

slide-4
SLIDE 4

ROSEBERY MINE

4

  • Current stoping below Mt Black
  • 1500 → 1800m below surface
slide-5
SLIDE 5

MINING METHOD

5

slide-6
SLIDE 6

GROUND SUPPORT

6

slide-7
SLIDE 7

Two brands used at Rosebery De-bonded Secura Bolt (23.5mm bar) De-bonded DSI CS Bar (23.5mm bar) Different nut & washer assembly Both bolts have Minimal resin bond at collar !!

RESIN BOLTS

7

slide-8
SLIDE 8

PROJECTILE FAILURES

8

slide-9
SLIDE 9

THE HAZARD

9

Projectile failures from Rosebery – Lower Mine Secura bolt projectile failure

slide-10
SLIDE 10

THE HAZARD

10

Minimal plate deformation – Impossible to identify!!

slide-11
SLIDE 11

EXTENT OF PROBLEM

11

  • Needed to quantify the problem
  • Once assessment completed, levels barricaded for rectification
slide-12
SLIDE 12

Fibrecrete Plate over Metal Strap – Required testing!

HAZARD CONTROL METHODS

12

slide-13
SLIDE 13

HAZARD CONTROL - Fibrecrete

13

Fibrecrete ‘cow pats’ over bolts QA/QC

  • Poor fibrecrete bond to resin bolt

bearing plates

  • Unable to assess failures

Operational

  • Breaking & re-establishment of

services

  • Fibrecrete availability

Not practical or suitable!

slide-14
SLIDE 14

HAZARD CONTROL – Plate Over

14

QAQC

  • Damage to resin bolt plate
  • Drill steels hitting bolts
  • Poor plate coverage of resin

bolts

  • Replacement plate pops off with

ground movement Operational

  • Breaking & re-establishment of

services

  • Jumbo availability
  • Bearing plate dimensions

Not practical or suitable!

slide-15
SLIDE 15

15

Continuing deformation ‘popping’ plates

HAZARD CONTROL – Plate Over

slide-16
SLIDE 16

Needed a solution that... ‒Does not compromise the integrity of the rock bolt ‒Support fixture still visible for assessment of ground conditions ‒Safe, cost effective & easy to install

METAL STRAP RESTRAINER- MSR

16

slide-17
SLIDE 17

METAL STRAP RESTRAINER- MSR

17

MSR designed to:

  • Fully contain a resin bolt projectile

failure and bearing plate

  • Not damage existing resin bolt
  • Safe installation
  • Suitable for both types of resin

bolts in service Required testing for typical Rosebery ground conditions A – direction of forces from projectile failure B – Deformation of MSR sustained during bolt failure

slide-18
SLIDE 18

18

METAL STRAP RESTRAINER- MSR

Examples of MSR’s in service at Rosebery Lower Mine

slide-19
SLIDE 19

MSR TEST PROGRAME

19

Testing completed with Geotech Pty Ltd NATA accredited lab

slide-20
SLIDE 20

MSR TEST PROGRAME

20

Six test programmes

  • MSR design
  • Dyna bolt

‒ Cracked fibrecrete ‒ Loose scats behind mesh

  • Cable tie option
  • Alternate methods

Solid concrete Cracked fibrecrete Loose scatt Loose fastener Behind mesh

Break down of fastener testing

slide-21
SLIDE 21

MSR TEST PROGRAME

21

Fastener through cracked fibrecrete (left) & loose ‘scat’ (right) Crack in fibrecrete Loose ‘scat’

slide-22
SLIDE 22

22

MSR TEST PROGRAME

Modified original design for use with cable ties for faster installation

slide-23
SLIDE 23

MSR TEST PROGRAME

23

Several alternate options were tested as a part of the programme Daisy Chains

  • Mild steel wire
  • Steel cable

These options did not meet all test criteria

slide-24
SLIDE 24

MSR TEST PROGRAME

24

95 tests completed on Secura & DSI Bolts Results: Successful projectile hazard management for:

  • Fibrecrete drives
  • Meshed drives

Bearing plates held with a cable tie

slide-25
SLIDE 25

Risk assessment ‒Minimise personnel exposure ‒Effective hazard mitigation ‒Level plans Development of TARP for further failures Training package for operators

UNDERGROUND INSTALL

25

slide-26
SLIDE 26

TARP

26

slide-27
SLIDE 27

TARP

27

slide-28
SLIDE 28

28

TRAINING PACKAGE

Operators trained to install straps

  • Video
  • Bolt identification
  • Level plans
  • TARP

Operator feed back on safe install

slide-29
SLIDE 29

TRAINING PACKAGE

SECURA BOLT

  • BIG STRAP
  • 1 piece nut and washer
  • Fit cable tie to nut of Secura bolt
  • Ensure cable tie is firm

DSI BOLT

  • SMALL STRAP
  • 2 piece nut and washer
  • Fit cable tie to bolt tail
  • Ensure cable tie is firm

Secura Bolt DSI Bolt

slide-30
SLIDE 30

TRAINING PACKAGE

  • Use for ALL TYPES of resin

bolts

  • 3 thick cable ties per strap –

ZIP UP TIGHT

  • 1 thick cable tie per plate –

LOOSE TO MESH

NEVER STAND DIRECTLY IN FRONT OF A LOADED RESIN BOLT

THICK CABLE TIES

slide-31
SLIDE 31

COMPARISON

31 MSR PLATE OVER FIBRECRETE

COST OF CONSUMABLES

$11 $10.00 $30

  • No. PER SHIFT

~300 ~150 ~100

PROS

  • Easy to install
  • Minimal training required for
  • perators
  • Consistent install between
  • perators
  • Test proven method
  • Minimal service work/

disruptions required

  • Remote application
  • Remote application

CONS

  • Battery life of hilti drills for

installing with fastener

  • Inconsistent install between
  • perators
  • Not 100% effective for all

bolts

  • Prep work required before

jumbo - services etc…

  • Damage to rock bolts
  • Equipment & operator

availability

  • Inconsistent install between operators
  • Prep work required before jumbo -

services etc…

  • Cold joins
  • Equipment & operator availability
slide-32
SLIDE 32
  • 100% projectile failure containment
  • 30+ fully contained failures
  • All crews able to install MSR’s
  • Faster installation with cable ties
  • Positive feed back from
  • perators!!

SUCCESS AT ROSEBERY!

32

slide-33
SLIDE 33

SUCCESS AT ROSEBERY

33

slide-34
SLIDE 34

CURRENT STATUS

34

Bolt optimization project Bolt design change

  • Soft bearing plate
  • Change in de-bond length

Alternate bolt trials

Current de-bonded resin bolt design

slide-35
SLIDE 35

Problem Quantified Barricaded Risk Assessed Rectified Back Mining!

SUMMARY

35

slide-36
SLIDE 36
  • MMG Technical & Operational team

‒Support of the test program ‒Underground installation

  • Geotech Pty Ltd

‒Design input & testing facilities ACKNOWLEDGEMENTS

36