Los Angeles County Metropolitan Transportation Authority
Regional Connector Transit Corridor Project Little Tokyo Working - - PowerPoint PPT Presentation
Regional Connector Transit Corridor Project Little Tokyo Working - - PowerPoint PPT Presentation
Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Little Tokyo Working Group Wednesday, August 5, 2009 Japanese American National Museum Why are we here? Continue the dialogue between
Why are we here?
- Continue the dialogue between Metro and the Little
Tokyo community
- Continue to be transparent as the project progresses
- Discuss issues specific to the Little Tokyo Community as
- ne of three remaining Japantowns in the nation
- Further inform the community about decision points and
the process for this phase
- Continue to be respectful, courteous and understanding
- f each other’s views
Continue the dialogue between Metro and the Little
- Goals of Today’s Meeting
- Project Study History
- Project Study Process
- Overview of Alternatives
- Overview of Conceptual Construction
- Overview of Potential Mitigations
- Q&A
- Next Steps
Agenda
- Metro is committed to working with the Little Tokyo
Community in developing a project which ensures the preservation and respect for the Little Tokyo community
- Progress on the development of the project’s vision and
benefit’s for Little Tokyo
- Identify the project benefits and impacts to the Little
Tokyo community both long term and short term
- Continue to identify proposed mitigations both during
construction and as part of operation
Goals of Today’s Meeting
Regional Connector Overview
- Little Tokyo would be
served by one station (the existing Little Tokyo/Arts District Station)
- Trains to the Eastside
and Pasadena only
- Transfers required to
reach the rest of the Metro Rail system
Direct Rail Service to Little Tokyo Area
Without the Regional Connector
- Little Tokyo would be
served by two stations:
- A new proposed
station
- Existing Little
Tokyo/Arts District Station
- Little Tokyo would have
direct trains to Pasadena, the Eastside, Culver City, and Long Beach
- Little Tokyo would be
accessible by light rail from the entire region
Direct Rail Service to Little Tokyo Area
With the Regional Connector
- Economic
- Improved access
- Transit reliability
- Cost savings
- Time savings
- Security
- Permanent neighborhood identity
- Increased regional visibility of Little Tokyo
Benefits of the Regional Connector Benefits of the Regional Connector
Alternatives Analysis Process
Initiated July 2007 - Completed January 2009
- Nearly 360 people attended scoping meetings and 2 additional rounds
- f public meetings in Nov. 07, Feb. 08 and Oct. 08
- In addition to targeted outreach to key stakeholders such as the Little
Tokyo Community Council and Historic Core Bid
Ongoing Community Outreach and Meetings
- Established during Alternatives Analysis Phase
- Discussed issues related to Little Tokyo and
concerns about 1st & Alameda
- Developed current concept for 1st & Alameda
- Reported results to Little Tokyo community to the
Little Tokyo Community Council and other stakeholders
- Incorporated results into the two build alternatives
Little Tokyo Ad-hoc Advisory Committee
- f the Little Tokyo Community Council
in the environmental process.
Project Development Process
Environmental Review Process
- No Build
- Transportation Systems Management
(TSM)
- At-Grade Emphasis LRT Alternative
- Underground Emphasis LRT Alternative
Alternatives Under Evaluation
No Build Alternative
TSM Alternative
At-Grade Emphasis LRT Alternative
Temple St Temple St A l a m e d a S t A l a m e d a S t
At-Grade Emphasis LRT Alternative
Temple and Alameda (Proposed)
VA Outpatient Clinic Federal Building Department of Water and Power
At-Grade Emphasis LRT Alternative
Temple and Los Angeles and Main Streets (Proposed)
Los Angeles Mall
Los Angeles St Los Angeles St Main St Main St
City Hall East City Hall
Temple St Temple St
City Hall
At-Grade Emphasis LRT Alternative
Main Street between 1st and Temple Streets (Proposed)
City Hall East City Hall East
M a i n S t M a i n S t
City Hall South
and Temple Streets (Proposed)
At-Grade Emphasis LRT Alternative
2nd Street West of Los Angeles Street (Proposed)
Caltrans
L
- s
A n g e l e s S t L
- s
A n g e l e s S t
Kyoto Grand Hotel
2 2nd
nd St
St
Higgins Vibiana Caltrans
At-Grade Emphasis LRT Alternative
2nd Street West of Broadway (Proposed)
LA Times
2 2
n d n d
St St Broadway Broadway
Planned Federal Courthouse Planned Federal
At-Grade Emphasis LRT Alternative
2nd Street West of Los Angeles Street (Proposed)
13’ 11’ 12’ 14’ 8’6” 7’ 13’ 78.6’’
Higgins LAPD Caltrans
Underground Emphasis LRT Alternative
1st St 1st St
Savoy Japanese American National Museum
Central Ave Central Ave A l a m e d a S t A l a m e d a S t
Underground Emphasis LRT Alternative
1st and Alameda Streets (Existing)
Office Depot
2 2nd
nd Street
Street Alameda St Alameda St t t t t t
1st St 1st St
Savoy Japanese American National Museum
Central Ave Central Ave A l a m e d a S t A l a m e d a S t
Underground Emphasis LRT Alternative
1st and Alameda Streets (Proposed) 2 2nd
nd Street
Street
Potential surface Potential surface parking lot parking lot Potential surface Potential surface parking lot parking lot
Alameda St Alameda St
1st St 1st St
Savoy Japanese American National Museum
Central Ave Central Ave A l a m e d a S t A l a m e d a S t
Underground Emphasis LRT Alternative
1st and Alameda Streets (Proposed) 2 2nd
nd Street
Street
Planned Nikkei Center
Alameda St Alameda St
1st St 1st St
Savoy Japanese American National Museum
Central Ave Central Ave A l a m e d a S t A l a m e d a S t
Underground Emphasis LRT Alternative
1st and Alameda Streets (Proposed) 2 2nd
nd Street
Street
Planned Nikkei Center
Alameda St Alameda St
Central Ave Central Ave 1st St 1st St A l a m e d a S t A l a m e d a S t
Savoy Japanese American National Museum
Underground Emphasis LRT Alternative
1st and Alameda Streets (Proposed) 2 2nd
nd Street
Street Potential for Development Potential for Development
Planned Nikkei Center
Alameda St Alameda St t t t t t
Underground Emphasis LRT Alternative
2nd Street (Proposed)
Higgins Little Tokyo Library Vibiana Caltrans
8’6” 12’ 12’ 12’ 16’ 18’ 42’
Caltrans
Metro Experience with Developments
Hollywood/Vine Hollywood/Vine Hollywood/Western Hollywood/Western Hollywood/Highland Hollywood/Highland Wilshire/Western Wilshire/Western
Others: Others: Wilshire/Vermont Wilshire/Vermont Del Mar Del Mar Memorial Park Memorial Park Misson Misson
Metro Experience with Developments
Benefits of the Regional Connector
- Economic Benefit
- 5,700 daily boardings at stations (riders dine, shop and explore)
- Property value increase/new jobs created with local hire
- Improved access
- LRT (rail) Alternatives provides region direct access to and from Little Tokyo
- One train equals the capacity of five 60-foot buses
- Transit reliability
- Buses and at-grade are subject to increased traffic congestion
- Cost savings
- Reduced transfers mean reduced cost to riders (each transfer =$1.25)
- Travel time savings
- Travel times savings from 12 – 20 minutes from Union Station
- Security
- Additional security at station area, not just on the train or bus
- Permanent neighborhood identity
- Integrated design and art around station and portal
Benefits of the Regional Connector
(riders dine, shop and explore) bs created with local hire
Construction Overview
- During Draft EIS/EIR
- Identify how project will be constructed and its impacts
Tunnel & Station construction processes Construction staging and soil removal locations Materials hauling routes & other traffic considerations Safety, air, noise, vibration an other impacts Identify mitigations
- Final EIS/EIR
- Respond to comments
- Certify EIS/EIR and adopt the Mitigation Monitoring Plan
- Factors in making construction decisions
- Engineering/Technical
- Cost
- Timing
- Community Input
Identifying Construction Impacts
constructed and its impacts
Construction staging and soil removal locations
Identifying Construction Impacts
Typical Construction Methods
At-Grade
Trackway construction Colorized concrete 3rd Street at-grade operation Overhead Catenary Pole Installation
Typical Construction Methods
Portal and Underpass
Portal and underpass construction similar but wider for underpass
Typical Underground Construction Methods
Cut and Cover for Stations and Portal
Finished Deck Excavation takes place under deck Opening for access to underground construction
Typical Underground Construction Methods
Tunnel Boring Machine (TBM) for Excavating Tunnels
Finished Tunnel Eastside Tunnel Boring Machines (TBMs) TBM Entering station area Station before TBM arrival
At-Grade Emphasis LRT Alternative
Construction Methods
Trackway on Temple/Main/Los Angeles/2nd
- Utility Relocation
- At-grade construction in street between
concrete barrier
- Excavate to depth of concrete trackway
- Place rail and concrete trackway
- Install foundation for catenary poles
- Install overhead catenary poles and wiring
At-Grade Emphasis LRT Alternative
Construction Activities within Little Tokyo
1st Street trackway excavation 1st Street rail line installation 1st Street trackway, poles and wiring
- Construction of platforms, canopies and walkways at stations
- n Los Angeles and Main Streets takes up to three lanes of
traffic and sidewalk space
At-Grade Emphasis LRT Alternative
Construction Activities within Little Tokyo
Little Tokyo Arts District station Eastside Gold Line East LA Civic Center Station
pies and walkways at stations
- n Los Angeles and Main Streets takes up to three lanes of
Underpass
- Utility Relocation
- Underpass requires installation of
soldier piles along sides to support walls
- Excavation of Alameda to depth
- f underpass
- Construct retaining walls and
supporting structures
- Maintain some traffic flow while
under construction
- Pedestrian Bridge
At-Grade Emphasis LRT Alternative
Construction Activities within Little Tokyo
Underpass construction is similar to portal but wider
- Utility Relocation
3-6 months
- Underpass
2 years
- Trackway/Stations
2 years TOTAL DURATION: APPROXIMATELY 4 YEARS
At-Grade Emphasis LRT Alternative
Potential Construction Timing Greater level of construction activity – exact sequencing and phase to be determined upon further analysis and community input
3-6 months
Underground Emphasis LRT Alternative
Construction Methods
Construction Staging Underpass and Ped Bridge Portal & Tunnel Excavation Portal Construction
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
1
st
S t r e e t 1st Street JANM Proposed Nikkei Development Alameda Street 2nd Street Central Avenue
2nd Street Station at Broadway and Spring
Proposed Concepts
Street Station at Broadway and Spring
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Station, Underpass & Portal Construction
- Clear construction
staging site
- Relocate utilities (2nd
Street Storm Drain)
- Install soldier piles
- Excavate 12-15’ of soil
- Concrete decking is
placed to restore street
- Construction continues
below
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Station, Portal and Tunnel Excavation
- Install shoring and excavate area to depth of station or portal
- Lower TBMs and excavate two parallel tunnels
TBM below
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Traffic flow above Material hauled out from Within staging area Staging Area
Tunnel Construction
- Tunnel and install pre-
cast concrete tunnels lining with gaskets
- After excavation is
complete install rails, electrical and other mechanical systems
- All occurring
underground
Cross-section of tunnel liner segments
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Station Construction
- Install station elements and
architectural features
- Removed decking, repave
street & re-open to traffic
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Repave and restored street in Boyle Heights Soto Station Mezzanine Soto Station Platform
Underpass
- Utility Relocation
- Underpass requires installation of
soldier piles along sides to support walls
- Excavation of Alameda to depth
- f underpass
- Construct retaining walls and
supporting structures
- Maintain some traffic flow while
under construction
- Pedestrian Bridge
Underground Emphasis LRT Alternative
Construction Activities within Little Tokyo
Same as underpass construction for At-grade Emphasis LRT Alternative
- Utility Relocation
3 months
- Drilling soldier piles
1-2 months
- Installing decking
1-3 months
- Tunnel/station/portal
2 years
- Underpass
1 year
- Remove decking & restore street
2-4 months
TOTAL DURATION: APPROXIMATELY 4 YEARS
Underground Emphasis LRT Alternative
Potential Construction Timing in Little Tokyo
Durations can be reduced by overlapping
- r intensifying activities with input from community
Off Street or beneath street
Metro Design – Portal Examples
Metro Gold Line: Del Mar Station
Gold Line portal under Colorado Blvd. Gold Line portal under Colorado Blvd. Gold Line portal under Colorado Blvd.
Metro Development – Portal Examples
Metro Gold Line: Del Mar Station
Development around portal on Metro Gold Line Del Mar Station
Portal Examples
Metro Design – At-Grade Examples
Metro Gold Line: Mission Station
Mission Station in South Pasadena next to Farmers Market Mission Station in South Pasadena
At-Grade Examples
Metro Design – Grade Crossing Examples
Metro Gold Line: Mission St and Meridian Ave, South Pasadena
Similar track configuration
Grade Crossing Examples
Metro Gold Line: Mission St and Meridian Ave, South Pasadena
Los Angeles County Metropolitan Transportation Authority
Metro Support Programs
- Communications
- Safety Education & Outreach
- Construction Impact Mitigation, Stakeholder
Communication and Public Outreach
- Web Development
- Media Relations
- Fact Sheets
- Maps
- Newspaper Ads
- Display Boards
- Construction Site Signage
- Direct Mail Meeting Invitations
Communications
Example Materials
- Construction Safety Outreach
- Rail Operations Safety Outreach
- Schools, Community Centers,
Churches, Neighborhood Groups, Libraries, etc.
- Safety Orientation Tours
- Metro Experience Mobile Theatre
- Rail Safety Ambassador Program
Safety Education and Outreach
Rail Operations Safety Outreach
- Construction Activities Coordination
- Community Support
- Construction Impact Mitigation
- Field Reports
- Monitor Mitigation Measures
- Construction Notices
- Project Promotion
- Stakeholders Communication
Construction Impact Mitigation Program
Construction Activities Coordination
Construction Impact Mitigation Program
Sample Materials
Concerns about:
- Traffic and parking
- Affects on businesses
- Property acquisition issues
- Environmental concerns such as noise, vibration, visual affects
- Driveway and access issues
- Safety
- Physically dividing a
community
- Preserving Little Tokyo
What have we heard?
- Refine the designs
- Develop with the community specific actions and
potential mitigation measures to be included in the Draft EIS/EIR
- Develop and adopt a Mitigation Monitoring Plan,
listing and commits to mitigation measures, specifying the reason for the measure, the timing, the partners in implementing the measure and the method of monitoring for every mitigation measure
How do we act on your input?
Develop with the community specific actions and
During Construction
- Valet parking for businesses
- Lease spaces from underutilized lots
- Shuttle services
- Provide space on Metro property as
part of staged construction After Construction
- Purchase additional land
- Partner on developments with City or
developer for added parking spaces
Potential Mitigation for Parking
- Support community events
such as Nisei week
- Contract with local businesses
- Sponsor local entertainment
- Provide promotional menus
- Provide high quality
advertising
- Advertise in local newspapers
- Promote local services to
public agencies
- Support farmers markets
Potential Mitigation for Businesses Potential Mitigation for Businesses
- Minimize number of
acquisitions
- Joint development opportunity
- Required to meet all Federal,
State and local laws related to relocation assistance and property acquisition
Mitigation for Acquisition and Displacement Mitigation for Acquisition and Displacement
- Sound walls decorated by local
artists at staging sites
- Use of noise control devices
- Use of electric vs. diesel power
- Hours of construction
- Hauling Routes
- Street Cleaning
Potential Mitigation During Construction Potential Mitigation During Construction
- Community presence program
- Support local arts programs
- Support documentation of neighborhood
history
Potential Mitigation to Preserve Community
- Influence of station, portal,
bridge, underpass and urban design
- Development oriented design
- Maintain access to driveways
& loading docks
- Auto traffic movements
- Pedestrian paths
- Landscaping
- Crosswalk design
Potential Mitigation Through Design Potential Mitigation Through Design
- Regularly scheduled meetings with stakeholders
- Conduct special meetings as necessary
- Issue updates through electronic communication
- Weekly progress meetings in the community
during construction
- Construction phase includes an outreach team in
the field daily available 24/7 as needed
Accountability
Regularly scheduled meetings with stakeholders Issue updates through electronic communication
Benefits of the Regional Connector
- Economic development
- Improved access
- Transit reliability
- Cost savings
- Time savings
- Security
- Permanent neighborhood identity
Minimize short term impacts during construction so that Little Tokyo can experience the long term benefits.
Benefits of the Regional Connector
Minimize short term impacts during construction so that
- On Construction?
- On Design
- On Mitigations?
- From Businesses?
- From Residents?
- From Property owners?
- For Outreach?
Comments and Questions
- Next Little Tokyo Working Group Meeting (Fall 2009)
- Ongoing Stakeholder Meetings
- Community Update Meetings (Nov 2009)