Recycled Water Project Sharon Heights GCC Project Update for the - - PowerPoint PPT Presentation

recycled water project sharon heights gcc
SMART_READER_LITE
LIVE PREVIEW

Recycled Water Project Sharon Heights GCC Project Update for the - - PowerPoint PPT Presentation

Recycled Water Project Sharon Heights GCC Project Update for the City of Menlo Park City Council February 9, 2016 Topics Overview of the Recycled Water Project Sharon Heights GCC Project Description Anticipated Costs and


slide-1
SLIDE 1

Project Update for the City of Menlo Park City Council February 9, 2016

Recycled Water Project – Sharon Heights GCC

slide-2
SLIDE 2

∗ Overview of the Recycled Water Project – Sharon Heights GCC ∗ Project Description ∗ Anticipated Costs and Benefits of Project ∗ Timeline and Current Status ∗ Next Steps

Topics

slide-3
SLIDE 3

∗ West Bay maintains 200+ miles of sewer mains ∗ West Bay conveys 3.5 MGD to Silicon Valley Clean Water ∗ Sharon Heights Golf & Country Club (SHGCC) is a partner with West Bay on the project and is formalizing a contract. Contract will require SHGCC membership approval. ∗ SHGCC: non-potable water demand of 152 AFY ∗ The West Bay Recycled Water Project – Sharon Heights GCC, will meet the 152 AFY demand, and potentially be expanded to meet other user demands in the future

Project Overview

slide-4
SLIDE 4

∗ Phase I (Alternative I) – Supply up to 152 AFY to SHGCC

∗ Wastewater conveyance and pump station ∗ Satellite treatment facility at SHGCC and pump station ∗ Solids discharge pipeline ∗ Recycled Water (RW) conveyance pipeline on SHGCC

∗ Phase I (Alternative II) – Supply up to 84 AFY to SLAC

∗ RW conveyance pipeline

∗ Phase II (Alternative III) – Supply up to 44 AFY (two business parks and HOA)

∗ RW conveyance pipeline

Project Description

slide-5
SLIDE 5

Project Overview

WTP PS 6” RW Delivery to SLAC

slide-6
SLIDE 6

Project Description

∗ 0.5 MGD Wastewater treatment plant ∗ Wastewater pump station and conveyance pipeline ∗ Solids disposal pipeline ∗ RW pump station ∗ Recycled water pipeline

slide-7
SLIDE 7

Project Description

RW Delivery to SLAC Forcemain from PS Treatment Facility RW Pump Station Waste Solids to Sewer

slide-8
SLIDE 8

Proposed Influent Pump Station Configuration

Existing Sewer Existing Sewer Forcemain to Treatment Facility Below-grade Pump Station Below-grade Valve Box Above-grade Electrical Equipment New Sewer New Sewer

slide-9
SLIDE 9

∗ 3.4 MGD MBR facility (7x the footprint of Sharon Heights facility) ∗ Buried process tanks and common wall construction reduce facility footprint ∗ No offensive odors or noise with covered process tanks

Example: Santa Paula Water Recycling Facility

September 2008 December 2008 June 2009 December 2009

slide-10
SLIDE 10

∗ Alternative I – SHGCC only ∗ 152 AFY of recycled water

∗ Total Capital Cost: $15.6 M ∗ Annual O&M Costs: $233,000 ∗ Unit Cost, Annualized: $6,100/AF

Project Benefits and Costs

slide-11
SLIDE 11

∗ Alternative II – SHGCC and SLAC

∗ Up to 236 AFY of recycled water ∗ Total Capital Cost: $17.1 M ∗ Annual O&M Costs: $258,000 ∗ Unit Cost, Annualized: $4,300/AF

Project Benefits and Costs

slide-12
SLIDE 12

∗ Alternative III –SHGCC and other users

∗ Up to 197 AFY of recycled water ∗ Total Capital Cost: $17.2 M ∗ Annual O&M Costs: $248,000 ∗ Unit Cost, Annualized: $5,200/AF

Project Benefits and Costs

slide-13
SLIDE 13

∗ Create a new non-potable water supply ∗ Increase water reliability in drought conditions ∗ Decrease usage of potable water for non-potable uses ∗ Help City meet 20 by 2020 water conservation goals

Project Benefits

slide-14
SLIDE 14

∗ Market survey completed August 2014 ∗ Facilities Plan completed August 2015 ∗ CEQA – MND adopted December 2015 ∗ State Revolving Fund (SRF) Application Completed December 2015

∗ Qualify for 1% loan & up to $6M grant

∗ Funding agreement with SWRCB by March 2016

Project Status

slide-15
SLIDE 15

Phase I (Alternative I):

∗ Design-Build-Operate 2016-2017 ∗ Initial phases 2016: Planning and Coordination, Acquisition and Management, Predesign, Design Review, Permitting ∗ Project Construction: late 2016 - 2017

Phase II (Alternative II) Construction: 2018+ Phase II (Alternative III) Construction: 2019+

Timeline

slide-16
SLIDE 16

∗ Program Management Contracting ∗ Finalize Memorandum of Understanding between West Bay and City of Menlo Park ∗ West Bay & SHGCC contract finalization ∗ Design/Build Procurement ∗ Predesign & Permitting ∗ Funding Coordination

∗ Execute funding agreement with SWRCB ∗ Apply for other grants as appropriate

Next Steps

slide-17
SLIDE 17

Next Steps