Recent Experience From Operation & near future Outlook
- V. Chohan
Recent Experience From Operation & near future Outlook V. - - PowerPoint PPT Presentation
Recent Experience From Operation & near future Outlook V. Chohan CERN, Geneva, Switzerland Follow-up Review of Reception Tests of CryoMagnets, AT Division, 16 December 2003 Outline Operation Experience since July 03 1. Where are we &
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
explanations & hard limits
( no cold tests) as expected from I CS & ACR so that we can all benefit from that experience
testing programme as was foreseen.
requirement & in the light of current magnet performance,
the secondary benefits available if such option is chosen I n addition, will show the setting up of the OP team in staffing , OP Tools necessary, developed & ones that need further efforts to continue successful operation.
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
5. 24 hr MTM piquet started end-Aug, hence further efficiency in work; this was not the case Feb-Aug 03(upto 22hr Mon-fri ) 6. Availability of New Benches for testing ( E2 -9 Sept, F2 -9 Oct) and with similar software / hardware as in C cluster for facilitated OP work 7. Stream-lining of magnet tests results storage directly in MTF database brought further simplicity in OP work & approach to tests - D.Tommasini deserves the exclusive thanks for that. 8. ‘Jackie-boxes’ & trotinette , Ohmic M’ment ease 9. Traveller clarifications & move of certain HV tests to I CS in Oct 03
Cohesion amongst Op crew of various backgrounds & cultures. ( & resolution
etc for I ndian Associate )
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
4 8 12 16 20 24 28 32
F e b M a r c h a p r i l m a y j u n e j u l y a u g s e p t O c t n
d e c
Month in 2003
total no of OP
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Y e a r2 0 0 3 F e b M a rc h a p ril m a y ju n e ju ly a u g s e p t O c t n o v d e c
1 k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in 2 G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H 3 J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie 4 Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l 5 N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille 6
J a k o b
F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e 7 A B 7 A B 7 A B 7 8
J a c q u e s O J a c q u e s O J a c q u e s O
9
D a v e D a v e D a v e
1 0 G .A d r ia n 1 1 1 2 1 3 g a n d h i g a n d h i g a n d h i g a n d h i d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l 1 1 4 m a ra th e m a r a th e m a r a th e m a r a th e u tta m u tta m u tta m u tta m u tta m u tta m u tta m 2 1 5 p r a m o d p ra m o d p r a m o d p r a m o d p r a m o d p r a m o d p ra m o d M 2 2 M 2 2 M 2 2 M 2 2 3 1 6 m a d h u m a d h u m a d h u m a d h u m a d h u m a d h u m a d h u M 2 3 M 2 3 M 2 3 M 2 3 4 1 7 s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y M 2 4 M 2 4 5 1 8 M 2 5 M 2 5 6 1 9 s h e tty s h e tty s h e tty s h e tty s h e tty s h e tty s h e tty 7 2 0 ra m r a m r a m r a m r a m ra m r a m 8 2 1 K h a r e K h a r e K h a r e K h a r e K h a r e 9 2 2 P a r e e k P a r e e k P a re e k P a r e e k P a r e e k 1 0 2 3 K a s liw a l K a s liw a l K a s liw a l K a s liw a l K a s liw a l 1 1 2 4 S r id h a r S rid h a r S r id h a r S r id h a r S r id h a r 1 2 2 5 2 6 2 7 G re e n M e a n s E x p e rie n c e d Y e llo w M e a n s N e w A rriv a ls F e b M a r c h a p r il m a y ju n e ju ly a u g s e p t O c t n o v d e c T O T A L 1 3 1 2 1 0 1 0 1 3 1 3 1 7 1 7 1 8 2 0 2 2 IN D IA 5 5 5 5 7 7 1 1 1 1 1 1 1 2 1 2 A B D iv 8 7 5 5 6 6 6 6 7 7 1 0
E x p e rin c e d if T e s ts fro z e n & s y s te m s C o n s o lid a te d
5 5 5 7 6 8 1 0 1 1 1 1 1 4 1 6
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
d_t est s 2 0 0 4 0 0 6 0 0 8 0 0 1 0 0 0 1 2 0 0 1 4 0 0 P T 1 P T 2 P T 3 P T 4 M M 0 P T 5 M M 1 P T 6 P T 7 M M 2 M M 3 P T 8 M M 4 M M 5 M M 6 P T 9 P T 1 0 P T 1 1 P T 1 2 P T 1 3 P T 1 4 P T M M 1 3 M M 1 4 M M 1 5 P T 2 9 P T 3 0
T i me i n M i n u t e s
t est s r emoved
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
New_t est s 2 0 0 4 0 0 6 0 0 8 0 0 1 0 0 0 1 2 0 0 1 4 0 0 P T 2 P T 3 P T 4 M M 0 P T 5 P T 1 6 P T 6 M M 3 P T 8 M M 4 P T 1 1 P T 3 0 P T 0 9 T i me i n mi n ut e s New
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Prep ICS Connection 720 1440 ICS ICS Prep 5 Lyre test 30 120 MTM Prep 6 IAP at WARM : Conf Res meas CDW1 120 60 MTM Prep 7 HV Insulation Test w arm after Bolting 90 90 MTM Prep 9 Electrical connection of TRU w ith the mobile rack 60 30 MTM Leak Test 72 720 Prep 12 Launch cycle to cool dow n 2160 2160 cryo PT 2 IAP at cold 180 180 MTM PT 3 HV tests at cold & QH res. Meas CDAP. 90 90 MTM PT 4 slow pow er abort check 1KA (125 A/s) 30 30 MTM MM0 Shaft alignment, MMPChecks at 1500 A 90 90 MTM PT 5 Provoked Quench at 1.5 kA; ALL LF, All HF 360 240 MTM PT 16 Diode Test Min NRJ at 3KA 180 180 MTM Interbench recuperation time (8 quenches) 480 PT 6 Training Quenches at 1.9K (4) 1200 1200 MTM PT 7 PT 7
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
MM3 LHC cycle 150 150 MTM MM1 PT8 Check of detraining effect : 30 30 MTM MM4 Full load line & Joints Meas 180 180 MTM MM2 PT 11 Ramp to 12850 A and fast de-excitation test 30 30 MTM PT 9 PT 30 HV Insulation Tests at 1.9 K 90 90 MTM PT 10 PT 09 Minimum Energy Quench @ 6.5 KA + RRR and final w arm up. 240 240 MTM PT 11 PT 31 Launch Thermal cycle w arm up 720 1440
cryo cryo
PT 12 PT 13 Electrical disconnection of TRU and mobile rack. 30 30 PT 13 PT 15 IAP at w arm Conf Res meas CDW2 30 60 PT ICS2 Final HV & Disconnection 720 1440 ICS ICS Time for tests and prep 53.5 60 Miscellaneous( Shafts issues, cryo, faults, etc….) ~10% 5 6 ESTIMATE COLD TESTS (1.9K) Time HOURS 58.5 66 Time for connection/disconnection -ICS [12 +12 hrs] 24 24 48 48 Time for w armup/cool dow n - cryo [ 36 +12 ] 48 48 60 60 Total time in hours 130.5 174.0 Total Time In DAYS 5.4 7.3
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
10 20 30 40 50 60 70 80 90 100
24-mars 31-mars 7-avr. 14-avr. 21-avr. 28-avr. 5-mai 12-mai 19-mai 26-mai 2-juin 9-juin 16-juin 23-juin 30-juin 7-juil. 14-juil. 21-juil. 28-juil. 4-août 11-août 18-août 25-août 1-sept. 8-sept. 15-sept. 22-sept. 29-sept. 6-oct. 13-oct. 20-oct. 27-oct. 3-nov. 10-nov. 17-nov. 24-nov. 1-déc.
Date
Dipoles tested ~120 hrs
~58 hrs
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
5 10 15 20 25
31/ 03/ 03 07/ 04/ 03 14/ 04/ 03 21/ 04/ 03 28/ 04/ 03 05/ 05/ 03 12/ 05/ 03 19/ 05/ 03 26/ 05/ 03 02/ 06/ 03 09/ 06/ 03 16/ 06/ 03 23/ 06/ 03 30/ 06/ 03 07/ 07/ 03 14/ 07/ 03 21/ 07/ 03 28/ 07/ 03 04/ 08/ 03 11/ 08/ 03 18/ 08/ 03 25/ 08/ 03 01/ 09/ 03 08/ 09/ 03 15/ 09/ 03 22/ 09/ 03 29/ 09/ 03 06/ 10/ 03 13/ 10/ 03 20/ 10/ 03 27/ 10/ 03 03/ 11/ 03 10/ 11/ 03 17/ 11/ 03 24/ 11/ 03 01/ 12/ 03 08/ 12/ 03
Date Number of staff or shifts 1 2 3 4 5 6 7 8 9 10 Dipole Usable No of Benches
C2 C1 F1 F2 E2 E1 C2 to SSS A 2 Only
N Benches
E1 Prblm staff
Shifts per week
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
[dipoles x benches x shifts/ test hrs] & [no. of Usable Benches] vs. Date
40 80 120 160 200 240
24/3 31/3 7/4 14/4 21/4 28/4 5/5 12/5 19/5 26/5 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 13/10 20/10 27/10 3/11 10/11 17/11 24/11 1/12 8/12
Week
[dipoles * benches * shifts] / Test hrs 1 2 3 4 5 6 Number of Usable Benches dipole*bench/test_hrs N
sable B enches
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
1. The OP crew work 24 hrs a day;
however, the MTM Piquet 24hr support could only start end-Aug
2. No outside hrs support from Supplier
Groups like AB/ CO which often is essential to go forward , e.g., Files & Config problems, Files upload problems, Applic. S/W, H/W problems, Network, Workstations, etc
3. Similar,lesser extent as above for AB/ PO 4. Shafts & Outside Hrs support: had not
been totally possible even under ICS; now MTM has taken over since several months with new constraint in Inserting or Pulling
at cold only ( < 80 K) - so an additional constraint for Operation ( often, in pulling out !) 5. I CS staff worked 35 hr/ week but then
doubled the staff & worked 14 hrs/ day
6. 11 Nov, [ & 14 July, 8 May..] Support
1. Commissioning Benches or Testing SSS first time as well as normal Dipole Testing Operation ; new Eqp Tests [MTM] 2. Cryostating crisis (Aug-Sept) & ‘chomage
technique’= keeping magnets ‘on’ & cold longer [CRI ,I CS]
3. Anticryo+ MRB crisis & I CS Logistics 4. Shafts Crisis : Lack of sufficient Equip
availability , meaning a constant juggling act to use the 2 available pairs for all
possible no of magnets under test and
with the constraints in insertion/pulling out
[MTM] 5. CFB issues ( C1 :Vclamp Quenches, Tempr.
Probes, etc), E1 mishap,..Leaks, etc [ACR]
6. New I FS Boxes & “goodness” [MEL] 7. Extra or New Tests required :Cold axis,
field Direction, Diode Connections, Qheaters with higher Resistance… [MAS,SU etc]
8. Floor Painting & ROCLA, He Dewar [CRI ,ACR,ADM..]
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
10 20 30 40 50 60 70 80 90
1001 1002 2001 3001 3002 1003 2003 2002 1005 1004 1008 1006 1010 1007 1011 1012 3004 1014 1013 1009
magnet days on Test bench 2001-2
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60
2 4 1 1 6 1 1 9 1 1 7 1 1 8 1 2 3 1 2 2 1 2 4 1 2 6 3 5 1 3 5 1 2 5 3 1 3 2 6 3 9 2 7 2 2 3 3 1 4 2 8 2 9 2 2 2 3 1 1 2 2 5 3 7 3 3 8 1 4 5 3 4 1 2 1 8 2 2 2 1 7 3 4 6 1 3 1 s s s 3 2 8 3 4 3 2 1 2 2 1 2 2 1 3 4 2 2 2 3 4 7 3 3 9 3 4 5 1 2 1 4 2 2 2 5 3 4 4 1 5 2 2 8 2 2 4 1 4 9 3 5 4 2 2 6 s s s 4 1 5 2 3 8 1 4 8 3 5 5 1 3 9 1 2 1 3 1 2 1 3 4 3 2 7 3 3 4 3 2 2 2 2 7 2 2 9 3 5 9 1 2 9 1 2 7 1 2 8 3 6 5 1 3 2 1 3 8
magnet
days on Test bench in 2003
End July & Review
Sept
Oct Nov Dec
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Bench F2 15 sept-21 Nov
5 10 15 20 25 30 35 40
MBBR2025 MBBR1049 MBBR1039 MBBR3034
bench A2: 1 sept-21 Nov
5 10 15 20
MBAR3022 MBBR1020 MBBR3042 MBAR3028 MBAR3054 MBAR3055
Bench C1: 18 Sept to 19 Nov
5 10 15
MBAR3027 MBBL1048 MBAR2024 MBAL3044 MBAL3045 MBBR2021
Bench E2: 28 Aug-25 Nov
5 10 15 20 25
MBBR1031 MBBR2010 MBBR3039 MBBL1050 MBAR2029 MBAR3008 MBBR1034
Bench E1: 9 Sept- 26 Nov 5 10 15 20 25 MBAR3043 MBBR2002 MBBR1042 MBAR2028 MBAR2026 MBBR3012 MBAR2027
Bench F1 9 Oct-24 Nov
5 10 15 20
MBBR2002 MBAR1052 MBBR1021 MBAL3059
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
24 48 72 96 120 144 168 192 216 1042 1032 1034 1052 1039 2029 3008 3044 3022 3027
Total Time(Hours)
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
1+1
27%
0+2
22% 23%
2
19%
4
33% 21%
2
21%
2
35%
1+1
33%
1+1
17%
45 56 85 3 48 36 63 1+1 36 48 SSW No LL 49 4K 42 4K no antiC 24 48 72 96 120 144 168 192 216 1042 1032 1034 1052 1039 2029 3008 3044 3022 3027
Total Time(Hours) Cold test Time(Hours)
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
4K 1+1 25%
TC 4K 8+3
51%
4K 1+1
28%
4K 3
47%
4K 5
24%
TC 4K 8+2
42%
128 159 120 169 85 130
96 192 288 384 480
1050 1031 3028 3042 1020 1029
A2 bench
7 Oct; Extra MMP
A2 bench
22Sept A2 bench
01Sept
Spec MMP 1st E2 28Aug + WE. Shafts E2 15Oct WE. Shafts C1 with SSS 19 Nov
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
ID Task Name 1
CFUA1
2
CFUA2
3
CFBC2
4
CFBC1
5
CFBE1
6
CFBE2
7
CFBF2
8
CFBF1
9
CFBD1
10
CFBD2
11
CFBB1
12
CFBB2
13
CFBA1
14
CFBA2
14-07 21-07 18-08 25-08 10-11 17-11 28-01 28-01 22-03 29-03 2003
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Cold T Tests H s Hour
s: E1 & E1 & E E2 B Benches enches
50 1+1 36 5 38 ssw 2 44 1+1 159 4K TC 8 88 4K 3 140 4K 5 128 4K 1+1 50 4 69 4K TC 7 67 3 31 no shft 4K 1+1 72 4K 5 134 4K 4 48 96 144 192 240 288 336 384 432 480 3043 2002 1042 2028 2026 3012 1031 2010 3039 1050 3008 1034 2029 1032 M agnet .
total hrs Cold Tests
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Time Distribution from Disconnection of Previous Dipole: E1 & E2 Benches
24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 3043 2002 1042 2028 2026 3012 1031 2010 3039 1050 3008 1034 2029 1032 Magnet
Change Over Time Pumping & Cooling Cold Tests Warming Warm Final Tests
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
C o l
d T e s t s H o u r H o u r s : E E 1 & 1 & E E 2 B e n e n c h e c h e s 5 0 1 + 1 3 6 5 3 8 s s w 2 4 4 1 + 1 1 5 9 4 K T C 8 8 8 4 K 3 1 4 0 4 K 5 1 2 8 4 K 1 + 1 5 0 4 6 9 4 K T C 7 6 7 3 3 1 n o s h ft 4 K 1 + 1 7 2 4 K 5 1 3 4 4 K 4 4 8 9 6 1 4 4 1 9 2 2 4 0 2 8 8 3 3 6 3 8 4 4 3 2 4 8 0 3 0 4 3 2 0 0 2 1 0 4 2 2 0 2 8 2 0 2 6 3 0 1 2 1 0 3 1 2 0 1 0 3 0 3 9 1 0 5 0 3 0 0 8 1 0 3 4 2 0 2 9 1 0 3 2 M a g n e t .
to ta l h rs C o ld T e s ts
Time Distribution from Disconnection of Previous Dipole: E1 & E2 Benches
24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 3043 2002 1042 2028 2026 3012 1031 2010 3039 1050 3008 1034 2029 1032 Magnet N
f H
rs
Change Over Time Pumping & Cooling Cold Tests Warming Warm Final Tests
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Standard Model
12 24 36 48 60 72 84 96 108 Per Any Magnet disconnect warm up cold tests cooldown pump down connection
Standard Model 12 *8 slices
12 24 36 48 60 72 84 96 108 Per Any Magnet disconnect warm up cold tests cooldown pump down connection
St a n a nda r da rd M d M ode
l :N o C
T e st s s so M I N I N I M U M 7 2 H H O U R O U RS R REQ U I U I RED
12 24 36 48 60 72 84 96 108 Per Any Magnet disconnect warm up cooldown pump down connection
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
12 24 36 48 60 72 84 96 108 Per Any Magnet disconnect warm up cooldown pump down connection
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
24 48 72 96 120 144 168 192 216 1042 1032 1034 1052 1039 2029 3008 3044 3022 3027
Total Time(Hours)
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
19-Oct-03 26-Oct-03 2-Nov-03 9-Nov-03 16-Nov-03 23-Nov-03 30-Nov-03 7-Dec-03 A2 3054 C1 2024 F1 1052 F2 1049 C1 1048 E1 2026 E2 3008 A2 3055 F2 1039 E1 3012 E2 1034 F1 1021 A2 3022 C1 3027 E2 2029 F1 3059.1 F2 3034 E1 2027 E2 1032 F1 3065 F2 1027 C1 1029 A2 1028 E2 3070 A2 3021 F2 1038 C1 2054 D2 3059.2 F1 3015
Remove Connect Leak Search Cool-Down Cold Test Warm Up
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
STR 13/11/03 Night No Fault STR 14/11/03 MorninNo Fault STR 14/11/03 Afterno 14/11/2003 16:00 14/11/2003 21:00 STR TBC1 Cryogenics Liquefactor STR 14/11/03 Afterno 14/11/2003 16:00 14/11/2003 21:00 STR TBF1 Cryogenics Liquefactor STR 14/11/03 Afterno 14/11/2003 16:00 14/11/2003 21:00 STR TBF2 Cryogenics Liquefactor STR 14/11/03 Night No Fault STR 15/11/03 MorninNo Fault STR 15/11/03 AfternoNo Fault STR 15/11/03 Night 15/11/2003 23:30 16/11/2003 03:06 STR TBC1 Cryo NOT OK current leads spare broken STR 15/11/03 Night 16/11/2003 01:00 16/11/2003 03:06 STR TBF2 Electronics switch box trigger sent STR 15/11/03 Night 16/11/2003 03:06 16/11/2003 03:06 STR TBF2 MMP serial communication STR 16/11/03 Mornin 16/11/2003 06:51 16/11/2003 13:00 STR TBF2 Power converters lead water STR 16/11/03 AfternoNo Fault STR 16/11/03 Night 16/11/2003 22:09 17/11/2003 06:00 STR TBC1 Protection systems V bus external card STR 17/11/03 Mornin 17/11/2003 06:00 17/11/2003 07:42 STR TBC1 Protection systems V bus external card STR 17/11/03 Mornin 17/11/2003 08:37 17/11/2003 11:30 STR TBC1 Protection systems V bus external card STR 17/11/03 AfternoNo Fault
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
OP Reported Faults 18Aug-24 Nov03
50 100 150 200 250 MTM ACR AB/CO AB/PO Faults Source Incidence
OP Reported Faults 18Aug-24 Nov03
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 MTM ACR AB/CO AB/PO Faults Source Incidence in %
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
C 1 1 0 1 9 S S L K 0 3 0 3 1 4 1 7 0 0 . n 0 1 C 1 1 0 1 9 S S L K 0 3 0 3 1 7 0 9 1 0 . n 0 2 C 1 1 0 1 9 S S L K 0 3 0 3 1 7 1 3 1 2 . n 0 3 C 1 1 0 1 9 S S L K 0 3 0 3 1 7 1 6 2 9 . n 0 4 C 1 1 0 1 9 S S L K 0 3 0 3 2 7 0 8 3 9 . n 0 5 C 1 1 0 1 9 S S l K 0 3 0 3 2 7 1 0 5 7 . n 0 6 C 1 1 0 1 9 M M K 0 3 0 3 0 4 1 5 0 4 . m d 0 1 c l a m p C 1 1 0 1 9 T r a i n i n g K 0 3 0 3 0 7 1 6 5 9 . a 0 4 I n t c l a m p C 1 1 0 2 4 S S L L 0 3 0 6 0 9 1 6 1 6 . n 0 1 C 1 1 0 2 4 1 / 2 H F 2 L 0 3 0 6 0 2 2 2 3 1 . h a 0 2 V b u s I n t C 1 1 0 2 4 a l l H F L 0 3 0 6 0 4 1 2 5 4 . h a 0 5 V b u s E x t C 1 2 0 2 5 T r a i n i n g L 0 3 0 7 3 1 0 0 3 4 . a 0 4 V c l a m p - e x t C 1 3 0 4 1 S S L L 0 3 0 8 2 1 0 2 1 4 . n 0 1 V c l a m p - e x t C 1 3 0 4 1 S S L L 0 3 0 8 2 4 0 4 2 2 . n 0 4 V c l a m p - e x t C 1 3 0 4 1 S S L L 0 3 0 8 2 4 1 0 2 2 . n 0 6 V c l a m p - i n t C 1 3 0 4 6 S S L L 0 3 0 9 0 2 1 4 2 6 . n 0 2 V c l a m p C 1 3 0 4 6 S S L L 0 3 0 9 0 2 1 7 5 8 . n 0 3 V c l a m p - e x t C 1 3 0 4 6 S S L L 0 3 0 9 0 2 2 2 5 2 . n 0 5 V c l a m p - e x t C 1 3 0 4 6 P r o v . Q u e n c h @ 1 . 5 K A L 0 3 0 9 0 7 0 8 0 1 . h a 0 2 V b u s - e x t C 1 3 0 4 6 P r o v . Q u e n c h @ 1 . 5 K A L 0 3 0 9 0 7 0 8 5 0 . h a 0 3 V b u s - e x t C 1 3 0 4 6 P r o v . Q u e n c h @ 1 . 5 K A L 0 3 0 9 0 7 0 9 1 6 . h a 0 4 V b u s - e x t C 1 3 0 4 6 D R Q L 0 3 0 9 1 0 1 4 3 2 . p a 0 1 V b u s - e x t C 1 3 0 4 6 D R Q L 0 3 0 9 1 0 1 5 0 8 . p a 0 2 V c l a m p - e x t C 2 1 0 1 5 S S L L 0 3 0 4 0 3 0 9 4 9 . n 0 1 e x t c l a m p C 2 1 0 1 5 S S l L 0 3 0 4 0 3 1 6 1 0 . n 0 2 C 2 1 0 1 5 S S L L 0 3 0 4 0 4 0 8 4 3 . n 0 3 C 2 1 0 1 5 S S l L 0 3 0 4 0 4 1 2 3 3 . n 0 4 C 2 1 0 1 5 S S L L 0 3 0 4 0 4 1 7 4 0 . n 0 5 C 2 3 0 0 5 S S L K 0 3 0 4 1 7 1 0 0 8 . n 0 1 C 2 3 0 0 5 S S L K 0 3 0 4 2 3 1 9 3 7 . n 0 4 C 2 3 0 0 5 S S L k 0 3 0 4 2 3 2 3 4 2 . n 0 5 C 2 3 0 0 5 S S L k 0 3 0 4 2 4 0 3 5 2 . n 0 6 C 2 3 0 0 5 S S L k 0 3 0 4 2 4 0 7 0 7 . n 0 7 C 2 3 0 0 5 D R Q K 0 3 0 4 2 4 1 1 1 4 . p a 0 1 C 2 3 0 0 5 D R Q K 0 3 0 4 2 4 1 5 2 1 . p b 0 1 C 2 3 0 1 3 S S L k 0 3 0 5 1 6 0 2 5 7 . n 0 1 C 2 3 0 1 3 S S L k 0 3 0 5 2 7 2 3 3 2 . n 0 2 C 2 3 0 1 3 S S L k 0 3 0 5 2 8 0 3 0 7 . n 0 3 C 2 3 0 1 3 S S L k 0 3 0 5 2 8 1 6 5 5 . n 0 4 C 2 3 0 1 3 S S L k 0 3 0 5 2 8 2 1 4 0 . n 0 5 C 2 3 0 1 3 S S L k 0 3 0 5 2 9 0 2 5 5 . n 0 6 C 2 3 0 1 3 D R Q k 0 3 0 5 2 9 0 7 0 4 . p a 0 1 C 2 3 0 1 3 D R Q k 0 3 0 5 2 9 1 1 5 6 . p a 0 2 C 2 3 0 1 3 V R Q k 0 3 0 5 3 0 0 0 1 8 . p a 0 3 V C l a m p e x t a t 9 7 9 1 A C 2 3 0 1 3 M i n e n e r g y K 0 3 0 5 2 3 2 0 2 6 . k a 0 4 e n t r y i n f a u l t y l i s t o f q u e n c h t a b l e C 2 3 0 1 3 M i n e n e r g y K 0 3 0 5 2 6 1 9 4 4 . k a 0 4 V c l a m p I n t a s p e r q u e n c h t a b l e C 2 1 0 2 6 S S L K 0 3 0 6 2 0 2 1 5 3 . n 0 1 V c l a m p a t 7 3 0 2 A C 2 1 0 2 6 S S L K 0 3 0 6 2 0 0 1 1 0 . n 0 2 V c l a m p a t 5 7 6 9 A C 2 1 0 2 6 S S L K 0 3 0 6 2 0 0 4 1 1 . n 0 3 V c l a m p a t 9 9 5 3 A C 2 1 0 2 6 S S L K 0 3 0 6 2 0 0 4 1 1 . n 0 4 V c l a m p a t 1 0 0 8 9 A
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
4 8 12 16 20 24 28 32
Jan Feb March april may june july aug sept Oct nov dec
Month in 2004
total no of OP
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
[dipoles x benches x shifts/ test hrs] & [no. of Usable Benches] vs. Date
40 80 120 160 200 240
24/3 31/3 7/4 14/4 21/4 28/4 5/5 12/5 19/5 26/5 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 13/10 20/10 27/10 3/11 10/11 17/11 24/11 1/12 8/12
Week
[dipoles * benches * shifts] / Test hrs 1 2 3 4 5 6 Number of Usable Benches dipole*bench/test_hrs N
sable B enches
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
[Dipoles x Benches x Shifts/ Test Hrs] & [no. of Dipole Usable Benches]
100 200 300 400 500 600 700 800 900 1000 1100 1200
2 4 / 3 / 3 7 / 4 / 3 2 1 / 4 / 3 5 / 5 / 3 1 9 / 5 / 3 2 / 6 / 3 1 6 / 6 / 3 3 / 6 / 3 1 4 / 7 / 3 2 8 / 7 / 3 1 1 / 8 / 3 2 5 / 8 / 3 8 / 9 / 3 2 2 / 9 / 3 6 / 1 / 3 2 / 1 / 3 3 / 1 1 / 3 1 7 / 1 1 / 3 1 / 1 2 / 3 1 5 / 1 2 / 3 2 9 / 1 2 / 3 1 2 / 1 / 4 2 6 / 1 / 4 9 / 2 / 4 2 3 / 2 / 4 8 / 3 / 4 2 2 / 3 / 4 5 / 4 / 4 1 9 / 4 / 4 3 / 5 / 4 1 7 / 5 / 4 3 1 / 5 / 4 1 4 / 6 / 4 2 8 / 6 / 4
Week
[dipoles * benches * shifts] / Test hrs 1 2 3 4 5 6 7 8 9 10 11 12 Number of Usable Benches (dipole*bench)*shifts/test_hrs N
sable B enches
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Hyp : 1 MB or SSS pe r be nch pe r w e e k N benches MB SSS S4 Total MB SSS S4 Total 26/01/2004 6 1 7 0 D2 02/02/2004 6 1 7 6 1 7 09/02/2004 7 1 8 13 2 15 D1 16/02/2004 7 1 8 20 3 23 23/02/2004 7 1 8 27 4 31 01/03/2004 7 1 8 34 5 39 08/03/2004 8 1 9 42 6 48 B1 15/03/2004 8 1 9 50 7 57 22/03/2004 8 2 10 58 9 67 B2 29/03/2004 8 2 10 66 11 77 05/04/2004 8 2 10 74 13 87 12/04/2004 8 2 10 82 15 97 19/04/2004 8 2 10 90 17 107 26/04/2004 8 2 10 98 19 117 03/05/2004 8 2 10 106 21 127 10/05/2004 8 2 10 114 23 137 17/05/2004 6 5 1 12 120 28 0.5 148.5 A1 A2 24/05/2004 6 5 1 12 126 33 1 160 31/05/2004 6 5 1 12 132 38 1.5 171.5 07/06/2004 6 5 1 12 138 43 2 183 14/06/2004 6 5 1 12 144 48 2.5 194.5 21/06/2004 6 5 1 12 150 53 3 206 28/06/2004 6 5 1 12 156 58 3.5 217.5 Already accepted 90 3
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
M agnets Appraisal
8350 8850 9350 9850 10350 10850 11350 11850 12350 12850 13350
M agnet
Amps
First Quench
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
ALL ramp2
8350 8850 9350 9850 10350 10850 11350 11850 12350 12850 13350
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
ALL ramp3
10350 10850 11350 11850 12350 12850 13350 Magnet c u r r e n t
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
ALL ramp3
10350 10850 11350 11850 12350 12850 13350
Magnet current ALL ramp2
10350 10850 11350 11850 12350 12850 13350
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
LI ST OF OPERATI ON METHODS FOR POWER TESTS& Mag. M’ments I N SM18
Revised/ Updated By Remarks
P.K.Kavalan, BARC, India, P.Radheshyam CAT,India
Check at 1000 A
DanielBabu, BARC, India S.Sridhar, IGCAR, India
Fast De-excitation test
at 4.4 K
P.Radheshyam, CAT,India
P.Radheshyam, CAT,India
O.Berrig, CERN,Geneva
Measurement
B.Maurya, BARC, India S.Malhotra , BARC, India Procedure
S.Malhotra, BARC, India
R.Marathe, CAT, India
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Y e a r2 0 0 4 J a n F e b M a rc h a p ril m a y ju n e ju ly a u g s e p t O c t n o v d e c 1 k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in 2 G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H 3 J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie 4 Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l 5 N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille 6 F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e F lo re n c e 7 E ric E ric E ric E ric E ric E ric E ric E ric E ric E ric E ric E ric 8
J a c q u e sO J a c q u e sO J a c q u e sO J a c q u e sO J a c q u e sO
9
D a v e D a v e D a v e D a v e D a v e
1 0 G .Ad ria n G .Ad ria n G .Ad ria n G .Ad ria n G .Ad rian 1 1
A B 1 1 A B 1 1
1 2
A B 1 2 A B 1 2
1 3 d a n ie l d a n ie l d a n ie l d a n ie l M 3 4 M 3 4 M 3 4 M 3 4 M 3 4 M 3 4 M 3 4 M 3 4 1 1 4 u tta m u tta m u tta m u tta m M 3 5 M 3 5 M 3 5 M 3 5 M 3 5 M 3 5 M 3 5 M 3 5 2 1 5 M 2 2 M 2 2 M 2 2 M 2 2 M 2 2 M 2 2 M 2 2 M 2 2 M 4 2 M 4 2 M 4 2 M 4 2 3 1 6 M 2 3 M 2 3 M 2 3 M 2 3 M 2 3 M 2 3 M 2 3 M 2 3 M 4 3 M 4 3 M 4 3 M 4 3 4 1 7 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 M 2 4 5 1 8 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 M 2 5 6 1 9 s h e tty s h e tty s h e tty s h e tty M 3 6 M 3 6 M 3 6 M 3 6 M 3 6 M 3 6 M 3 6 M 3 6 7 2 0 ra m ra m ra m ra m M 3 7 M 3 7 M 3 7 M 3 7 M 3 7 M 3 7 M 3 7 M 3 7 8 2 1 K h a r e K h a re K h a re K h a r e K h a re K h a re M 3 8 M 3 8 M 3 8 M 3 8 M 3 8 M 3 8 9 2 2 P a re e k P a re e k P a re e k P a re e k P a re e k P a re e k M 3 9 M 3 9 M 3 9 M 3 9 M 3 9 M 3 9 1 0 2 3 K a s liw a l K a s liw a l K a s liw a l K a s liw a l K a s liw a l K a s liw a l M 4 0 M 4 0 M 4 0 M 4 0 M 4 0 M 4 0 1 1 2 4 S rid h a r S r id h a r S rid h a r S rid h a r S r id h a r S rid h a r M 4 1 M 4 1 M 4 1 M 4 1 M 4 1 M 4 1 1 2 2 5 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 M 2 6 1 3 2 6 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 M 2 7 1 4 2 7 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 M 2 8 1 5 2 8 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 M 2 9 1 6 2 9 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 M 3 0 1 7 3 0 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 M 3 1 1 8 3 1 M 3 2 M 3 2 M 3 2 M 3 2 M 3 2 M 3 2 M 3 2 M 3 2 1 9 3 2 M 3 3 M 3 3 M 3 3 M 3 3 M 3 3 M 3 3 M 3 3 M 3 3 2 0 3 3 2 1 3 4 2 2 G re e n M e a n s E xp e rie n c e d Ye llo w M e a n s N e w Arriva ls J a n F e b M a rc h a p ril m a y ju n e ju ly a u g s e p t O c t n o v d e c T O T AL 2 4 2 4 2 8 2 5 2 7 2 7 2 7 2 7 2 7 2 7 3 0 3 0 IN D IA 1 4 1 4 1 8 1 8 2 0 2 0 2 0 2 0 2 0 2 0 1 8 1 8 AB D iv 1 0 1 0 1 0 7 7 7 7 7 7 7 1 2 1 2
Exp erin ced if T ests fro zen & system s C o n so lid ated
1 7 1 7 1 9 1 9 1 7 1 7 1 7 1 7 2 3 2 1 2 3 2 3
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S 2 4 2 5 2 6 2 7 22 42 56 23 43 57 24 58 25 59 26 44 60 27 45 61 28 46 62 29 47 63 30 64 31 65 32 48 66 33 49 67 34 50 68 35 51 69 36 52 70 37 71 38 53 72 39 54 73 40 55 74 41 75 W1 W3 W5 W2 W4 W6
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
Ol d 5 0 0 1 0 0 0 1 5 0 0 2 0 0 0 2 5 0 0 P r e p1 P r e p2 P r e p3 P r e p4 P r e p5 P r e p6 P r e p7 P r e p8 P r e p9 P r e p1 0 P r e p1 1 P r e p1 2 P T 3 1 P T 3 2 P T 3 3 P T 3 4 P T 3 5 Pr ep1 Pr ep2 Pr ep3 Pr ep4 Pr ep5 Pr ep6 Pr ep7 Pr ep8 Pr ep9 Pr ep10 Pr ep11 Pr ep12 PT3 1 PT3 2 PT3 3 PT3 4 PT3 5 r emoved
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
n ew_pr ep+con n ect i
scon n ect i
i n g/ war mi n g 5 0 0 1 0 0 0 1 5 0 0 2 0 0 0 2 5 0 0 P r e p I C S P r e p 5 P r e p 6 P r e p 7 P r e p 9 P r e p 1 2 P T 3 1 P T 1 3 P T 1 5 P T I C S 2 T i me i n mi n ut e s con n ect i
di scon n ect i
war m up cooldown
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets
16 December 2003 V.Chohan Follow-up Review of Reception tests of Cryomagnets