Recent developments in Resource Adequacy in California Karl - - PowerPoint PPT Presentation

recent developments in resource
SMART_READER_LITE
LIVE PREVIEW

Recent developments in Resource Adequacy in California Karl - - PowerPoint PPT Presentation

Recent developments in Resource Adequacy in California Karl Meeusen, PhD Senior Advisor Infrastructure and Regulatory Policy WECC Market Interface Committee June 27, 2019 Overview Overview Recent developments at the CPUC


slide-1
SLIDE 1

Recent developments in Resource Adequacy in California

Karl Meeusen, PhD Senior Advisor – Infrastructure and Regulatory Policy WECC Market Interface Committee June 27, 2019

slide-2
SLIDE 2

Overview

  • Overview
  • Recent developments at the CPUC
  • Centralized procurement and decentralized load service
  • Analyzing the RA fleet

Page 2

slide-3
SLIDE 3

What is resource adequacy in California

  • Multiple jurisdictional entities (currently over 30 different

Local Regulatory Authorities) – Each LRA can establish its own RA rules

  • Multiple capacity products procured

– System – Local – Flexible

  • RA resources must be made available to CAISO markets

Page 3

slide-4
SLIDE 4

California’s aggressive pursuit of a low carbon future must consider the future procurement landscape

Page 4

  • Aggressive renewable energy goals

33% by 2020 60% by 2030

  • Deep greenhouse gas (GHG) reduction goals

2020 Target Reduce GHG emissions to 1990 levels 2030 Target 40% below 1990 levels 2050 Target 80% below 1990 levels

  • Robust electric vehicles goal: 1.5 million by 2025

100% 0-carbon by 2045

  • 12,000 MW of distributed generation by 2020;
  • 1.3 GW of battery storage by 2024
slide-5
SLIDE 5

California procurement landscape is changing rapidly

  • Significant changes to local RA procurement (D.19-02-

022)

– Three years forward requirements (100%, 100%, 50%) – PG&E Other” local area requirements now disaggregated

  • Proposal in Assigned Commissioner and ALJ ruling in

IRP on 6/20/19 (R.16-02-007)

– RFO for each LSE to procure share of 2,000 MW new peak capacity online by 8/1/21 – Potentially extend of one or more OTC units – Require SCE to solicit 500 MW of capacity from existing resources without a contract past 2021

Page 5

slide-6
SLIDE 6

California’s transition to a central buyer

  • Community Choice Aggregation

– Government entity formed by cities and counties that assumes the load-serving responsibilities for its constituents – Chooses the electricity generation mix on behalf of its consumers without having to own the wires/infrastructure to move electricity

  • Challenges of the “load migration” to CCAs

– IOUs don’t want to buy capacity for load they will not serve – No longer large LSE capable of buying grid-scale renewable resources needed for state to achieve its energy policy goals – CCAs may have distinct preferences about how best to serve load

Page 6

slide-7
SLIDE 7

Roles and obligations of a central buyer

  • Ensures state has an entity to procure resources given

transition to many small LSEs

  • Could be an IOU, state-run or state-overseen entity
  • A central buyer can have various roles and obligations,

depending on policy objectives:

– Full vs. residual procurement – Procurement of different capacity types (system, local, and flexible) – Procurement only or also act as a market participant – Procurement duration (one year or up to 10)

Page 7

slide-8
SLIDE 8

CAISO is proposing to assess only RA portfolio to test adequacy under various load and net load conditions

  • Provides greater certainty that a broad mix of resources

can meet CAISO operational needs

– Including thermal, hydro, wind, solar, energy and availability limited resources, distributed energy resources

  • CAISO must assess how the shown RA fleet works

collectively to meet system needs

– Similar in concept to the collective deficiency test the CAISO conducts for local RA – Some resources may be more “effective” in ensuring reliable

  • perations under different scenarios
  • Must balance modelling complexity with CAISO
  • perational needs

Page 8