Reay Creek Remediation Project September 22, 2013 Reay Creek is a - - PowerPoint PPT Presentation

reay creek remediation project
SMART_READER_LITE
LIVE PREVIEW

Reay Creek Remediation Project September 22, 2013 Reay Creek is a - - PowerPoint PPT Presentation

Reay Creek Remediation Project September 22, 2013 Reay Creek is a fish bearing stream that runs through the airports east industrial area, though Sidney and then drains into Bazan Bay. Early in 2012, the VAA approved $230,000 to remediate


slide-1
SLIDE 1

Reay Creek Remediation Project

September 22, 2013

slide-2
SLIDE 2

Reay Creek is a fish bearing stream that runs through the airport’s east industrial area, though Sidney and then drains into Bazan Bay. Early in 2012, the VAA approved $230,000 to remediate Reay Creek. Primary goals of this project are to:

  • Reduce heavy metal and other pollutant

concentrations in storm water runoff

  • Incorporate fish and riparian habitat features for

potential fish habitat restoration in upper Reay Creek in the future

  • Improve water quality while limiting bird and wildlife

conflicts with the airport

  • Provide for emergency storage to limit the impact of

contaminant spills or other emergent events

slide-3
SLIDE 3
slide-4
SLIDE 4
  • Testing for cadmium and other heavy metals from various
  • utfalls took place over the course of several years. Storm drains

and pipes were cleaned and testing continued.

  • In late January of 2012, the initial concept of the Reay Creek

remediation project was formed and core samples from the proposed location where taken.

  • Letters of support were rallied from community stakeholders.
  • An RFP for design/build was issued.
  • Required permits and approval were obtained from the

department of fisheries and oceans.

Work undertaken prior to the Project

slide-5
SLIDE 5

The project design team was led by Kerr Wood Leidal Associates Ltd. with SLR Consulting Ltd. and Murdoch de Greef Inc., providing environmental and landscape consulting, respectively. Draycor Construction Ltd. was the lead construction contractor.

slide-6
SLIDE 6

Work begins in August of 2012

slide-7
SLIDE 7

Work is well underway.

slide-8
SLIDE 8

Water control gates were installed at the wetland’s outlet as a protective measure to capture any unforeseen contaminant spills should they occur During construction, contaminated materials from the existing creek channel were removed.

slide-9
SLIDE 9

Work was substantially complete by the end of October, 2012

slide-10
SLIDE 10

Spring of 2013

slide-11
SLIDE 11
slide-12
SLIDE 12

Great Community Impact

slide-13
SLIDE 13
slide-14
SLIDE 14

James Bogusz

Director Airside Operations, Technology and

Environment

Victoria Airport Authority james.bogusz@victoriaairport.com 250-953-7570