reay creek remediation project
play

Reay Creek Remediation Project September 22, 2013 Reay Creek is a - PowerPoint PPT Presentation

Reay Creek Remediation Project September 22, 2013 Reay Creek is a fish bearing stream that runs through the airports east industrial area, though Sidney and then drains into Bazan Bay. Early in 2012, the VAA approved $230,000 to remediate


  1. Reay Creek Remediation Project September 22, 2013

  2. Reay Creek is a fish bearing stream that runs through the airport’s east industrial area, though Sidney and then drains into Bazan Bay. Early in 2012, the VAA approved $230,000 to remediate Reay Creek. Primary goals of this project are to: • Reduce heavy metal and other pollutant concentrations in storm water runoff • Incorporate fish and riparian habitat features for potential fish habitat restoration in upper Reay Creek in the future • Improve water quality while limiting bird and wildlife conflicts with the airport • Provide for emergency storage to limit the impact of contaminant spills or other emergent events

  3. Work undertaken prior to the Project • Testing for cadmium and other heavy metals from various outfalls took place over the course of several years. Storm drains and pipes were cleaned and testing continued. • In late January of 2012, the initial concept of the Reay Creek remediation project was formed and core samples from the proposed location where taken. • Letters of support were rallied from community stakeholders. • An RFP for design/build was issued. • Required permits and approval were obtained from the department of fisheries and oceans.

  4. The project design team was led by Kerr Wood Leidal Associates Ltd. with SLR Consulting Ltd. and Murdoch de Greef Inc., providing environmental and landscape consulting, respectively. Draycor Construction Ltd. was the lead construction contractor.

  5. Work begins in August of 2012

  6. Work is well underway.

  7. Water control gates were installed at the wetland’s outlet as a protective measure to capture any unforeseen contaminant spills should they occur During construction, contaminated materials from the existing creek channel were removed.

  8. Work was substantially complete by the end of October, 2012

  9. Spring of 2013

  10. Great Community Impact

  11. James Bogusz Director Airside Operations, Technology and Environment Victoria Airport Authority james.bogusz@victoriaairport.com 250-953-7570

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend