PYRO PROCESS UNIT Adnan Can Optimization & Capacity Upgrade - - PowerPoint PPT Presentation
PYRO PROCESS UNIT Adnan Can Optimization & Capacity Upgrade - - PowerPoint PPT Presentation
PYRO PROCESS UNIT Adnan Can Optimization & Capacity Upgrade Capacity Upgrade of an Existing Clinker Production Line, Nuh Cement Evaluation of the Existing Conditions Clinker Cooler Refrofit Cooler Vent Fan Replacement Preheater Cyclone
Evaluation of the Existing Conditions Clinker Cooler Refrofit Cooler Vent Fan Replacement Preheater Cyclone Modifications Kiln Feed System Modification
Capacity Upgrade of an Existing Clinker Production Line, Nuh Cement
01-EVALUATING THE EXISTING CONDITIONS
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Evaluating the Existing Conditions of the 1st Line
Capacity : 2700-2800 tpd Specific Heat Consumption : 850-870 kcal/kg clinker Standard Cooler Loss : 140 kcal/kg clinker Clinker Temperature : 170°C + ambient Tertiary Air Temperature : 715°C
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Evaluating the Existing Conditions of the 1st Line
Pressure Drop at PH-Tower Exit : 82-84 mbar ID Fan Power Consumption : 12-13 kWh/t clinker Cooler Vent Fan Power Consumption : 2,5 kWh/t clinker Kiln Feeding System : Pneumatic Total Power Consumption of Kiln : 31 kWh/t clinker 01-EVALUATING THE EXISTING CONDITIONS
02- CLINKER COOLER
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 1# Clinker Cooler Reftrofit Scope of Work
Complete Cooler Internals Cooler Casing Clinker Cooler (Roller Crusher to be installed) New Cooler fans with Silencer, Motor and Drives Dismantling and Erection Works Supervision, Commissioning and Training
03- COOLER VENT FAN
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 2# Cooler Vent Fan Replacement
The fan rotor to be replaced with state-of-the-art design fan Complete procurement, dismantling and erection is in the scope 1 kWh/t clinker to be reduced
03- PREHEA TER CYCLONE MODIFICA TION
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 3# Preheater Cyclone Modification Guaranteed Values
Capacity : 3200 tpd Preheater Tower Pressure : 69 mbar at 3200 tpd Energy Consumption Saving : 2 kWh/t clinker Specific Heat Consumption : 790 kcal/kg clinker
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 3# Preheater Cyclone Modification Scope of Work
8 cyclones (O1A, O1B, O2, O3 & V1A, V1B, V2 and V3) to be modified together with riser ducts Dip tubes, splash boxes, meal flaps Complete manufacture, dismantling and erection Commissioning, Training and Optimization 03- PREHEA TER CYCLONE MODIFICA TION
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 3# Preheater Cyclone Modification / Existing Cyclones
Preheater String 1# O2 & O3 Cyclones 03- PREHEA TER CYCLONE MODIFICA TION 03- PREHEA TER CYCLONE MODIFICA TION
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 3# Preheater Cyclone Modification / Modified Cyclones
Preheater String 1# O2 & O3 Cyclones 03- PREHEA TER CYCLONE MODIFICA TION
04- CFD ANAL YSIS OF THE MODIFIED CYCLONE
CFD Analysis of the Modified Cyclones
Before the modification After the modification
Static Pressure Distribution
Before Modification : 2436 Pa After Modification : 1657 Pa
Before the modification After the modification
CFD Analysis of the Modified Cyclones
Tangential Velocity Distribution
04- CFD ANAL YSIS OF THE MODIFIED CYCLONE
Before the modification After the modification
CFD Analysis of the Modified Cyclones
Axial Velocity Distribution
04- CFD ANAL YSIS OF THE MODIFIED CYCLONE
05- CFD ANAL YSES RESUL TS FOR 2
NDST
AGE
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
1657 Pa 2603 Pa 1788 Pa
Phase 3# Preheater Cyclone Modification / CFD Analyses Results for 2nd Stage
Nuh Cement Plant, Turkey
STATIC PRESSURE TOTAL PRESSURE Existing Cyclone Simple Modification Existing Cyclone Simple Modification
2436 Pa
06- NUH CEMENT PLANT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
07- KİLN FEED SYSTEM MODİFİCATİON
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Phase 4# Kiln Feed System Modification Scope of Work
Pneumatic Feeding System to be replaced with mechanical method (bucket elevator, airslide) Basic and Detailed Engineering Complete set of equipment Steel structure and manufacture All erection, commissioning, supervision and training
08- MODIFICA TIONS A T NUH CEMENT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
09- OVERALL GUARANTEES OF ALL PROJECT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Overall Guarantees of All Project
Capacity : 3200 tpd Specific Heat Consumption : 790 kcal/kg clinker Energy Consumption : 26 kWh/t clinker Energy Consumption Saving : 5 kWh/t clinker Clinker Temperature : 65°C + ambient
10- ACHIEVED V ALUES
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Achieved Values
Capacity : 3400 tpd Specific Heat Consumption : 750 kcal/kg clinker Energy Consumption : 24 kWh/t clinker Energy Consumption Saving : 7 kWh/t clinker Clinker Temperature : 55°C + ambient
11- BEFORE AND AFTER
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Nuh Cement Plant, Turkey
Evaluation of the Existing Conditions Raw Meal Drying and Grinding Unit Kiln De-Dusting Unit Pyro Process Unit
Ongoing Capacity Upgrade Project of an Existing Clinker Production Line, Gazakh Cement Plant
11- GAZAKH CEMENT PLANT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Evaluating the Existing Conditions
Capacity : 2500-2700 tpd Specific Heat Consumption : 870 kcal/kg clinker Raw Mill Capacity : 205 tph Fineness of the Mill Product :≥15.5% R90µm Separator Efficiency : 75%
12- RAW MEAL DRYING AND GRINDING UNIT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Raw Meal Drying and Grinding Unit Scope of Work
New drying equipment for the raw meal Complete replacement of the separator and cyclones New Raw Mill Fan complete with motor and drive New raw meal transport unit Raw meal weighing unit modifications Complete procurement, dismantling and erection Supervision, commissioning and training
13- KILN DE-DUSTING UNIT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Kiln De-Dusting Unit Scope of Work
Bag Filter modifications New Bag Filter Fan with motor and drive Complete procurement, dismantling and erection works Commissioning, Training and Optimization
14- PREHEA TER UNIT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Preheater Unit Scope of Work
Preheater cyclone modifications TA Duct and Calciner connection modification New dip tubes, riser ducts and splash boxes New ID Fan, complete with motor and drive Complete manufacture, dismantling and erection Commissioning, Training and Optimization
15- GUARANTEES
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Overall Guarantees of All Project
Production Capacity : ≥240 tph Mixed Raw Material Moisture : Max 8% Mixed Raw Material Feed Size : 90% <25 mm Raw Meal Moisture Content : ≤1% Separator Efficiency : ≥85%
Raw Mill Unit
15- GUARANTEES
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Overall Guarantees of All Project
Clinker Production Capacity : ≥3300 tpd Heat Consumption : ≤765 kcal/kg clinker Preheater Pressure Drop : ≤60 mbar ID Fan Power Consumption : 9 kWh/t clinker Top Stage Cyclone Efficiency : 93%
Rotary Kiln Unit
15- GUARANTEES
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Overall Guarantees of All Project
Free Lime : ≤1.5% (daily avg.) C3S : ≥55 (Std. Bogue formula) LSF : 93-97 Silica Ratio : 2.0 - 2.8 Al2O3 : 1.0 – 1.8 New Process Fans’ Efficiency : ≥80%
Quality Parameters
16- HIGHLIGHTS OF THE PROJECT
Lorem ipsum dolor sit amet, consectetur adipiscingelit.
Gazakh Cement Plant, Azerbaijan
Supply of the equipment will be at 6 months Flame-off flame-off period is planned to be 35 days
Highlights of the Project