Puyallup Parking and Access Project
Motion No. M2019-110
11/21/2019
Puyallup Parking and Access Project Motion No. M2019-110 - - PowerPoint PPT Presentation
Puyallup Parking and Access Project Motion No. M2019-110 11/21/2019 Puyallup Parking and Access Improvements Project Overview 510 space parking structure 167 surface parking lot Pedestrian bridge over 5 th Ave will provide
11/21/2019
2
Project Overview
access to the station area.
Design Build Contract Award
3 Shared Use Path Sharrows ST Access Grant
4
Puyallup River Trail Red Lot City implemented Access Improvements ST Access Grant City Active Transportation Plan
5
2012-15 2016 2017 2018 2019 2020 2021 2022 2023 2024
Open for Service PE and Environmental Documentation Right Of Way Acquisition Design, Construction and Testing Baseline Project Design Build Procurement Project to Build Third Party Agreements
6
Puyallup Station Improvements: Baseline Budget $79.1M
ALLOCATION $ COMMITMENTS
$79.1M Proj. Dev. Design Build
Illustrative - Not to Scale
Approved Today’s Action Future Action
7
Puyallup Station Improvements: Baseline Budget $79.1M
ALLOCATION $ COMMITMENTS
$79.1M Proj. Dev. Design Build
Illustrative - Not to Scale
Approved Today’s Action Future Action