puhoi area
play

Puhoi Area October 2014 Background The Puhoi region is supplied by - PowerPoint PPT Presentation

Vector Network Reliability Puhoi Area October 2014 Background The Puhoi region is supplied by two HV feeders; the Waiwera feeder which originates from Orewa (brown) and the Satelite which comes from Warkworth (red). Each feeder exceeds


  1. Vector Network Reliability Puhoi Area October 2014

  2. Background The Puhoi region is supplied by two HV  feeders; the Waiwera feeder which originates from Orewa (brown) and the Satelite which comes from Warkworth (red). Each feeder exceeds 100km in length and  is predominantly overhead. Both feeders are classified as rural, in total  they supply 2,021 connections.

  3. Puhoi Village The two feeders meet at the Puhoi Village, the  Southern end is supplied by the Satellite feeder and the Northern end receives power from Waiwera. There is an 'open point' between the feeders, this  can be closed to allow power to be back-fed when required. Each side experiences different outages. 

  4. Service Levels The level of service we are able to provide  depends on where you live. Urban homes have fewer faults on average  and are shorter in duration than rural feeders This is due to the length and exposure of  rural overhead lines and a number of factors that are largely outside our control such as: Severe weather conditions • Bird strikes • Car vs pole accidents • Vegetation •

  5. Unplanned Outage Causes Note: 38% of faults on the Northern end and 57% of faults on the Southern end occurred during storm periods.

  6. Unplanned Outage Durations

  7. Distribution of Outages - Count This plot shows the distribution and count of  fault outages over the last two years. Puhoi is near the end of both feeders so  unfortunately experiences relatively poor reliability. Outage counts over the last 12 months have  been high, largely due to the four major storms earlier this year; 14-17 March • 17-20 April • 10-16 June • 8-12 July •

  8. Distribution of Outages - Duration This plot shows the cumulate duration of all  fault outages over the last two years. Values are in hours.

  9. Preventative Maintenance Vector has a comprehensive preventive maintenance  program with standards regarding; Inspection Tasks. • Test Activities. • Maintenance Servicing. • Condemned Pole Assessment. • Feeder maintenance and replacement tasks are driven  by asset condition and risk. There have been 6 HV outages caused by conductor failure on the • spur line to Wenderholm Regional Park from 2011 to 2014. We have recently completed a conductor replacement exercise removing the problematic 16mm Cu conductor. In addition, Wenderholm is locked after-hours with no vehicle • access to patrol/repair the line. Over the coming months we plan to install additional DDOs (fuses) before the line enters the park, splitting the protection on this spur line and improving restoration times. New inspection technologies are constantly being  assessed. New-generation ultrasonic pole surveys were introduced in 2013.

  10. Tree Trimming At least 1/3 (& up to 3/4) of all faults* are vegetation-related.  Vector has a Regulatory obligation to maintain safety clearance distances around electricity lines.  Tree owners have regulatory obligations to trim their trees in accordance with these safety clearances As part of our historical tree inspection cycle, Vector last undertook network inspections, issued CTNs  and then trimming in: 38SATE: 2006/2011/underway • 26WAIW: 2009/2013/underway • Our 2014 feeder tree survey’s identified two sets of works:  Trees currently breaching Regulatory clearance distances from electricity lines • − Tree owners (private or Council) will be issued with regulatory Cut Trim Notices to restore clearances (at their cost) 38SATE: Private: 24 sites = 145 trees & Council: 7 sites = 63 trees  26WAIW: Private 17 sites = 159 trees & Council: 5 sites = 15 trees  − Where these are ‘first cuts’ Vector will be undertake the works for the tree owner (at our cost) 38SATE: 14 sites  26WAIW: 6 sites  Trees that pose a risk to the network (outside of regulatory safety clearance distances) • − Identified trees that have a high-risk of causing a fault due to: flying debris/broken branches, tree fall hazard − We will be liaising with each private tree owner to agree trimming or removal requirements, and Vector will contribute to the cost depending on what is agreed. 38SATE: Private: 5 sites = 67 trees  26WAIW: Private: 25 sites = 155 trees  Tree owners will start receiving letters soon, and we request they contact the Treescape liaison person detailed on the  letter to work through the detail of the tree trimming works required. * 33% of faults were verified as vegetation issues. In addition 40% of faults were ‘transient’ - a high proportion of them will be vegetation related.

  11. Protection Scheme Review Protection systems do not prevent feeder  faults, but do minimise their impact. Both feeders supplying Puhoi have  sophisticated, multi-tiered systems including automated devices and numerous HV switches and fuses. The feeders are being reviewed to further  refine the system and leverage technological developments. Additional fuses, sectionalising fuses and  isolation points will be installed at optimal locations.

  12. Electrical Safety General Report any hazards to 0508 VECTOR (0508 832 867).  Broken lines - Treat all power lines as live at all times and keep everyone well clear  of the area. Arcing/sparking Equipment – Keep clear, report immediately.  Car vs Pole - If lines are down stay in the car until help arrives. If forced to  evacuate, jump clear. Do not to touch the vehicle and the ground at the same time. Working Safely Minimum safe work distances;  >4m from OH lines • >5m from a pole when digging • A close approach consent is required to work closer. High Loads - You must apply for a high load permit if you plan to move any tall  structure such as a house or a boat. If you are unsure about anything before you start any work near our networks call  0508 VECTOR (0508 832 867) or visit www.vector.co.nz and download ‘A guide for working safely’.

  13. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend