SLIDE 1 PUBLIC SERVICES AREA
CRAIG HUPY, AREA ADMINISTRATOR CHUPY@A2GOV.ORG
SLIDE 2 PUBLIC SERVICES AREA
Public Services Units
*Wastewater Treatment Plant
*Systems Planning *Engineering Water Treatment Plant Public Works
SLIDE 3 WASTEWATER TREATMENT SERVICES
EARL J. KENZIE, P.E., MANAGER EKENZIE@A2GOV.ORG
SLIDE 4
WASTEWATER TREATMENT SERVICES
Contact: 49 Old Dixboro Road Ann Arbor, MI 48105-9405 (734) 794-6450 Overview History Major Capital Projects Treatment Processes Challenges
SLIDE 5 WASTEWATER TREATMENT SERVICES STAFF
33 Full Time Employees
Manager
1 position
Assistant Manager
1 position
WWTS Engineer
1 position
Water Utility Supervisor
5 positions
Maintenance Supervisor
1 position
Water Utility Technician
17 positions
SCADA Administrator
1 position
Inventory Control Technician
1 position
Administrative Assistant
2 positions
Electrical/Control Systems Technician
3 positions
SLIDE 6
Wastewater Treatment Services Operating Budget: $15,269,985 Operate and maintain the wastewater treatment system; including the Wastewater Treatment Plant, eight sewage lift stations and industrial pretreatment program.
SLIDE 7 WASTEWATER TREATMENT SERVICES OVERVIEW
Geddes Rd. US 23 Old Dixboro Rd.
Located in Ann Arbor Township
SLIDE 8 WASTEWATER TREATMENT SERVICES OVERVIEW
Services Ann Arbor Township, Scio Township, and Pittsfield Township in addition to the City
Services approximately 130,000 people Staffed 24/7 by certified, trained technicians Operations regulated by State and Federal agencies Permitted capacity at 29.5 mgd Average daily flow is 18.4 mgd
SLIDE 9
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 10
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 11
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 12
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 13
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 14
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 15
WASTEWATER TREATMENT SERVICES HISTORY
SLIDE 16
WASTEWATER TREATMENT SERVICES HISTORY
Old West Plant – 9.5 mgd 1936 – 1964 Newer East Plant – 20 mgd 1977
SLIDE 17 RESIDUALS HANDLING IMPROVEMENTS
Construction Schedule
Start: February 2009 Completion: June 2012
Construction Budget
Approximately $45.5 million
ACEC Awards
MI Engineering Honorable Conceptor Award – 2013 National Recognition Award - 2013
SLIDE 18
GRAVITY BELT THICKENER
SLIDE 19
SOLIDS HANDLING BUILDING
SLIDE 20
TRUCK LOADING FACILITY
SLIDE 21 FACILITIES RENOVATIONS PROJECT
Construction Schedule
Start: June 2012 Completion: August 2017
Construction Budget
Approximately $100 million
ASCE Awards
MI Section Outstanding Civil Engineering Award – 2017 SE MI Outstanding Civil Engineering Project of the
Year Award - 2017
SLIDE 22 FACILITIES RENOVATIONS PROJECT
FRP Objectives
Replacement of West Plant Plant-wide Infrastructure Rehabilitation Improvements to East Plant
Complex Design and Construction
Six years to complete design Five plus years to construct Numerous regulatory and site challenges
SLIDE 23 FACILITIES RENOVATIONS PROJECT STATE FUNDING
State Revolving Fund
$110,305,000 in State Revolving Fund low interest loan with deferred
repayment
$2,592,168 in loan principal forgiveness for green project features $256,153 grant for reimbursement of engineering design fees
Michigan Department of Treasury
Estimated $1.5 M savings from sales tax exemption for contractor
purchases
SLIDE 24
WEST PLANT DEMOLITION
SLIDE 25
UTILITIES DUCT BANK
SLIDE 26
CLARIFIER WALL CONSTRUCTION
SLIDE 27
PRECONSTRUCTION AERIAL VIEW
SLIDE 28
AERIAL VIEW – AUGUST 2013
SLIDE 29
POST CONSTRUCTION AERIAL VIEW
SLIDE 30
FACILITIES RENOVATIONS PROJECT
SLIDE 31 WASTEWATER TREATMENT PROCESSES
Liquid Treatment
Primary
Physical
Secondary
Biological
Chemical
Physical
Tertiary
Physical
Disinfection
Ultra-violet (UV)
Solids Removal
Screenings
Grit
Fats, oils & grease (FOG)
Biosolids
Lime stabilization and subsurface land application
Centrifuge dewatering and landfill disposal
SLIDE 32
BIOSOLIDS CENTRIFUGE
SLIDE 33
CENTRIFUGED BIOSOLIDS
SLIDE 34
LAND APPLICATION OF LIQUID BIOSOLIDS
SLIDE 35
WASTEWATER TREATMENT SERVICES CHALLENGES
Single Access Rd. Fleming Creek Huron River Active RR Track
SLIDE 36
WASTEWATER TREATMENT SERVICES CHALLENGES
NPDES Permit Requirements Odor Management Long-term Biosolids Management Strategy Energy Management to Increase Sustainability Succession Planning to Ensure Knowledgeable Workforce Aging Infrastructure Changing Federal or State Regulations