Public Meetings
January 2016
Public Meetings January 2016 Agenda Welcome and Introductions - - PowerPoint PPT Presentation
Public Meetings January 2016 Agenda Welcome and Introductions Project update Process Project definition Key environmental findings Key traffic analysis findings Related activities Bike/pedestrian projects 15L
January 2016
Agenda
3
What is the purpose of this project?
To identify and provide a package of multi- modal transportation improvements in the East Colfax corridor that:
transportation corridors, systems, and modes
components of federal sustainability & livability plans and principles
5
Maximum number of cars on a street Distribution of people served by these cars The same number of people on a bus The same number of people
Previous Studies and Plans
6
CCD Strategic Transportation Plan, 2008
corridor by 2025
CCD Colfax Streetcar Feasibility Study, 2010
use ~30,000 riders per day
~22,000 riders per day
Colfax Corridor Connections Study
during peak periods
7
Stakeholders and Public Involvement
8
Project Stakeholders & Team
9
Public Involvement Activities
buses
10
Initial Feedback on BRT Concept
analysis
Constrained with FasTracks, which is their current priority
11
Public Meeting Feedback:
12
Several hundred comments submitted
Most cited benefits of BRT were:
Most cited areas where more information was desired were:
13
specifics of project with partners
What’s Happened Since the Last Public Meetings?
How Did We Get Here?
What’s the study area for this project?
10 miles
Why is This Project Needed?
(2010 to 2035) (2010 to 2035)
*ridership includes 10, 20, and 15 & 15L
(2010 to 2035) (2010 to 2035)
* *
Why is This Project Needed?
Mode/Technology Options Considered
Roadway Expansion Enhanced Bus Bus Rapid Transit Light Rail Modern Streetcar Automated Guideway Transit Monorail MagLev Commuter Rail Heavy Rail (Metro) Gondola Personal Rapid Transit
Route/Alignment Options
centers
adopted plans
change’
commercial & mixed-use
Colfax Avenue - Route Recommended to Advance
13th/14th Colfax 17th 20th/ Montview Enhanced Bus Bus Rapid Transit Modern Streetcar Light Rail
* Other transportation improvements (bike, pedestrian, etc.) are components of all options
21
Locally Preferred Alternative: Bus Rapid Transit in Exclusive Lanes During Peak Hours
23
Project definition
Project definition
24
Exclusive lanes (replacing general purpose lanes) during peak periods between Broadway (and the Civic Center Station) in downtown Denver and Syracuse Street in east Denver, a distance
Exclusive lanes would continue to allow right-turns for autos and would also allow crossing for parking adjacent to the lanes.
25
Project definition Extent of improved service frequencies and stop enhancements: I-25 to I-225
26
Project definition Extent of peak-period exclusive lanes: Broadway to Syracuse
Project definition
27
Branded service with low-floor articulated buses the 10-mile length of the corridor.
Project definition
28
Five-minute peak-period headways the entire length of the 10- mile corridor.
Project definition
29
Twenty enhanced passenger stations throughout the corridor with real-time passenger information, off-vehicle ticketing, and other passenger amenities. Stops will consist of curb extensions where appropriate (primarily in current bus stop location with minimal parking loss) and on- sidewalk curbside enhancements where curb extensions are not appropriate.
Example BRT Before/After Concept
35
Bus Rapid Transit: How It Addresses Corridor Needs
More than doubles ridership of current bus service…
Up to 50,000 Daily Riders
Bus Rapid Transit: How It Addresses Corridor Needs
Increases person-trips potential by 25%…
40
Bus Rapid Transit: How It Addresses Corridor Needs
End-to-end transit travel time change
More Information at meeting station….
Already heavily used urban transportation corridor Minimal to no impacts (and many benefits) in most federal resource areas Categorical exclusion document being prepared under guidance of Federal Transit Administration Anticipated completion spring 2016
Key environmental issues and findings
More Information at meeting station….
Bus Rapid Transit: Traffic Takeaways
Congestion occurs today and will get worse in the future with or without the project Traffic diversion occurs today and will get worse in the future with or without the project Some shift from autos to transit due to improved travel times and convenience Appropriate operational improvements at hot spots as necessary BRT increases person-trip capacity by up to 25%
Bus Rapid Transit: Traffic Methodology
Traffic Analysis used two separate types of models
ridership forecasting
specific intersection analysis
VISSIM evaluated specific intersection operations along Colfax Synchro evaluated select intersections adjacent to Colfax (such as 13th, 14th, etc.) Analysis conducted with and without the project
Bus Rapid Transit: Traffic Findings
Many streets see only a minor increase in delay/congestion Regardless of project, some intersection hot spots become apparent For corridor hot spots, we have identified potential operational improvements:
relocation (all within ROW)
Currently developing package of operational improvements using Synchro model to see which are most effective to meet the goals
More Information at meeting station….
Bike/Pedestrian Access
Bike/Ped access has been a key component of the BRT project from the beginning. We are identifying short term opportunities for pedestrian and bicycle improvements that support the larger Colfax bus rapid transit (BRT) project
More Information at meeting station….
Short-term opportunity to improve transit on Colfax while still working toward long-term goal of implementing BRT
15L Improvements
More Information at meeting station….
More Information at meeting station….
How BRT Meets Project Goals:
economic development
Spring 2016:
Bicycle/pedestrian improvement coordination Complete detailed traffic analysis Complete details on short-term 15L enhancements Complete environmental clearance
2016-2017:
Begin design phase Compete for federal funding Identify local/regional funding sources
2019-2020:
Complete design Federal funding in place Target to start construction
2021-2022: Target for project Implementation
Questions?