Public Involvement Meeting May 6, 2014 Presentation outline - - PowerPoint PPT Presentation

public involvement meeting
SMART_READER_LITE
LIVE PREVIEW

Public Involvement Meeting May 6, 2014 Presentation outline - - PowerPoint PPT Presentation

Public Involvement Meeting May 6, 2014 Presentation outline Introductions Town Hall meetings Forward progress Project improvements and schedule Noise barriers Roundabouts and Diverging diamond interchange Community


slide-1
SLIDE 1
slide-2
SLIDE 2

Public Involvement Meeting

May 6, 2014

slide-3
SLIDE 3

Presentation outline

  • Introductions
  • Town Hall meetings
  • Forward progress
  • Project improvements and schedule
  • Noise barriers
  • Roundabouts and Diverging diamond interchange
  • Community sensitive solutions
  • Community outreach and business resources
slide-4
SLIDE 4

Introductions

  • WIS 441 Tri-County Project team

− Will Dorsey, Northeast Region Director − Brian Roper, Project Chief − Chad DeGrave, Design Supervisor − Tammy Rabe, Construction Supervisor − Scott Ebel, Project Manager − Paul Vraney, Design Project Manager − Tom Buchholz, Construction Project Manager − Kathleen Slattery, Deputy Project Manager − Eric Sikorski, Deputy Project Manager − Mark Kantola, Communication Manager

slide-5
SLIDE 5

Transportation Moves Wisconsin

Town Hall meetings

  • Meetings to provide an opportunity to get

information and share your thoughts on how transportation impacts your life each day

  • Submit comments online dot.wisconsin.gov

Green Bay May 7

5-6:30 p.m. US 41 Project Office, 1940 West Mason St

Oshkosh May 8

5-6:30 p.m. UW Alumni and Conference Center, 625 Pearl Ave

slide-6
SLIDE 6

Forward progress

  • Construction schedule acceleration
  • Field office

− Permanent presence − Public / business involvement

slide-7
SLIDE 7

Project improvements-overview

Reconstruct 5 interchanges and add missing movements at US 41

slide-8
SLIDE 8

Project improvements-overview

Replace 6 miles of mainline pavement, expand to 6 lanes

slide-9
SLIDE 9

Project improvements-overview

Improve design speed of roadway curves

slide-10
SLIDE 10

Project improvements-overview

Construct a second parallel bridge over Little Lake Butte des Morts

slide-11
SLIDE 11

Project improvements-overview

Revise interchange control

slide-12
SLIDE 12

Project improvements-overview

Add auxiliary lanes along US 41 for system interchange

  • peration
slide-13
SLIDE 13

New items / refinements

  • Refined since

summer 2013:

− Box culverts − Bridge abutments − Fill areas − Locations and shapes of stormwater detention basins − US 41 mainline shoulder reconstruction − Real estate acquisition − Retaining walls

slide-14
SLIDE 14

Function 2012 2013 2014 2015 2016 2017 2018 2019 Design Real Estate Utilities Construction

Note: Yellow indicates schedule update Timelines are subject to change

Project schedule

slide-15
SLIDE 15
  • Traffic impacts

− Nighttime lane closures − Ramp closures

  • Changeable

message boards

− News / media alerts − Website

Construction

slide-16
SLIDE 16
  • Recognizing work zones
  • Driving
  • Consequences

− Fines, prison, injuries/fatalities − Slow down − Follow the law − Put your cell phone away − Expect the unexpected − Plan ahead − Flashing lights − Orange signs − Barrels and flags

Work zone safety

slide-17
SLIDE 17

US 41 interchange and US 41 mainline Mainline construction: 2018 Interchange construction: 2014-2018

Project schedule

US 41 grading work is advanced to start this summer

slide-18
SLIDE 18

US 41/WIS 441 interchange (north)

  • Reconstruct US

41/ WIS 441 system interchange

  • Free-flow

movements all directions

  • Freeway split for

US 10 WB and WIS 441 SB

  • Add auxiliary

lanes on US 41

2014 - 2018

slide-19
SLIDE 19

Construction

May 2014 let

Structures Grading Roadway

2014 - 2015

slide-20
SLIDE 20

US 41/WIS 441 interchange

(south)

  • Add auxiliary lanes on

US 41 to County II interchange

2018

slide-21
SLIDE 21

Little Lake Butte des Morts crossing New bridge construction: 2014-2016 Existing bridge rehab: 2016-2018

Project schedule

New bridge construction is advanced to start this fall

slide-22
SLIDE 22

Little Lake Butte des Morts structures

  • Construct 2nd parallel bridge over LLBDM
  • New concrete structure closely matches existing
  • Spans will vary from existing, more cost effective
  • Stain existing and new structures to match
  • Structures will have overhead bridge deck lighting
slide-23
SLIDE 23

2014 - 2016

(new bridge) Structures Grading Roadway

Construction

August 2014 let

slide-24
SLIDE 24

County P (Racine Road) interchange, WIS 441 mainline and Racine Road Construction: 2015-2018

Project schedule

slide-25
SLIDE 25

2015 - 2018

County P/Racine Rd interchange

  • Reconstruct

County P/ Racine Rd interchange

  • Reconstruct

mainline on new alignment

  • Expand to 6 lanes
  • Additional auxiliary

lanes

  • Improve design speed
  • f curve to 70 mph

Note: design alternatives currently under consideration

slide-26
SLIDE 26

County AP (Midway Road) interchange and WIS 441 mainline Construction: 2017-2018

Project schedule

slide-27
SLIDE 27

2017 - 2018

County AP/Midway Rd interchange

  • Reconstruct County AP/

Midway Rd interchange

  • Expand mainline on new

alignment

  • Improve design speed of

curve to 70 mph

slide-28
SLIDE 28

WIS 47 (Appleton Road) and US 10

(Oneida Street) interchange ramps and

WIS 441 mainline Construction: 2018-2019

Project schedule

slide-29
SLIDE 29

2018 - 2019

WIS 47/Appleton Rd interchange ramps

  • Reconstruct WIS 47/

Appleton Rd interchange ramps

  • Expand mainline on existing

alignment

Constructed in 2015

slide-30
SLIDE 30

WIS 47, US 10 interchange ramps and WIS 441 mainline

2018 - 2019

  • Reconstruct WIS

47/ Appleton Rd and US 10/Oneida St interchange ramps

  • Expand

mainline on existing alignment

slide-31
SLIDE 31

WIS 47 (Appleton Road) and Vermillion Street Construction: 2015

Project schedule

Planned 75-day CLOSURE of WIS 47 interchange in late spring 2015

slide-32
SLIDE 32

2015

WIS 47/Appleton Rd interchange

Update: Fully reconstruct Appleton Road south to Midway

  • Roundabouts
  • Bike and

pedestrian facilities

Planned 75-day CLOSURE of WIS 47 interchange in late spring 2015

slide-33
SLIDE 33

Project schedule

US 10 (Oneida Street) Construction: 2017

slide-34
SLIDE 34

2017 2015

US 10/Oneida St interchange

  • Construct a Diverging

diamond interchange at US 10/Oneida St

  • Enhance safety and

mobility with access changes

  • Meadow Grove Blvd

left-in/right-in/right-out

  • Primrose Ln right-in/

right-out

  • Extend Vermillion St to

Midway Rd

slide-35
SLIDE 35

2014 – 2015 construction preview

Construction Project 2014 - 2018 Reconstruct the US 41 interchange 2014 - 2016 Construct a new bridge across LLBDM 2015 - 2018 Reconstruct County P (Racine Rd) interchange, WIS 441 mainline and Racine Rd 2015 Reconstruct WIS 47 (Appleton Rd) and construct Vermillion St connection

slide-36
SLIDE 36

Next steps - real estate acquisitions

  • Business and residential

displacements

− identified on displays − Wisconsin’s relocation program

  • Re-establishment of

displaced persons and businesses

  • Prompt and reasonable

relocation payments

  • Fair market value
slide-37
SLIDE 37
  • Noise abatement criteria is set by

WisDOT’s Facilities Development Manual, Chapter 23, Noise

  • Existing, linear feet (LF):
  • Noise walls = 20,900 LF
  • To be replaced = 9,700 LF
  • Berm = 3,100 LF
  • Feasible and reasonable

barrier proposed = 4,800 LF

Noise analysis

slide-38
SLIDE 38

Existing noise wall locations Existing berm Feasible and reasonable noise walls

Noise analysis results

slide-39
SLIDE 39
  • Hold public meeting(s) with potentially

benefited residents

− Property owners and renters − Within 500 feet in any direction from the proposed noise barrier

  • Determine level of support for the proposed

noise barrier

− Ballots cast by owners or residents of benefited receptors − Simple majority of ballots

Noise analysis

Next steps

slide-40
SLIDE 40

Proposed roundabouts

Roundabouts & diverging diamond interchange

Proposed diverging diamond interchange Roundabouts no longer proposed

slide-41
SLIDE 41

Roundabouts

  • 10 percent fewer bicycle crashes
  • Fewer conflict points, meaning

fewer opportunities for crashes

Source: Insurance Institute for Highway Safety

  • 90 percent fewer fatal crashes
  • 76 percent fewer crashes with

injury

  • 30-40 percent reduction in

pedestrian crashes

slide-42
SLIDE 42

Roundabout outreach

  • Roundabout education

− www.wisconsinroundabouts.gov − “All about roundabouts” DVD − Wisconsin driver’s handbook brochure − Driver’s test – written exam question

slide-43
SLIDE 43

Diverging diamond interchange

Improved Safety and Capacity

  • Moves more traffic
  • Free-flow right and left

turns onto freeway

  • Reduces conflict points

by nearly half (14 vs 26)

Why a DDI?

  • Saves $3M compared

to RAB and standard signal alternatives

  • Better 2038 traffic level
  • f service than

alternatives (C v. D/E)

slide-44
SLIDE 44

Diverging diamond interchange

Easy navigation, guides drivers with:

  • Overhead signs
  • Pavement markings
  • Traffic signals

Meets the needs

  • f all road users
  • Large trucks
  • Pedestrians
  • Bicyclists

Widespread use

  • Built in over 9 states
  • Planned or considered

in at least 25 states

slide-45
SLIDE 45

Next steps – transportation management plans

Coordinate with taskforces, stakeholders along corridor

  • Enhance safety
  • Keep traffic moving during construction
  • Keep customers connected with businesses
slide-46
SLIDE 46

Next steps - design coordination

  • Interchange CSS meetings and

coordination meetings with municipalities − Ongoing

  • Neighborhood noise barrier meetings

− Begin summer/fall 2014

slide-47
SLIDE 47

WIS 441 CSS process

  • Assess project area, identify characteristics, develop

concepts (completed)

  • Stone concepts - Community leaders provide

preference (completed)

  • Color concepts - Community leaders provide

comment and preference (Completed)

  • Focused workshops with community stakeholders

(Underway)

slide-48
SLIDE 48

CSS recommendations

Junction 10/441 & 41 structures Structures east of LLBDM

slide-49
SLIDE 49

Bus shelter

CSS process

slide-50
SLIDE 50

Landscape concepts

CSS process

slide-51
SLIDE 51
  • Maintain trust and credibility within the community
  • Be the first and best source for project information
  • Seek public input at project milestones

Next steps - public outreach

slide-52
SLIDE 52
  • WisDOT will continue to

keep public informed

− Project web presence − Media outreach − Newsletters − Public meetings

  • Feedback

Communicating with you

www.us41wisconsin.gov/wis441

slide-53
SLIDE 53
  • Coordinate with businesses along corridor
  • Provide businesses with first hand information at milestones
  • Identify needs and concerns before and during construction

Next steps - business outreach

slide-54
SLIDE 54

Business resources

‘In this together’ kit

  • Partnership with businesses
  • Tools to maintain connection

with customers

− Print ad templates − Web banner ads − Web site button

slide-55
SLIDE 55

Business resources - signing

  • Early ‘heads up’ on temporary business signing
  • Signs should be coordinated

− Start thinking about coordinating with other area businesses − WisDOT will reach out to business closer to construction with more details

slide-56
SLIDE 56
  • Comment forms

− Submit today or via mail − Submit comments by May 27, 2014

  • Join project email list

− Provide email address on sign-in sheets − Send email to project staff

Communicating with you

slide-57
SLIDE 57

Questions?

slide-58
SLIDE 58