Pavement shows signs of distress. Bridges over Ashwaubenon Creek constructed in
1952 and 1956 need to be replaced.
Wingwalls on box culvert at Dutchmans Creek are
tipping.
Provide improvements that meet current WisDOT
design standards.
Address operational, physical, and safety concerns
along the highway.
SLIDE 4
Project Limits
Approximately 500-1000 feet north of 8th Street Roundabout to
Lombardi Avenue.
Resurfacing project. Concrete repair at intersections. Replace bridges over Ashwaubenon Creek. Replace box culvert wingwalls at Dutchmans
Creek.
Upgrade traffic signals to current standards.
SLIDE 5
Replace guardrail within project limits. Replace railroad crossing surface and signals. Access to property north of Vanderperren Way to
be updated.
Project to be constructed in 2017.
SLIDE 6
Road will be closed between Parkview Road and
Hansen Road for bridge construction.
WIS 32 traffic will be detoured to US 41. Ashland Avenue will reopen to through traffic after
bridge construction is complete.
Resurfacing work to be completed under single
lane closures.
Temporary side road closures for concrete repair
and signal upgrades.
SLIDE 7
Vanderperren Way Property
Add left turn lane for northbound and southbound lanes to the
south of the access point.
Access from driveway will be left in – right in – right out only. Southbound drivers can perform u-turn at Vanderperren Way
to go north.
SLIDE 8