Public Involvement Meeting #1 Autumn Ridge Path
(Milwaukee Street – Ziegler Road)
Public Involvement Meeting #1 Autumn Ridge Path (Milwaukee Street - - PowerPoint PPT Presentation
Public Involvement Meeting #1 Autumn Ridge Path (Milwaukee Street Ziegler Road) Introductions & Project Contacts Hannah Mohelnitzky Chris Dawson City of Madison Engineering City of Madison Engineering (608) 266-4093 Public
(Milwaukee Street – Ziegler Road)
Chris Dawson City of Madison Engineering (608) 266-4093 cdawson@cityofmadison.com Chris Petykowski, P.E. City of Madison Engineering (608) 267-8678 cpetykowski@cityofmadison.com Darren Fortney, AICP, LEED-GA SEH Inc. (608) 620-6191 dfortney@sehinc.com Hannah Mohelnitzky City of Madison Engineering Public Information Officer (608) 242-6003 hmohelnitzky@cityofmadison.com Alder Grant Foster City of Madison Common Council district15@cityofmadison.com
6:00 – 6:15 Open House 6:15 – 6:30 Welcome & Project Presentation 6:30 – 6:45 Q & A / Comments 6:45 – 8:00 Open House
– Benefits to the Community
– Pathway & Structures – Aesthetics & Lighting
– Design and Construction
Series of Paths and Low Volume Streets
Parks and Commercial Areas to Capitol City Path and Downtown
Typical Section
Structures, With Vertical Protection
Hiestand Park: 4(f) Resource Evaluation & Documentation:
Special consideration given to certain park lands and conservation areas as well as to National Register or Register eligible historic sites.
Pathway Lighting
– User Safety & Security – On “All” Night
Control Feature
– 3000K Color Temperature – 20-ft Poles
Fall 2019 – Winter 2020
Spring 2020
Spring 2021
Spring 2023
Anticipated Construction Costs
– $1.0 M (Path) – $3.2 M (Structure)
https://www.cityofmadison.com/engineering/projects/autumn-ridge-path
Subscribe for Email Updates
Comment Forms Please Return by November 22, 2019