public information meeting
play

Public Information Meeting WIS 48 (Knapp Street) Bear Paw Ave. to - PowerPoint PPT Presentation

Public Information Meeting WIS 48 (Knapp Street) Bear Paw Ave. to Hammond Ave. City of Rice Lake WisDOT Project I.D. 8120-04-30 March 7, 2017 Welcome & Introductions Agenda for Meeting Project Scope 4-Lane to 3-Lane Conversion


  1. Public Information Meeting WIS 48 (Knapp Street) Bear Paw Ave. to Hammond Ave. City of Rice Lake WisDOT Project I.D. 8120-04-30 March 7, 2017

  2. Welcome & Introductions

  3. Agenda for Meeting • Project Scope • 4-Lane to 3-Lane Conversion Information • Wisconsin Avenue Intersection • Hammond Avenue Intersection • Project Timeline • Construction Timeline • Questions & Comments Project ID 8120-04-30 March 7, 2017 Page 3

  4. Project Scope • Project Limits – Bear Paw Ave. to Hammond Ave. – Approximately 1 mile long • Proposed Improvements – Rehabilitate existing pavement – Convert existing 4-lane roadway to 3-lane roadway – Install right turn lane and traffic signal at Wisconsin Ave. – Reconstruct Knapp St. & Hammond Ave. Intersection – Install traffic signal at Knapp St. & Hammond Ave. Intersection – Install several sections of sidewalk throughout the corridor – Upgrade existing curb ramps to meet current standards Project ID 8120-04-30 March 7, 2017 Page 4

  5. Public Involvement Meeting #1 – January 22, 2015 • 4-Lane to 3-Lane conversion • Wisconsin Avenue intersection operation • Lowering the speed limit • Proposed sidewalk locations Project ID 8120-04-30 March 7, 2017 Page 5

  6. 4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 6

  7. 4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 7

  8. 4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 8

  9. 4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 9

  10. Wisconsin Avenue Intersection Project ID 8120-04-30 March 7, 2017 Page 10

  11. Hammond Avenue Intersection Project ID 8120-04-30 March 7, 2017 Page 11

  12. Project Timeline • Currently 70% plans are completed • Right-of-Way acquisition starting in spring 2017 – Right-of-way impacts will be at Knapp & Hammond intersection – Right-of-way required at proposed sidewalk locations and some curb ramp locations • Final plans and specifications completed fall 2017 • Construction 2018 Project ID 8120-04-30 March 7, 2017 Page 12

  13. Construction Timeline Stage 1 – Removal of existing islands at Hammond Avenue and installation of temporary pavement for future stages Project ID 8120-04-30 March 7, 2017 Page 13

  14. Construction Timeline Stage 2 – Construction on eastbound WIS 48; access to business and private driveways to remain open Project ID 8120-04-30 March 7, 2017 Page 14

  15. Construction Timeline Stage 3 – Construction on westbound WIS 48; Hammond Ave. closed; access to businesses and private driveways to remain open Project ID 8120-04-30 March 7, 2017 Page 15

  16. Construction Timeline Stage 4 – Construction of median islands and traffic signals; temporary lane closures for construction Project ID 8120-04-30 March 7, 2017 Page 16

  17. Questions/Comments Thank you for your Participation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.