Public Information Meeting WIS 48 (Knapp Street) Bear Paw Ave. to Hammond Ave. City of Rice Lake WisDOT Project I.D. 8120-04-30 March 7, 2017 Welcome & Introductions Agenda for Meeting Project Scope 4-Lane to 3-Lane Conversion


slide-1
SLIDE 1

Public Information Meeting

WIS 48 (Knapp Street) Bear Paw Ave. to Hammond Ave. City of Rice Lake

WisDOT Project I.D. 8120-04-30

March 7, 2017

slide-2
SLIDE 2

Welcome & Introductions

slide-3
SLIDE 3

Agenda for Meeting

  • Project Scope
  • 4-Lane to 3-Lane Conversion Information
  • Wisconsin Avenue Intersection
  • Hammond Avenue Intersection
  • Project Timeline
  • Construction Timeline
  • Questions & Comments

March 7, 2017 Project ID 8120-04-30 Page 3

slide-4
SLIDE 4

Project Scope

  • Project Limits

– Bear Paw Ave. to Hammond Ave. – Approximately 1 mile long

  • Proposed Improvements

– Rehabilitate existing pavement – Convert existing 4-lane roadway to 3-lane roadway – Install right turn lane and traffic signal at Wisconsin Ave. – Reconstruct Knapp St. & Hammond Ave. Intersection – Install traffic signal at Knapp St. & Hammond Ave. Intersection – Install several sections of sidewalk throughout the corridor – Upgrade existing curb ramps to meet current standards

March 7, 2017 Project ID 8120-04-30 Page 4

slide-5
SLIDE 5

Public Involvement Meeting #1 – January 22, 2015

  • 4-Lane to 3-Lane conversion
  • Wisconsin Avenue intersection operation
  • Lowering the speed limit
  • Proposed sidewalk locations

March 7, 2017 Project ID 8120-04-30 Page 5

slide-6
SLIDE 6

4-Lane to 3-Lane Conversion (Road Diet)

March 7, 2017 Project ID 8120-04-30 Page 6

slide-7
SLIDE 7

4-Lane to 3-Lane Conversion (Road Diet)

March 7, 2017 Project ID 8120-04-30 Page 7

slide-8
SLIDE 8

4-Lane to 3-Lane Conversion (Road Diet)

March 7, 2017 Project ID 8120-04-30 Page 8

slide-9
SLIDE 9

4-Lane to 3-Lane Conversion (Road Diet)

March 7, 2017 Project ID 8120-04-30 Page 9

slide-10
SLIDE 10

Wisconsin Avenue Intersection

March 7, 2017 Project ID 8120-04-30 Page 10

slide-11
SLIDE 11

Hammond Avenue Intersection

March 7, 2017 Project ID 8120-04-30 Page 11

slide-12
SLIDE 12

Project Timeline

  • Currently 70% plans are completed
  • Right-of-Way acquisition starting in spring 2017

– Right-of-way impacts will be at Knapp & Hammond intersection – Right-of-way required at proposed sidewalk locations and some curb ramp locations

  • Final plans and specifications completed fall 2017
  • Construction 2018

March 7, 2017 Project ID 8120-04-30 Page 12

slide-13
SLIDE 13

Construction Timeline Stage 1 – Removal of existing islands at Hammond Avenue and installation of temporary pavement for future stages

March 7, 2017 Project ID 8120-04-30 Page 13

slide-14
SLIDE 14

Construction Timeline Stage 2 – Construction on eastbound WIS 48; access to business and private driveways to remain open

March 7, 2017 Project ID 8120-04-30 Page 14

slide-15
SLIDE 15

Construction Timeline Stage 3 – Construction on westbound WIS 48; Hammond

  • Ave. closed; access to businesses and private driveways to

remain open

March 7, 2017 Project ID 8120-04-30 Page 15

slide-16
SLIDE 16

Construction Timeline Stage 4 – Construction of median islands and traffic signals; temporary lane closures for construction

March 7, 2017 Project ID 8120-04-30 Page 16

slide-17
SLIDE 17

Questions/Comments Thank you for your Participation