Projects and Choosing the Best Project Delivery Method Ryan Toner - - PowerPoint PPT Presentation
Projects and Choosing the Best Project Delivery Method Ryan Toner - - PowerPoint PPT Presentation
Session 4: Managing Projects and Choosing the Best Project Delivery Method Ryan Toner | Vice President | Dibble Engineering Renju Abraham, PE PM / Associate Engineer Burns & McDonnell Mike Smejkal, PE, AAE VP of Planning &
Session 4: Managing Projects and Choosing the Best Project Delivery Method
Ryan Toner | Vice President | Dibble Engineering
Session Speakers
Renju Abraham, PE PM / Associate Engineer Burns & McDonnell Mike Smejkal, PE, AAE VP of Planning & Engineering Tucson Airport Authority Sandy Kukla, AIA Executive Vice President DWL Architects + Planners Mike Hill Senior Project Manager Sundt Construction, Inc. Tim Morrison, PE, PMP Program/Project Manager FAA Phoenix ADO
SWAAAE 2019
Current Trends in Construction Delivery Methods
Renju Abraham, PE
SWAAAE 2019
Various Project Delivery Methods
D-B-B Design-Build Design-Build-Operate-Maintain CM at Risk CM/Agent Job Order Contracting P3
Alternative Delivery
- Design-Bid-Build
- Design-Build
- DBFOM, DBOO, DBOOM
- Progressive D-B
- CM at Risk
- P3
- IPD
- Job Order Contracting
- CM/Agent (Multi-Prime)
SWAAAE 2019
What is the best construction delivery method?
It depends on who you ask!
SWAAAE 2019
The “MacLeamy” Curve
Method #1 Traditional Design Design-Bid Bid- Build Build
SWAAAE 2019
Design-Bid-Build
Designer Contractor Owner QBS Competitive Bids Design Construction
Design Procurement Bidding & Value Engineering
The Lawsuit!
Method #2 Design Design-Build Build
SWAAAE 2019
Design-Build
A/E Owner Best Value Design
Design-Build Procurement
Design-Builder Construction
Time Saved
SWAAAE 2019
Design-Build Flavors Sprinkle in:
- Finance
- Finance-Operate-Maintain (DBFOM)
- Own-Operate (DBOO)
- Own-Operate-Maintain (DBOOM)
- Lease-Back
SWAAAE 2019
Design- Build; Fast Track
SWAAAE 2019
Why Design-Build?
- Sing
Single le Point
- int
Respo esponsibil nsibility ity & & Accounta Accountabil bility ity
- The
he Numbe Number r 1 F 1 Fac actor tor
- Faster
aster
- Chea
Cheaper per
2018 Study: 212 Projects Found that Design-Build had:
- 1. Lower overall
cost growth
- 2. No schedule
growth
- 3. Faster
delivery speed
Method #3 CM a CM at Ri t Risk sk
SWAAAE 2019
CM @ Risk
Designer CM at Risk Owner QBS Competitive Bids Trade Subs
Bond Bonds
Design Construction
Design Procurement Trade Subs Hired CM@R Hired
QBS
SWAAAE 2019
CM@Risk
- Normally involves hiring CM after design has
started or in progress
- CM does perform the work – guarantees price,
schedule, and quality
- Award usually made on a qualitative basis, and
not strictly on price
- On public work, CM bonds the entire contract
SWAAAE 2019
CM@Risk
- Special Legislation needed for public projects
because…
- CM hired on qualifications, not low bid
- Violates competitive bidding laws
- Award to CM prior to knowing the Subs
- Violates “subcontractor listing laws” in
some states
Method # 4 Public Public-Priva Private te Par artner tnerships ships (P3) (P3)
SWAAAE 2019
P3
- Used commonly outside of the U.S., especially
in the U.K.
- Not really alternative project delivery method, as
much as an alternative project funding mechanism for public works projects
- Financial difficulties in many public agencies
limit the funds available for public projects
- This makes P3 a more enticing option
- −>“Buy Now, Pay Later”
Method # 5 Job Or
- b Order
der Contr Contracting acting (JOC) (JOC)
SWAAAE 2019
Job Order Contracting
- Also called “IDIQ”
- Indefinite Delivery, Indefinite Quantity
- Common for recurring but (often)
relatively minor design or construction work
- Scope and timing difficult to know in
advance
- Often involves repair, remodeling, or
repetitive work
- Sometimes used for larger, new projects
Method # 6 CM CM-Agent/ Agent/ Multi Multi-Prime Prime
Design
Design & CM Procurement
Construction
Time Saved
Designer CM-Agent Owner QBS Negotiated Trade Primes
Trade Contractor Procurement
Bid
Manage (Sometimes)
- No Guarantees on
Cost or Quality
Bonds No Bond
CM@Risk
SWAAAE 2019
How do you select a method?
- Owner shall determine the most important
criteria/ objective of the project
- Stakeholder/ community input is a key factor
- Be considerate of funding sources and
legislations
- Flatwork versus vertical
- Familiarity and past success at the airport may
also be considered
SWAAAE 2019
Owner’s Perspective
Mike Smejkal, PE, AAE
SWAAAE 2019
Owner’s Perspective
Design Bid Build
Design Bid Build
- Easily Defined
Phasing & Scope
- Mill & Overlay
SWAAAE 2019
Owner’s Perspective
CMAR
Sample Projects
- Terminal Apron Reconstruction Project (AIP Funded)
- Complicated Phasing
- Multiple Grant Years w/ complex systems (400 Hz &
Fueling System)
- FAA reviews design (for standards/eligibility) prior to
GMP development
- Terminal Optimization Project (PFC Funded)
- Complicated Phasing
- Complicated cutover of critical systems.
Scoring CMAR
- Approach to Teaming, Describe competitive proposal
process
- AZ – Fee not allowed in
SWAAAE 2019
Owner’s Perspective
CMAR
- 2 Gates Closed at a time
- Started August 2013
- 18-20 month total duration
- $45-50M Budget
- New 16” PCC on Recycled PCC Base
- New Trench Drain System
- Hydrant Fueling & 400 Hz Modifications
SWAAAE 2019
Owner’s Perspective
CMAR
- Relocate/Expand Security Checkpoints
- Expand Concession Opportunities
- Upgrade 50 year old building infrastructure
SWAAAE 2019
Owner’s Perspective
Design Build
Design Build
- TAA’s Solar Phase 1 (AIP Funded)
- No FAA Standards to follow
- Basic Requirements (1MW of Power) over area in
parking lot (min. # of stalls must be maintained)
- Need a detailed requirements document for RFP
Scoring
- SOQ – Shortlist
- Technical Proposal Scored based on shortlist
- Teaming & Approach is heavily weighted
- After Technical Proposal is scored open sealed costs
SWAAAE 2019
Owner’s Perspective
Design Build
SWAAAE 2019
Owner’s Perspective
Summary
- Choose Best Method for each project
- Relationship is different with A/E & Contractor for
each method
- Clearly communicate with FAA & State (FSL or SL)
- n signoffs
- Airfield Civil/AIP funded – CMAR better than
Design Build
SWAAAE 2019
Consultant’s Perspective
Sandy Kukla, AIA
SWAAAE 2019
Consultant’s Perspective
PHX Sky Harbor International Airport Terminal 3 Modernization Design/Build PHX Terminal 3 Modernization CMAR/Design-Bid-Build/JOC TUS Terminal Optimization Project AZA West Terminal Expansion Lessons Learned
SWAAAE 2019
2 1 3
Consultant Perspective - Design/Build
PHX Sky Harbor International Airport Terminal 3 Modernization 25 Gates $590 M Total Project 1.9 M Square Feet 11.2 Million Annual Pax
SWAAAE 2019
Consultant Perspective - Design/Build
PHX Sky Harbor International Airport Terminal 3 Modernization
SWAAAE 2019
Consultant Perspective - Design/Build
PHX Sky Harbor International Airport Terminal 3 Modernization Complex Project
- Scale
- Active Campus
- Toughest Part Came First
- Phasing – Funding and
Constructability
- Multiple Stakeholders - 10
Airlines
- Unique Design
SWAAAE 2019
Consultant Perspective - Design/Build
PHX Sky Harbor International Airport Terminal 3 Modernization D/B Considerations
- Is a Project Definition Manual
Required?
- How does communication occur
between the owner and designer?
- Who is the client?
SWAAAE 2019
Consultant Perspective – CMAR/DDB/JOC
Tucson International Airport Terminal Optimization Project JOC / Design-Bid-Build CMAR
SWAAAE 2019
Consultant Perspective – CMAR/DDB/JOC
Phoenix-Mesa Gateway Airport CMAR Design/Bid/Build JOC
SWAAAE 2019
Consultant Perspective – DBB
Phoenix-Mesa Gateway Airport
- Dependent on market
- Phasing by Designer
- Defined Scope
- Detailed documents
- Contractor input is voluntary
- Based on Bid – Who is your Contractor?
- Phasing by Designer
SWAAAE 2019
Consultant Perspective – DBB/JOC/CMAR
Comparison of CMAR to DBB Comparison of CMAR to JOC
SWAAAE 2019
Consultant Perspective – JOC
Tucson International Airport Authority Department Relocations (Demo)
- Small Scale
- Demolition/Unknown Conditions
- On-call Contractor
- Minimal Documents
- Reduced Permit Requirements
- Contractor may be unfamiliar with
typical process
SWAAAE 2019
Consultant Perspective – CMAR
Tucson International Airport Terminal Optimization Project
- Continuous Operations
- Complex Phasing
- Early Document Packages
- Time between Design Phases
for CMAR Review
- Time for Value Engineering/
Scope Reduction
SWAAAE 2019
Consultant Perspective – CMAR
Phoenix-Mesa Gateway Airport
- CMAR Selection Process
- CMAR Design Assist
- Team Project Goals
- Better Construction Staffing
- Project Start Preparation
- Quality
SWAAAE 2019
Consultant Perspective – Lessons Learned
Laughlin/Bullhead Int’l Airport Aircraft Rescue Fire Fighting Station 1. Do an analysis 2. Establish your project criteria, vision and goals. 3. Understand your organization’s characteristics. 4. No One-size fits all
- 5. Set up your project for Success.
SWAAAE 2019
Contractor’s Perspective
Mike Hill
SWAAAE 2019
Contractor’s Perspective
Communication – Key to It All
Why Hard Bid a Project?
- Process is fixed, all decisions made
- Program criteria is clear
- Market is slowing or receding, reducing the cost of time
- There is ample time to design, test, challenge assumptions before going to
market
- Unemployment is up, labor available
- You have ample contingency if market response is not what was planned or
expected. Why Utilize an Alternative Delivery?
- Certainty of outcome is paramount
- Date-Cost-Quality is critical
- Need is Dynamic, Morphing over time
- Costs escalating market place
- Unemployment is down
- Long lasting facility (Cost of construction is app. 20% of overall all cost of the
building)
SWAAAE 2019
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Airport Owners Know:
- Business
- Customers
- What they need
- How to run an airport
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Designers Know:
- Efficiencies
- Aesthetics
- People flow
- Function
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Contractors Know:
- Constructability
- Schedule
- Costs
- Material Lead Times
Having the right contractor makes all the difference.
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Teamwork:
- Meet overall expectations
- High quality
- Fastest overall schedule
- Lowest cost consistent with quality and
performance objectives
- Design most effective
- Complies with technical specs
- Limits design changes cost
- Limit impacts to current operations
- Promotes innovation and VE
- Least confrontational
- Great Result for Customers
- Limits Construction Aggravation
- Limit claims for add’l costs
- Trusted Advisors
- Great Relationships
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Out for Bid:
- Great Package out for bid
- Market Pricing
- Approx. 85% - Hard Bid
- Local Contractors
- Pre-selected Contractors
- DBE/SDB
- Pre-Qualified Contractors
- Great Result for Owners
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
Bad Communication:
- Owner requirements
- Local vs Corp
- 3 Owner Teams (10)
- Renegade Designer
- Custom details
- Custom structure
- Comp Design 50%
- Terminated
- Missed all deadlines
- Hired New Arch
- What Owner budget
- Accumulated Costs from all
Contractor’s Perspective
Communication – Key to It All
SWAAAE 2019
FAA’s Perspective
Tim Morrison, PE, PMP
SWAAAE 2019
FAA’s Perspective
AC 150/5100-14E, Change 1 – Architectural, Engineering, and Planning Consultant Services for Airport Grant Projects
Before undertaking alternative project delivery for an AIP funded project, the conditions for the project must be evaluated to determine if alternative delivery is more beneficial than the traditional design-bid-build method.................. Sponsors should follow all applicable State and local laws but must include the required Federal contract clauses and provisions in the procurement documents. See Title 2 CFR § 200.326.
SWAAAE 2019
FAA’s Perspective
Who Benefits from Alternative Delivery?
- Scope / Schedule / Budget
- Scale
- Complexity
SWAAAE 2019
FAA’s Perspective
Where a Sponsor decides to utilize an Alternative Project Delivery System (APDS) such as design-build (DB)
- r
construction manager-at-risk (CMAR), the Sponsor may use the competitive proposal approach (as defined in 2 CFR §200.320) for selection provided price and other factors such as qualifications, skill, experience, and design approach are considered when selecting a firm to perform this service. The selection of an A/E services firm is the only instance where prices must be excluded as a consideration under a competitive proposal selection.
SWAAAE 2019
FAA’s Perspective
AIP Handbook – Order 5100.38E, Change 1 Mandatory ADO pre-review and concurrence with the sponsor’s use of design-build proposal for AIP funded projects is based on requirements found in 49 USC § 47142(a)(2). ADO pre-review and concurrence is also required by FAA policy for any AIP-funded project where construction manager-at-risk or
- ther competitive proposal methods that involve selection
based on factors other than price are proposed.
SWAAAE 2019
FAA’s Perspective
Sponsor Requirements for Cost Reasonableness
- Engineer’s estimate
- A statement signed by the sponsor that the cost analysis was performed
that includes the sponsor’s recommendation that the FAA accept the statement and analysis as evidence of cost reasonableness.
- Bid tabulation (one bidder), proposal (sole source, design/build,
construction manager-at-risk), or winning quote (small purchase).
- Copy of the signed contract
- Any other support documentation requested by the ADO.
Questions?
Renju Abraham, PE PM / Associate Engineer Burns & McDonnell Mike Smejkal, PE, AAE VP of Planning & Engineering Tucson Airport Authority Sandy Kukla, AIA Executive Vice President DWL Architects + Planners Mike Hill Senior Project Manager Sundt Construction, Inc. Tim Morrison, PE, PMP Program/Project Manager FAA Phoenix ADO