Project Risk Management: A New Approach Stefan Creemers Erik - - PowerPoint PPT Presentation

project risk management a new approach
SMART_READER_LITE
LIVE PREVIEW

Project Risk Management: A New Approach Stefan Creemers Erik - - PowerPoint PPT Presentation

Project Risk Management: A New Approach Stefan Creemers Erik Demeulemeester Stijn Van de Vonder Risk management 101 Risk identification Risk analysis Risk mitigation Risk control Risk management 101 Risk identification Quantify


slide-1
SLIDE 1

Project Risk Management: A New Approach

Stefan Creemers Erik Demeulemeester Stijn Van de Vonder

slide-2
SLIDE 2

Risk management 101

Risk identification Risk analysis Risk mitigation Risk control

slide-3
SLIDE 3

Risk management 101

Risk identification Risk analysis Risk mitigation Risk control

  • Quantify probabilities and impacts of risks
  • Assess the impact on project objectives
  • Calculate the project objectives
slide-4
SLIDE 4

Risk management 101

Risk identification Risk analysis Risk mitigation Risk control

  • Quantify probabilities and impacts of risks
  • Assess the impact on project objectives
  • Calculate the project objectives

Where to start?

slide-5
SLIDE 5

Project risk management: current approach

Uncertainty is captured in activity durations:

  • Normal distribution
  • Triangular distribution
  • Beta distribution

Monte Carlo simulation is used to obtain estimates of project

  • bjectives (e.g. cdf of the

completion time)

slide-6
SLIDE 6

Project risk management: current approach

Uncertainty is captured in activity durations:

  • Normal distribution
  • Triangular distribution
  • Beta distribution

Monte Carlo simulation is used to obtain estimates of project

  • bjectives (e.g. cdf of the

completion time)

slide-7
SLIDE 7

Risk mitigation: how is it done?

TORNADO GRAPH

slide-8
SLIDE 8

Risk mitigation: how is it done?

TORNADO GRAPH

Focus mitigation efforts on the most sensitive activity; the activity that has the highest rank

slide-9
SLIDE 9

Ranking activities: existing measures

Criticality index Significance index Cruciality index Schedule sensitivity index

slide-10
SLIDE 10

Problems with the current approach

  • Project managers have a very hard time

to model uncertainty

  • All of the previous ranking measures

have been criticized

  • It is not clear where the uncertainty
  • riginates from
  • It is unclear how to mitigate uncertainty
slide-11
SLIDE 11

New approach: risk-driven (instead of activity-based)!

… Project

ACT 1 ACT 2 ACT 3 Risk 1 Risk 2 Risk 3 Risk 5 Activity duration distribution (ACT 1) Risk 1 Risk 4

Risk 1 Risk 2 Risks 1&2

slide-12
SLIDE 12

Ranking risks: proposed measures

Cruciality index Critical Delay Contribution (CDC)

slide-13
SLIDE 13

Advantages of the new approach

  • Risks are much easier to predict than

uncertainty

  • CDC is calculated on risk per activity

basis and can be aggregated on the level

  • f risks and activities
  • Risks root causes are ranked => we know

which risk to mitigate!

slide-14
SLIDE 14

Risk-driven = ranking of risks rather than activities

TORNADO GRAPH

slide-15
SLIDE 15

Risk-driven = ranking of risks rather than activities

TORNADO GRAPH

slide-16
SLIDE 16

Evaluation of the new approach using a computational experiment

For a large set of projects (600 projects of PSPLIB 120):

– Model uncertainty (i.e. define risks, impacts, probabilities…) – Simulate the project execution – For each ranking measure:

  • Calculate the highest-ranked risk according to the measure
  • Eliminate the highest-ranked risk (i.e. focus our mitigation

efforts on this risk

How good do the measures perform when mitigating 10 risks?

slide-17
SLIDE 17

Computational experiment: ranking measures

ACTIVITY-BASED =>

SELECT THE LARGEST RISK THAT IMPACTS THE HIGHEST-RANKED ACTIVITY

RISK-DRIVEN =>

SELECT THE LARGEST RISK

CDC ACT CDC RISK CI ACT CI RISK SSI SI ACI

slide-18
SLIDE 18

Results

slide-19
SLIDE 19

Results

Project Delay Number of risks eliminated

slide-20
SLIDE 20

Results

Project Delay Number of risks eliminated Random Greedy Optimal Solution space

slide-21
SLIDE 21

Results

ACI SI

slide-22
SLIDE 22

Results

CI act SSI

slide-23
SLIDE 23

Results

CDC = best of activity- based measures CDC act

slide-24
SLIDE 24

Results

CI risk CDC act

slide-25
SLIDE 25

Results

CDC risk CI risk CDC = best of risk-driven measures

slide-26
SLIDE 26

Conclusions

  • A risk-driven approach to project risk analysis is

better than a activity-based approach

  • CDC is able to outperform current best practice

measures (activity-based AND risk-driven)

  • CDC is very close to greedy optimal
  • Results are robust/hold for a wide variety of settings