Project Presentation EANC Meeting Nevada County Contractors - - PowerPoint PPT Presentation

project presentation
SMART_READER_LITE
LIVE PREVIEW

Project Presentation EANC Meeting Nevada County Contractors - - PowerPoint PPT Presentation

Banner Cascade Pipeline Project Presentation EANC Meeting Nevada County Contractors Association November 29, 2012 BANNER CASCADE PIPELINE ALIGNMENT Nevada County Airport BANNER CASCADE PIPELINE PROJECT Project Overview Second Phase


slide-1
SLIDE 1

Banner Cascade Pipeline Project Presentation

EANC Meeting

Nevada County Contractors Association November 29, 2012

slide-2
SLIDE 2

BANNER CASCADE PIPELINE ALIGNMENT

Nevada County Airport

slide-3
SLIDE 3

BANNER CASCADE PIPELINE PROJECT

  • Project Overview
  • Second Phase – Following Cascade Upper

Bench Replacement – 2000

  • Take Pressure off Lower Cascade Canal with

installation of 6.8mi of 48 inch steel pipe

  • Project began in 2001 with EIR Process
  • Seven years to EIR certification and approval
  • Design began in January 2008
slide-4
SLIDE 4

BANNER CASCADE PIPELINE PROJECT

slide-5
SLIDE 5

BANNER CASCADE PIPELINE PROJECT

slide-6
SLIDE 6

BANNER CASCADE PIPELINE PROJECT

  • Project Overview
  • Second Phase – Following Cascade Upper

Bench Replacement – 2000

  • Take Pressure off Lower Cascade Canal with

installation of 6.8mi of 48 inch steel pipe

  • Project began in 2001 with EIR Process
  • Seven years to EIR certification and approval
  • Design began in January 2008
slide-7
SLIDE 7

BANNER CASCADE PIPELINE PROJECT

  • Design Overview
  • RFP Process for the Design Consultant
  • Design concept: Stakeholder Involvement
  • Hosted Three Public Workshops during the

design at 10%, 50% and 90% completion

  • Gathered Public Input from property owners

from workshops and numerous 1 on 1 meetings and incorporated into design

  • Design began in January 2008 and concluded

January 2010 with a Contractor RFQ process

slide-8
SLIDE 8

BANNER CASCADE PIPELINE PROJECT

  • Bid Overview
  • Contractor RFQ process used a matrix to

select qualified contractors prior to bidding the project

  • Bid project knowing that the contractors

would perform to District standards

  • Included in the bid process a local bidders

preference

  • Teichert Construction awarded the contract
slide-9
SLIDE 9

BANNER CASCADE PIPELINE PROJECT

  • Pre-Construction Overview
  • Easement Acquisitions - continued
  • Well Monitoring Program - continued
  • Pre-construction Environmental Surveys
  • Environmental Monitoring for Creek Crossings

(before and during construction)

  • Removal of approx. 600 trees from alignment

staged over two year period

slide-10
SLIDE 10

BANNER CASCADE PIPELINE PROJECT

slide-11
SLIDE 11

BANNER CASCADE PIPELINE PROJECT

slide-12
SLIDE 12

BANNER CASCADE PIPELINE PROJECT

  • Pre-Construction Overview
  • Easement Acquisitions - continued
  • Well Monitoring Program - continued
  • Pre-construction Environmental Surveys
  • Environmental Monitoring for Creek Crossings

(before and during construction)

  • Removal of approx. 600 trees from alignment

staged over two year period

  • Scotch Broom Removal
slide-13
SLIDE 13

BANNER CASCADE PIPELINE PROJECT

slide-14
SLIDE 14

BANNER CASCADE PIPELINE PROJECT

  • Pre-Construction Overview
  • Easement Acquisitions - continued
  • Well Monitoring Program - continued
  • Pre-construction Environmental Surveys
  • Environmental Monitoring for Creek Crossings

(before and during construction)

  • Removal of approx. 600 trees from alignment

staged over two year period

  • Scotch Broom Removal
slide-15
SLIDE 15

BANNER CASCADE PIPELINE PROJECT

slide-16
SLIDE 16

BANNER CASCADE PIPELINE PROJECT

  • Construction Overview
  • Started a communication process to inform

the neighborhoods of the upcoming work

  • Had Ombudsman working as a direct link

between the property owners and NID

  • Installed seven Project Information Boards in

strategic locations along the alignment

  • Held several Public Workshops with the

neighborhoods prior to start of construction

slide-17
SLIDE 17

BANNER CASCADE PIPELINE PROJECT

slide-18
SLIDE 18

BANNER CASCADE PIPELINE PROJECT

slide-19
SLIDE 19

BANNER CASCADE PIPELINE PROJECT

  • Construction Overview
  • Started a communication process to inform

the neighborhoods of the upcoming work

  • Had Ombudsman working as a direct link

between the property owners and NID

  • Installed seven Project Information Boards in

strategic locations along the alignment

  • Held several Public Workshops with the

neighborhoods prior to start of construction

slide-20
SLIDE 20

BANNER CASCADE PIPELINE PROJECT

  • Construction Overview (con’t)
  • Weekly Monitoring of the Mitigation

Monitoring and Reporting Program (MMRP)

  • Environmental Monitoring for Creek Crossings

(before and during construction)

  • Monitoring and Compliance with the Storm

Water Pollution and Prevention Plan (SWPPP)

  • Provided Dust Claim form
slide-21
SLIDE 21

BANNER CASCADE PIPELINE PROJECT

  • Construction Overview (con’t)
  • Tree Restoration Program followed pipeline

installation.

  • NID personnel met with each property owner

to determine the type, quantity, and location

  • f tree replacement.
  • MMRP required a two for one tree

replacement in a 15 gallon container.

slide-22
SLIDE 22

BANNER CASCADE PIPELINE PROJECT

slide-23
SLIDE 23

BANNER CASCADE PIPELINE PROJECT

slide-24
SLIDE 24

BANNER CASCADE PIPELINE PROJECT

slide-25
SLIDE 25

BANNER CASCADE PIPELINE PROJECT

slide-26
SLIDE 26

BANNER CASCADE PIPELINE PROJECT

Banner Lava Cap Road

slide-27
SLIDE 27

BANNER CASCADE PIPELINE PROJECT

slide-28
SLIDE 28

BANNER CASCADE PIPELINE PROJECT

slide-29
SLIDE 29

BANNER CASCADE PIPELINE PROJECT

slide-30
SLIDE 30

BANNER CASCADE PIPELINE PROJECT

slide-31
SLIDE 31

BANNER CASCADE PIPELINE PROJECT

slide-32
SLIDE 32

BANNER CASCADE PIPELINE PROJECT

slide-33
SLIDE 33

BANNER CASCADE PIPELINE PROJECT

slide-34
SLIDE 34

BANNER CASCADE PIPELINE PROJECT

slide-35
SLIDE 35

BANNER CASCADE PIPELINE PROJECT

slide-36
SLIDE 36

BANNER CASCADE PIPELINE PROJECT

slide-37
SLIDE 37

BANNER CASCADE PIPELINE PROJECT

slide-38
SLIDE 38

BANNER CASCADE PIPELINE PROJECT

slide-39
SLIDE 39

BANNER CASCADE PIPELINE PROJECT

slide-40
SLIDE 40

BANNER CASCADE PIPELINE PROJECT Questions?

slide-41
SLIDE 41

BANNER CASCADE PIPELINE PROJECT

Project Objectives:

  • Safety First
  • Install the pipeline system and minimize impacts
  • f construction on the residents and community
  • Provide and make available treated water, raw

water and fire protection along the pipeline alignment

  • Put the raw water system into service as soon as

possible

slide-42
SLIDE 42

BANNER CASCADE PIPELINE PROJECT

Expectations During Construction:

  • School Bus, Mail Delivery, Garbage and

Emergency have been notified of Project

  • Tree Removal and Clearing
  • Traffic Detours and Delays
  • Noise / Dust Control
  • Minimize Driveway Blockage – Owners

Notified Minimum 72 hours Prior to Work

  • Trench Restoration Followed by Final Overlay
slide-43
SLIDE 43

BANNER CASCADE PIPELINE PROJECT

Expectations During Construction (con’t):

  • Restoration Contractor – To Meet with Each

Owner Regarding Replacement Tree Location

  • For everyone’s safety - Residents need to stay
  • ut of construction zones during the working

hours

  • Please be Patient – We also want this work

completed as soon as possible

slide-44
SLIDE 44

BANNER CASCADE PIPELINE PROJECT

Miscellaneous:

  • Use of Local Contractors, Suppliers and Consultants
  • NID tank site will be used for job trailers and equipment

and material storage for project

  • Waterline from meter to house is the home owners

responsibility

  • Taking treated water and currently have a well – need

backflow device or need to abandon well

  • Mainline extensions can be started after the treated line is

in service. Speak with Shannon Bradley for information

  • Project Website: www.nidbannercascade.com