Project Development & Environment 1 (PD&E) Study Kick-off - - PowerPoint PPT Presentation

project development environment
SMART_READER_LITE
LIVE PREVIEW

Project Development & Environment 1 (PD&E) Study Kick-off - - PowerPoint PPT Presentation

SR 874 Ramp Connector Project Development & Environment 1 (PD&E) Study Kick-off Meeting Moving Miami - Dade MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 Project Development & Environment Study


slide-1
SLIDE 1

1

SR 874 Ramp Connector Project Development & Environment (PD&E) Study

“Moving Miami-Dade”

MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501

Kick-off Meeting

slide-2
SLIDE 2

2

Project Development & Environment Study

  • Develop and evaluate engineering and environmentally feasible

alternative solutions that meet the need determined in the Planning Phase.

  • Evaluate potential impacts to the social, natural and physical

environments and determine ways to avoid or minimize impacts.

  • Inform and involve the public in the development of the project.
  • This process is mandated by the National Environment Policy Act

(NEPA) and state law. It represents a combined effort by technical professionals who analyze information and document the best alternative for a community’s transportation needs.

slide-3
SLIDE 3

3

Project Life Cycle

slide-4
SLIDE 4

4

4

Project Development & Environment Study

slide-5
SLIDE 5

5

Project Description

SR 874

  • Urban Principal

Arterial Expressway

  • Approximately 7.2

miles

  • Posted Speed Limit

55mph

  • Hurricane Evacuation

Route

  • Part of SIS/FIHS
  • Proposes a new

ramp connection between the existing SR 874 at the HEFT with SW 136th St

slide-6
SLIDE 6

6

Corridor Characteristics

Part of the Florida Intrastate Highway System (FIHS) Part of the Strategic Intermodal System (SIS)

  • Develops and maintains the network of

highways that combined make up the intrastate system

  • Composed of interconnected limited and

controlled-access roadways including interstate highways and Florida’s Turnpike system

  • System of transportation facilities of statewide

and interregional significance

  • Focused on the efficient movement of

passengers and freight

  • Carries 68% of all truck traffic and 29% of all

traffic This project is included in the Miami-Dade County 2035 Long Range Transportation Plan and in the Miami-Dade Comprehensive Development Master Plan

slide-7
SLIDE 7

7

Purpose and Need

1. Social Demand and Economic Development 2. System Connectivity 3. Capacity 4. Evacuation Route/ Emergency Services

slide-8
SLIDE 8

8

Purpose and Need

Social Demand and Economic Development

  • The study area is one of the fastest growing most densely populated communities in the state with

limited expressway access

  • Population and jobs are anticipated to increase by 104% and 37%, respectively by 2035
  • Improvements to the Kendall-Tamiami Executive Airport and near by supporting land-uses such as

new tourist developments anticipated for Miami MetroZoo, schools, community and shopping centers will increase traffic congestion in the area

  • Growth in industrial and flex-space

activities in the area are largely dependent upon expressway access

slide-9
SLIDE 9

9

Purpose and Need

System Connectivity

  • SR 874 provides a southwest to

northeast connection from the HEFT to the Palmetto Expressway (SR 826)

  • The proposed connector would

provide an alternate travel route, relieving congestion at the HEFT/SW 120 St and SW 152 St interchanges

  • The new facility would provide

local traffic a more direct route to the centers of employment in the County (i.e. Downtown Miami and Miami International Airport)

slide-10
SLIDE 10

10

Purpose and Need

Capacity

  • SW 120 St and SW

152 St are the only corridors in the area with access to the expressway system

  • SW 120 St and SW

152 St and their interchanges with the HEFT are currently

  • perating over

capacity

  • Expressways in the

area are currently heavily congested

slide-11
SLIDE 11

11

Purpose and Need

Evacuation Route/ Emergency services

  • The lower southeast Florida Region has been identified by

the National Oceanic Atmospheric Administration (NOAA) as one of the most hurricane vulnerable areas in the United States

  • HEFT is one of three continuous north-south corridors

along with Krome Avenue to the west and US 1 to the east and thus serves as a critical evacuation route

  • The SR 874/Don Shula Expressway facilitates access to
  • ther critical north-south facilities (i.e. SR 826/Palmetto

Expressway, US-1, I-95)

  • This project would provide an additional connection to the

SR 874 facility and expedite the mobility at the HEFT interchanges decreasing evacuation time

slide-12
SLIDE 12

12

Corridor Constraints

  • Tamiami Complex

Pineland Preserve and Nixon Smiley Pineland Preserve

  • Multiple Residential

neighborhoods

  • Existing and

proposed FP&L lines

  • CSX Railroad
  • FP&L Davis

Substation

  • Proposed HEFT

improvements

  • Kendall Tamiami

Executive Airport – FAA compliance

TAMIAMI COMPLEX PINELAND PRESERVE BONITA LAKES DAVIS SUBSTATION CSX RR GPC SPUR

VENEZIA LAKES NIXON SMILEY PINELAND PRESERVE KENDALL TAMIAMI EXECUTIVE AIRPORT

slide-13
SLIDE 13

13

Key Project Components

  • Public Involvement
  • Engineering
  • Corridor Analysis
  • Traffic Analysis
  • Issues
  • Environmental
  • Coordination
slide-14
SLIDE 14

14

Public Involvement

slide-15
SLIDE 15

15

Public Involvement

Community Involvement

  • Identify Key Stakeholders, businesses, etc.
  • Meetings:

– Fact sheets – Newsletters – Project website – Public meetings – Preparing responses to inquiries – Agency/Elected Officials Kick-off Meeting – Public Kick-off Meeting – County Commissioners Presentation – Public Alternatives Workshop – Public Hearing

  • Ways of engaging the community:
slide-16
SLIDE 16

16

Public Involvement

Public Outreach Program

  • A Public Outreach Program was conducted as a part of the SR 874

Connector Project Concept Study (June, 2008)

  • A total of 41 community groups in the area were incorporated in the study
  • Public Concerns included:
  • Height of ramp
  • Aesthetics
  • Tolls
  • Lighting
  • Noise from ramps
  • Noise walls
  • Future ramp connection to turnpike
  • Level of service of surrounding streets
  • Issues identified by environmental agencies
slide-17
SLIDE 17

17

Engineering

Alternative Selection Process

slide-18
SLIDE 18

18

Engineering

Corridor Analysis

Preferred alternative from the SR 874 Connector Report was later found to be unfeasible due to impacts to Pineland Preserve Corridors B, C, D, & E commence at the intersection

  • f

SW 136/SW 137 Ave and traverse in part along SW 136 St Corridors A & D would require additional R/W along SW 128 St. This corridor has warehouses abutting the roadway as well as a dedicated nature preserve Corridor C would partially traverse over the CSX railroad and is in very close proximity to both the Bonita Lakes housing development and the Pineland Preserve. Corridors B & E would either infringe

  • n

the existing FPL easement and thus conflict with the planned expansion

  • f

the transmission lines and/or impact numerous existing warehouses Corridors A&D would require a modification to the planned HEFT interchange in order to accommodate the new ramps

Avoid impacts to:

  • Pineland Preserves
  • FP&L
  • Residences
  • Proposed HEFT

improvements

slide-19
SLIDE 19

19

Engineering

Traffic Analysis

  • Perform Data Collection
  • Traffic Analysis Years:
  • Opening: 2017
  • Interim: 2027
  • Design: 2037
  • Determine traffic

improvements/ impacts of proposed facility on existing street grid

  • Determine any additional

improvement that may be required

  • Requires the Preparation of

an Interchange Modification Report (IMR)

  • Requires FDOT review

(FIHS/ SIS facility)

slide-20
SLIDE 20

20

Issues

  • Intersection Impacts
  • Drainage/ Stormwater treatment
  • Retention ponds within bridge footprint
  • Potential Joint Use Pond Agreement with

Venezia Lakes residential development

  • FAA approach surface compliance for the

Kendall Tamiami Executive Airport

  • Minimize right-of-way
  • Develop necessary horizontal and vertical

alignments to avoid or minimize impacts to a multitude of project constraints

Engineering

slide-21
SLIDE 21

21

  • Direct Effects
  • Natural Issues
  • Physical Issues
  • Socio-Economic Issues
  • Cultural Issues
  • Indirect & Cumulative Effects (ICE)
  • Indirect (or secondary)
  • Cumulative (actions by others)

Environmental

slide-22
SLIDE 22

22

Physical Issues

  • Noise Impacts - Numerous noise

sensitive receptors

  • Multiple noise sensitive sites

along project corridor

  • Air Quality - Improvements that

reduce congestion also reduce air quality impacts

Environmental

Cultural Issues

  • Historic Structures and Districts - No

historical sites identified

  • Archaeological Analysis
  • Performing Cultural Resource

Assessment Survey (CRAS)

slide-23
SLIDE 23

23

Natural Issues

  • Floodplains
  • Site within 100 year flood

plain

  • Special Designations
  • Wildlife and Habitat
  • 26-acre Tamiami Pineland

Complex- part of Dade County Archipelago Florida Forever Project

  • Recreation Areas
  • Section 4(f) Potential
  • Aesthetics
  • Secondary and Cumulative

Environmental

Seven (7) issues of Substantial degree were identified within the project area including

slide-24
SLIDE 24

24

Possible Permits

  • Army Corps of Engineers (ACOE)

– Dredge Fill Permit

  • SFWMD

– Environmental Resource Permit (ERP)

  • MD Department of Environmental Resources

Management (DERM)

– Class II

  • Right-of-Way Occupancy Permit

– To work within and over CSX right-of-way

Environmental

slide-25
SLIDE 25

25

  • On-going/Planned Developments
  • Miami-Dade County
  • Florida Department of Transportation ( FDOT)
  • Florida Turnpike Enterprise (FTE)
  • Miami Dade Public Works (MDPW)
  • Miami Dade Transit (MDT)
  • Florida Highway Administration (FHWA)
  • Florida Department of Environmental

Protection (FDEP)

  • South Florida Water Management District

(SFWMD)

  • Florida Power & Light (FPL)
  • CSX Transportation (CSX)
  • Federal Aviation Administration (FAA)

Coordination

slide-26
SLIDE 26

26

Collaborative Effort

slide-27
SLIDE 27

27

PROJECT SCHEDULE

Next Steps

  • Final Design: 2011-2013
  • Right-of-Way: 2013-2015
  • Construction: 2015-2017
slide-28
SLIDE 28

28

More Information

If you would like to learn more about this study, please contact:

  • Ms. Tere Garcia

Public Information Officer Phone: (305) 860-3758 Cell: (786) 277-9292 Fax: (305) 860-3759 E-mail: Tgarcia@bermelloajamil.com