1
SR 874 Ramp Connector Project Development & Environment (PD&E) Study
“Moving Miami-Dade”
MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501
Project Development & Environment 1 (PD&E) Study Kick-off - - PowerPoint PPT Presentation
SR 874 Ramp Connector Project Development & Environment 1 (PD&E) Study Kick-off Meeting Moving Miami - Dade MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 Project Development & Environment Study
1
MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501
2
alternative solutions that meet the need determined in the Planning Phase.
environments and determine ways to avoid or minimize impacts.
(NEPA) and state law. It represents a combined effort by technical professionals who analyze information and document the best alternative for a community’s transportation needs.
3
4
4
5
SR 874
Arterial Expressway
miles
55mph
Route
ramp connection between the existing SR 874 at the HEFT with SW 136th St
6
Part of the Florida Intrastate Highway System (FIHS) Part of the Strategic Intermodal System (SIS)
highways that combined make up the intrastate system
controlled-access roadways including interstate highways and Florida’s Turnpike system
and interregional significance
passengers and freight
traffic This project is included in the Miami-Dade County 2035 Long Range Transportation Plan and in the Miami-Dade Comprehensive Development Master Plan
7
1. Social Demand and Economic Development 2. System Connectivity 3. Capacity 4. Evacuation Route/ Emergency Services
8
Social Demand and Economic Development
limited expressway access
new tourist developments anticipated for Miami MetroZoo, schools, community and shopping centers will increase traffic congestion in the area
activities in the area are largely dependent upon expressway access
9
System Connectivity
northeast connection from the HEFT to the Palmetto Expressway (SR 826)
provide an alternate travel route, relieving congestion at the HEFT/SW 120 St and SW 152 St interchanges
local traffic a more direct route to the centers of employment in the County (i.e. Downtown Miami and Miami International Airport)
10
Capacity
152 St are the only corridors in the area with access to the expressway system
152 St and their interchanges with the HEFT are currently
capacity
area are currently heavily congested
11
Evacuation Route/ Emergency services
the National Oceanic Atmospheric Administration (NOAA) as one of the most hurricane vulnerable areas in the United States
along with Krome Avenue to the west and US 1 to the east and thus serves as a critical evacuation route
Expressway, US-1, I-95)
SR 874 facility and expedite the mobility at the HEFT interchanges decreasing evacuation time
12
Pineland Preserve and Nixon Smiley Pineland Preserve
neighborhoods
proposed FP&L lines
Substation
improvements
Executive Airport – FAA compliance
TAMIAMI COMPLEX PINELAND PRESERVE BONITA LAKES DAVIS SUBSTATION CSX RR GPC SPUR
VENEZIA LAKES NIXON SMILEY PINELAND PRESERVE KENDALL TAMIAMI EXECUTIVE AIRPORT
13
14
15
Community Involvement
– Fact sheets – Newsletters – Project website – Public meetings – Preparing responses to inquiries – Agency/Elected Officials Kick-off Meeting – Public Kick-off Meeting – County Commissioners Presentation – Public Alternatives Workshop – Public Hearing
16
Public Outreach Program
Connector Project Concept Study (June, 2008)
17
Alternative Selection Process
18
Corridor Analysis
Preferred alternative from the SR 874 Connector Report was later found to be unfeasible due to impacts to Pineland Preserve Corridors B, C, D, & E commence at the intersection
SW 136/SW 137 Ave and traverse in part along SW 136 St Corridors A & D would require additional R/W along SW 128 St. This corridor has warehouses abutting the roadway as well as a dedicated nature preserve Corridor C would partially traverse over the CSX railroad and is in very close proximity to both the Bonita Lakes housing development and the Pineland Preserve. Corridors B & E would either infringe
the existing FPL easement and thus conflict with the planned expansion
the transmission lines and/or impact numerous existing warehouses Corridors A&D would require a modification to the planned HEFT interchange in order to accommodate the new ramps
Avoid impacts to:
improvements
19
Traffic Analysis
improvements/ impacts of proposed facility on existing street grid
improvement that may be required
an Interchange Modification Report (IMR)
(FIHS/ SIS facility)
20
Issues
Venezia Lakes residential development
Kendall Tamiami Executive Airport
alignments to avoid or minimize impacts to a multitude of project constraints
21
22
Physical Issues
sensitive receptors
along project corridor
reduce congestion also reduce air quality impacts
Cultural Issues
historical sites identified
Assessment Survey (CRAS)
23
Natural Issues
plain
Complex- part of Dade County Archipelago Florida Forever Project
Seven (7) issues of Substantial degree were identified within the project area including
24
– Dredge Fill Permit
– Environmental Resource Permit (ERP)
Management (DERM)
– Class II
– To work within and over CSX right-of-way
25
Protection (FDEP)
(SFWMD)
26
27
Next Steps
28