Presentation to Citizens Transportation Advisory Committee of the - - PowerPoint PPT Presentation

presentation to citizens transportation advisory
SMART_READER_LITE
LIVE PREVIEW

Presentation to Citizens Transportation Advisory Committee of the - - PowerPoint PPT Presentation

Presentation to Citizens Transportation Advisory Committee of the Metropolitan Planning Organization February 20, 2013 FDOT DISTRICT 6 1 Existing Conditions/Deficiencies Safety and Operational Issues: poor horizontal and vertical


slide-1
SLIDE 1

1

Presentation to Citizens Transportation Advisory Committee

  • f the

Metropolitan Planning Organization

February 20, 2013 FDOT DISTRICT 6

slide-2
SLIDE 2

Existing Conditions/Deficiencies

  • Safety and Operational Issues: poor horizontal and vertical geometry, lane

continuity, etc.

  • Entrances/Exits Ramps: undesirable left hand entrance/exit ramps
  • Weaving: competing movements in a very short distance
  • Access: poor access to and from I-395
  • Clearances: low clearance from local streets to I-395

2

slide-3
SLIDE 3

PD&E Recommendations

  • Record of Decision (ROD) issued by FHWA on July 16, 2010
  • Alt. No. 3 approved as selected alternative
  • Improved geometric design
  • Eastbound and westbound elevated connector facilities
  • Right hand entrance and exit ramps to mainline

Begin Project End Project

3

slide-4
SLIDE 4

Commitments

  • Roadway vertical clearance west of FEC should be a minimum of 19

feet and east of FEC a minimum of 25 feet.

  • A minimum of 200 feet between the I-395 westbound bridge and the

Adrienne Arsht Center for the Performing Arts (AACPA) will be provided.

  • A minimum of 225 feet of column span length will be provided.
  • The Department commits to providing an aesthetically pleasing

bridge.

  • The

Department will provide aesthetics enhancements (e.g. landscaping) to help maximize the total integration of the project with the adjacent community.

  • Reconnect NW 2nd Avenue .

4

slide-5
SLIDE 5

Refinements to Alternative

  • Approved by FDOT D6 June 2012
  • Added additional thru lane in each direction from 2L to 3L.
  • Eliminated most design exceptions and variations.
  • Improved interchange at North Miami /NE 1st Aves. with I-395.
  • Length of “Aesthetic Pleasing Bridge” is approximately 600 feet total length.

Begin Project End Project

5

slide-6
SLIDE 6

Proposed Plan & Profile

6

NW 3 AVE NW 2 AVE FEC RR MIAMI AVE NE 1 AVE NE 2 AVE BISCAYNE BLVD METROMOVER 19.0’ 23.4’ 24.0’ 25.3’ 29.6’ 20.2’ 28.5’

RAMPS AT N MIAMI / NE 1 ST AVE

slide-7
SLIDE 7

Right-of-Way Impacts

  • Total of 70 Fee Simple Parcels and 15 Permanent

Easements required for project.

  • Twenty-eight parcels acquired to-date.
  • Right-of-way funded thru FY 2015.

7

slide-8
SLIDE 8

Public Involvement

  • Initial presentation to the MPO on December 8, 2011
  • Five Technical Advisory Committee (TAC) and Four Project

Advisory Group (PAG) meetings held to-date.

  • Two presentations to Miami-Dade County’s Transportation

Aesthetic Review Committee (TARC)

  • Project meetings with City of Miami, City of Miami Beach,

Downtown Development Authority (DDA) and Miami Community Redevelopment Agency (CRA)

  • Website and Project Branding
  • Outreach office- 1015 NW 3 rd Ave, Miami
  • Public workshop- April 2013

8

slide-9
SLIDE 9

Visual Quality Process

9

  • Objectives: Balance Cost, Engineering,

Architecture, Constructibility and Community Expectations

  • Steps Taken:
  • Developed Corridor Character
  • Received Input from TAC, PAG and Community
  • Established Selection Criteria
  • Developed Bridge Type Alternatives
slide-10
SLIDE 10

Bridge/Structures Design

  • Main Span ~ 600 ft x 2 = 1,200 FT
  • Main Span Length was optimized to manage total project construction

cost

  • Avoid curved alignment
  • Main Span Approaches ~ 8,000 ft
  • Connectors & Ramps ~ 11,000ft

10

slide-11
SLIDE 11

Approach Structures

  • Box Girders (Single or dual box)

11 Approach Span – 10ft deep Girder Approach Span – 8ft to 17.5ft varying depth Girder

slide-12
SLIDE 12

Main Span Designs

  • Fifteen different design concepts presented to TAC and

PAG

  • TAC- FDOT District 6 and Central Office
  • PAG- Major Stakeholders within project area
  • Based on five TAC and four PAG meetings held, the

following four designs have been recommended:

  • Infinity Arch
  • Wishbone Arch
  • Aesthetic Viaduct
  • Segmental Box

12

slide-13
SLIDE 13

Main Span : Infinity Arch

  • View : Looking East

13

slide-14
SLIDE 14

Main Span : Infinity Arch

  • Challenges
  • Complicated construction

sequence

  • Will require additional

phases to MOT

  • Overall Length
  • Suspended span

approximately 690 ft.

14

Total Cost = $ 739,577,926

slide-15
SLIDE 15

Main Span : Wishbone Arch

  • View : I-395 WB

15

slide-16
SLIDE 16

Main Span : Wishbone Arch

  • Challenges
  • Arches erected separately
  • Complicated foundation
  • Overall Length
  • Suspended span

approximately 600 ft.

16

Total Cost = $ 672,662,651

slide-17
SLIDE 17

Main Span : Aesthetic Viaduct

  • View : Southeast towards Biscayne Bay

17

slide-18
SLIDE 18

Main Span : Aesthetic Viaduct

  • Challenges
  • Fabrication of tower
  • Maintaining cables taut
  • ver time
  • Overall Length
  • Suspended spans

approximately 300 ft.

18

Total Cost = $ 604,280,740

slide-19
SLIDE 19

Main Span : Segmental Box

West along Biscayne Boulevard towards AACPA 19 PortMiami Bridge (segmental Box) Nighttime

slide-20
SLIDE 20

Main Span : Segmental Box

  • Overall Length
  • Main Span 300 ft.

20

Total Cost = $ 559,365,990

slide-21
SLIDE 21

Schedule of Milestones

  • Survey: Completed
  • Soil Testing: Completed
  • Traffic Analysis: Completed
  • Alignment: Completed
  • Public Involvement: On-Going
  • Draft Preliminary Plans: Submitted November 2012
  • Bridge Development Report (BDR)
  • Visual Quality Manual (VQM)
  • Various Component Sets
  • Final Preliminary (15%) Plans: April 2013
  • Hold Public Meeting: April 2013
  • Issue Draft Request For Proposal (RFP): June 2013
  • Complete Right of Way Acquisition: Fall 2014

21

slide-22
SLIDE 22

Questions?

I-395 Reconstruction

22

slide-23
SLIDE 23

Main Span : Segmental Box

West along Biscayne Boulevard towards AACPA 23 PortMiami Bridge (segmental Box) Nighttime