Lean Earthworks
Mrs Katarina Fidler & Mr Shane Betts,
Carillion Infrastructure
Presentation 1. Business Improvement strategy in Carillion - - PowerPoint PPT Presentation
Lean Earthworks Mrs Katarina Fidler & Mr Shane Betts, Carillion Infrastructure Presentation 1. Business Improvement strategy in Carillion Infrastructure: Lean Sigma on M6 Guards Mill Lean Sigma in company strategy
Mrs Katarina Fidler & Mr Shane Betts,
Carillion Infrastructure
Presentation
in Carillion Infrastructure:
M6 Guards Mill scope of works
Lean Sigma on M6 Guards Mill
£4.77m of efficiency savings
team on site
3% net benefit
Lean Sigma in company strategy
Building on M6 success…
Business Improvement strategy focused on
Capturing Lessons Learnt
Process Improvement
Best Practice / Lessons Learned EVIDENCE
Evidence Coordinators
Evidence Champion
Bid Submissions Adoption of Best Practice
Continuous Improvement Continuous Improvement
ROMS Lessons Learnt Submissions
Successes and Barriers
Cultural Barriers
Business Improvement strategy focused on
Successes and Barriers
People…Pace…Passion
Lessons Learnt so far
People…Pace…Passion
problem solving
M6 Extension – Carlisle to Guards Mill
Application of Lean Sigma
to Earthworks Logistics & Efficiency
Earthworks Efficiency Project
Quad of Aims
Defi ne
Success Criteria
Deliverables
Monitoring
Stakeholder Benefits
Purpose
movements in terms of cost per cubic meter
Debog (620 –1400) High Level Process Map
Access to Excavator
Tip Stone to Hole Dozer Stone to Hole Stockpile Stone
Load Dumper
Position and Load Dumper = 3.66 mins (25t exc)Load Dumper with Cut Material
Exc (40t) = 1.5 min/lL Exc (25t) = 3.5 min/LDrive to Tip Dump Cut Material Return to Site
Access to Hole
Stone Delivered Fill Needed Request Fill from Stock Wait Wait
No Yes Ave time leave excavator – return to excavator = 12 mins
Non – Value Adding Value Adding (Cut Process Value Adding (Fill Process)
Key
Yes No No Yes
Debog (620 –1400) High Level Process Map
Access to Excavator
Tip Stone to Hole Dozer Stone to Hole Stockpile Stone
Load Dumper
Position and Load Dumper = 3.66 mins (25t exc)Load Dumper with Cut Material
Exc (40t) = 1.5 min/lL Exc (25t) = 3.5 min/LDrive to Tip Dump Cut Material Return to Site
Access to Hole
Stone Delivered Fill Needed Request Fill from Stock Wait Wait
No Yes Ave time leave excavator – return to excavator = 12 mins
Non – Value Adding Value Adding (Cut Process Value Adding (Fill Process)
Key
Yes No No Yes
Opportunity for Improvement
Based on 170 cubes per hour from work study calcs Cubes Lost/Day Double handling Dumpers used to move stock (approx 2hrs/day) 340 @ £1.45 Additional plant (1 x 25 tonne excavator) Restricted Access for Plant/Deliveries Excavator waiting for Dumper (approx 50mins/day) 141 @ £1.45 Additional Waiting Time Waiting for replacement Plant Waiting for Documentation 340 @ £1.45 Waiting for Engineer Unforeseen Ground Conditions Smaller load capacity Deviation from normal working Rework NCR 0003 (30m x 30m excess dig) Other Fuel
Total Estimated Efficiency Loss
Total Cost £9860 £4140 £4089 ???? £493 ???? ???? ???? £1314 ????
£19,896
Current Performance…Daily Cost per Meter Cubed
Daily cost per cubic metre minus Tendered Value
Daily cost per cubic metre minus Tendered Value
Overall Cost/M3 4950 - 5600 (Debog)
£0.00 £5.00 £10.00 £15.00 £20.00 £25.00 *12-Oct 13-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 13-Nov 14-NovDate £/M3
Overall Cost per M3 Total Tendered RateOverall Cost/M3 620 - 1120 (Debog)
£0.00 £1.00 £2.00 £3.00 £4.00 £5.00 £6.00 £7.00 £8.00 £9.00 £10.00 12-Sep 13-Sep 14-Sep 15-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 09-Oct 10-Oct Date Cost/Cube Ave Cost per M3 per Day Tendered Rate£11.42/Metre Cubed
£3.08/Metre Cubed
Cubed
Measure Phase Conclusions
handling and therefore reduces capacity and additional plant – Erratic deliveries from quarry – Called off greater than capacity
reduces potential output – Restricted access to and from tip – Restricted access to excavation – Waiting for Wagons
force a change to normal working practice – Wrong Plant Size – Additional work e.g. deeper excavation
– Abandoned work and rework
be measured – Plant breakdown time – Documentation etc
Cause and Effect Diagram
Earthworks Reduced Efficiency
Method Planning Equipment
Inappropriate starting point for worksMaterials Environment People
M/C running over unsuitable ground Poor Planning Lack of understanding Cant load enough Not enough trucks Constrained access Excessive Excavator Movement Wrong Truck Location Constrained access Insufficient Working Hours (7.30Earthworks Efficiency Project Analysis of Data
D i stance R everse 200 150 100 50 160 140 120 100 80 60 40 20 S 17. 1298 R-Sq 78. 4% R-Sq(adj ) 77. 7% Fi tted Li ne P lProcess Outputs: Variation in the inputs will impact on these
Removal Wagons
Process inputs: These are the critical inputs which needed to be addressed. They affect productivity and cost
Analyse Phase Conclusions
be given when suspending works – Weather considered at planning meetings
quantities based on estimated capacity
to avoid
employed is critical to output – Balance with Excavator capability
possible – Alternate Work Methods
possible – Haul Routes
to nearest passing point – Lay bys – Turning Circles
Overproduction Waiting Movement Process Inventory Motion Defects
Overall Cost/M3 4020 - 4950
£0.00 £5.00 £10.00 £15.00 £20.00 £25.00 *23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 20-Nov 21-Nov 22-NovDate £/M3
Overall Cost per M3 Total Tendered Rate
Performance Improvements… ...Daily Cost per Meter Cubed
Daily cost per cubic meter versus Tendered Value No Earthworks due to Weather Lay-by Introduced
Landscape (2 Dumpers)
Removed.
Landscape (1 Dumper)
used due to Heavy Rain
Improve Phase
Work Flow Planning Sheet
Improve
Generic Process Steps Observed Cycle Times Observed Frequency Driving Distances in Meters Calculated Cycle Times for New Process Enter Plant and Labour Requirements
Work Balance Table
Set Out Work Fill or Cut Fill and Compact Cut and Remove to Tip Set Out Work Fill or Cut Fill and Compact Cut and Remove to Tip Set Out Work Fill and Compact Dig and Aside Remove to Landscape Set Out Work Fill and Compact Dig and Aside Remove to Landscape Set Out Work Cut or Fill Fill and Compact Cut and Remove to Landscape Set Out Work Cut or Fill Fill and Compact Cut and Remove to Landscape Set Out Work Fill and Compact Dig and Aside Remove to Tip Set Out Work Fill and Compact Dig and Aside Remove to Tip
Set Out Work Fill and Compact Dig and Aside to Landscape Set Out Work Fill and Compact Dig and Aside to Landscape
Examples of Different Workflows and their estimated outputs/cost at NB6 Adopted Method Not Possible at NB6 Possible at NB6 Possible at NB6 Possible at NB6
Estimated Cost/M3 at NB6 £ . 00 £ 1 . 00 £ 2 . 00 £ 3 . 00 £ 4 . 00 £ 5 . 00 £ 6 . 00 £ 7 . 00 £ 8 . 00 Proposed Method Total Capacity (M3/Day)Workshops
Earthworks Efficiency Project Benefits
to the Earthworks Processes
reduce the qty of imported fill
complaints of dirty roads
“The cultural spin offs from the process improvement activity employed at M6 Guards Mill are significant. Everyone expects to be challenged; doing it better tomorrow than we did it today is how we do things around here.” Chris Hayton, Project Director