City of Providence City of Providence Pavement Management Pavement Management Analysis Analysis Presented by: Vanasse Hangen Brustlin, Inc. April 27 , 2012 Presentation Overview Pavement Management Background C Process P ity of


slide-1
SLIDE 1

1

City of Providence City of Providence Pavement Management Pavement Management Analysis Analysis

Presented by: Vanasse Hangen Brustlin, Inc. April 27, 2012 C

Presentation Overview

  • Pavement Management Background

P

ity of Providence - Pavem

  • Process
  • Current Conditions
  • Budget Analysis
  • Project Selection
  • Next Steps

ment Management

  • Next Steps
slide-2
SLIDE 2

2

C

What is Pavement Management? What is Pavement Management?

Pavement Management Background

ity of Providence - Pavem

 The practice of planning for pavement maintenance

and rehabilitation with the goal of maximizing the value and life of a pavement network.

ment Management

Otherwise known as “Getting the Biggest Bang for Your Buck”

C

Pavement Management Background

Pavement Deterioration Curve Pavement Deterioration Curve

ity of Providence - Pavement Management Will cost $20.00 to $30.00 Here

slide-3
SLIDE 3

3

C

The Process The Process

Pavement Management Process

ity of Providence - Pavem

 Develop Pavement Management Database  Pavement distress identification and quantification

(Visual Inspection Only)

  • Performed in 1997, 2006, 2012 (partial)

 Refine Pavement Deterioration Curves  Pavement Condition Index (PCI) calculation on a 0 ‐100 scale

ment Management

 Define Treatment Options and Costs  Develop list of candidate projects  Apply engineering and local judgment to define annual road program

C

Average Roadway Pavement Condition Index = Average Roadway Pavement Condition Index = 67 67

Current Conditions

ity of Providence - Pavem

70 80 90 100

Condition Index (PCI) Do Nothing Routine Maintenance Preventive Maintenance

67

ment Management

40 50 60

Pavement Years Structural Improvement Base Rehabilitation

slide-4
SLIDE 4

4

C

Distribution of Conditions* Distribution of Conditions*

Current Conditions

ity of Providence - Pavem

20 30 40 50 60

14 9 12.3 51.0 38.0 25.8 42.6 45.5 51.3 37.8 16.4 41.0 12 5

Miles

ment Management

10 20

14.9 16.4 10.7 12.5

Pavement Condition Index

C

Current Roadway Pavement Backlog Summary Current Roadway Pavement Backlog Summary

Current Conditions

Backlog in Miles

ity of Providence - Pavem

Base Rehabilitation 89.66 Routine Maintenance 49.59 Do Nothing 22.81

Backlog in Miles ~400 City Maintained Miles Backlog in Dollars ~$140 Million

Base Rehabilitation $48,209,000 Preventative Maintenance $15,421,000 Routine Maintenance $2,073,000

ment Management

Structural Improvement 150.05 Preventative Maintenance 88.27 Structural Improvement $73,881,000

slide-5
SLIDE 5

5

C

Budget Analysis Budget Analysis

$8 Milli M i t i PCI

Budget Analysis

ity of Providence - Pavem

 $8 Million per year‐ Maintains PCI  $10 Million per year‐ Will increase Average PCI to 74

in 10 years

 $13 Million per year‐ Will increase Average PCI to 75

in 5 years.

ment Management C

Projected Pavement Condition Projected Pavement Condition

Budget Analysis

85

ity of Providence - Pavem

65 70 75 80

avement Condition Index

ment Management

55 60 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

Pa

$8M/Year $10M/Year $13M/Year

slide-6
SLIDE 6

6

C

Projected Backlog of Work Projected Backlog of Work

Budget Analysis

$200.0 s

ity of Providence - Pavem

$120.0 $140.0 $160.0 $180.0

Backlog Of Work

Millions

ment Management

$60.0 $80.0 $100.0 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 $8M/Year $10M/Year $13M/Year

C

 System uses Cost/Benefit Calculation to Prioritize Projects

Project Selection

ity of Providence - Pavem

 Factors Increasing Benefit  Traffic Volume  Lower Cost  Worse Condition (Lower PCI)  How Long the Repair Type is expected to last

ment Management

 Key Concepts  Repair roads before they fall into a more expensive

“treatment band”

 Fix the Roads used by the most people.

slide-7
SLIDE 7

7

C

 Determine Funding Level

Next Steps

ity of Providence - Pavem

 Utilize GIS to Coordinate Projects Geographically  Reduce Mobilization cost for contractors  “Neighborhood” Planning  Coordinate with Utility Companies

ment Management

 Perform Project Level Evaluations and Testing to

determine actual repair for each candidate street.

Questions & Answers

VHB Pavement Engineering Services Gordon Daring, PE and Lance Baden