presentation outline
play

Presentation Outline Project Background Analysis 1: Implementation - PowerPoint PPT Presentation

Presentation Outline Project Background Analysis 1: Implementation of MEP Prefabrication Analysis 2: Building Information Modeling Virtual Mockup Analysis 3: Precast Floor Planks Structural Breadth (Will Not Be Discussed)


  1. Presentation Outline • Project Background • Analysis 1: Implementation of MEP Prefabrication • Analysis 2: Building Information Modeling – Virtual Mockup • Analysis 3: Precast Floor Planks • Structural Breadth (Will Not Be Discussed) • Analysis 4: Solar Photovoltaic (PV) Panels • Electrical Breadth • Summary • Acknowledgements

  2. Project Background

  3. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Project Background Williamstown, MA PRESENTATION OUTLINE Project Background • Location • Analysis 1: Implementation of • 225 South Street, Williamstown, MA 01267 • MEP Prefabrication Museum/Institutional • Analysis 2: BIM – Virtual • Mockup • Building Parameters 78,800 SF • Analysis 3: Precast Floor Planks • 68,150 SF Gross Building Area • Analysis 4: Solar PV Panels • Electrical Breadth • Museum Building Parameters • Summary Cost: $28 Million – GMP • • Delivery Method: Design – Bid – Build • Acknowledgements • Schedule: Jan 2011 – Sep 2013 • Architect: Tadao Ando •

  4. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Project Background Williamstown, MA PRESENTATION OUTLINE Project Background • Analysis 1: Implementation of • MEP Prefabrication CIP Structure • Analysis 2: BIM – Virtual • Glazed Aluminum Curtain Wall On • Mockup The First Floor Analysis 3: Precast Floor Planks • PLANT • Construction Phases: Analysis 4: Solar PV Panels • Electrical Breadth • Plant • VECC • Summary • VECC Acknowledgements •

  5. Analysis 1 MEP Prefab

  6. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 1: Implementation of MEP Prefabrication Williamstown, MA PRESENTATION OUTLINE The Problem The Goal Project Background • Analysis 1: Implementation of • Embedded piping has to be within the • Increase accuracy and efficiency. • MEP Prefabrication middle third of the matslab (30”). Problem & Goal • Put the schedule back on track. • Long runs with 1/8” of pitch exceeds • Analysis 2: BIM – Virtual 10”. • Potential cost savings. • Mockup Constructability issues, intense rebar. • Project is behind schedule. • Analysis 3: Precast Floor Planks • Analysis 4: Solar PV Panels • Electrical Breadth • Summary • Acknowledgements •

  7. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 1: Implementation of MEP Prefabrication Williamstown, MA Coordination with Other Trades PRESENTATION OUTLINE Quantity Take-Off Project Background • Analysis 1: Implementation of • Bracket Know what is in the system. • MEP Prefabrication Utilizing 3D Model • How the units will be divided. • Quantity Take-Off • Clash Detection. • Understand Constraints & • Site Challenges • In Slab System Location. • Coordination Complications • Threaded Where plumbing would penetrate slab. • Max. size of a single unit due to • Analysis 2: BIM – Virtual • Exact locations reduces conflicts between trades • Bars transportation limitations. Mockup Analysis 3: Precast Floor Planks • Site Challenges Analysis 4: Solar PV Panels • Electrical Breadth • Intensive amount of rebar. Summary • • Iron Angle Pipe penetration through slab to connections • Acknowledgements • • Lay, Support, and achieve required Pitch.

  8. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 1: Implementation of MEP Prefabrication Williamstown, MA Prefab Cost Savings PRESENTATION OUTLINE Prefab Schedule Savings Project Background • Current System Percent Time Analysis 1: Implementation of • Final Results: • Activity Prefab Duration MEP Prefabrication Duration Savings Cost & Schedule • Time savings of general conditions cost and critical path. Current Prefab • Area 1 7 3.5 Days 50% Analysis 2: BIM – Virtual • $14,611 of GC. • Area 2 7 3.5 Days 50% Total Tot: $71,680 Tot: $35,840 Mockup Area 3 7 3.5 Days 50% $35,840 of labor. • Total Savings N/A 50% Area 4 7 3.5 Days 50% Analysis 3: Precast Floor Planks • Total 28 Days 14 Days 50% Total: $57,771. • Analysis 4: Solar PV Panels • Total N/A 3.5 Days 12.5% Electrical Breadth • Savings Summary • Acknowledgements •

  9. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 1: Implementation of MEP Prefabrication Williamstown, MA PRESENTATION OUTLINE Conclusion & Recommendation Project Background • Analysis 1: Implementation of • It is best to apply the analysis on the building to save time and • Congestion reduction. • MEP Prefabrication Conclusion & • money. Enhanced safety in the building footprint. • Recommendation “3.5” Critical path savings. • Analysis 2: BIM – Virtual • Mockup Total of $57,771 of cost savings. • Analysis 3: Precast Floor Planks • Analysis 4: Solar PV Panels • Electrical Breadth • Summary • Acknowledgements •

  10. Analysis 2 BIM - Virtual Mockup

  11. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 2: BIM – Virtual Mockup Williamstown, MA PRESENTATION OUTLINE The Problem The Goal Project Background • Analysis 1: Implementation of BIM utilized only in 3D clash detection. • • Increase efficiency. • MEP Prefabrication More BIM uses can BIM used. • Add value to the owner and to the building. • Analysis 2: BIM – Virtual • Mockup Supporting the physical Mockup will be built. • Problem & Goal • Analysis 3: Precast Floor Planks • Analysis 4: Solar PV Panels • Electrical Breadth • Summary • Acknowledgements •

  12. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 2: BIM – Virtual Mockup Williamstown, MA PRESENTATION OUTLINE Initial Use of BIM How Can Virtual Mockup Help? Project Background • Analysis 1: Implementation of • 3D Clash detection. • Quantity take off. • MEP Prefabrication To coordinate complex MEP’s • Resolving design issues (Architect). • embedded in the matslab. Analysis 2: BIM – Virtual • Mockup Started on August 2011. • Aids any project’s system prefabrication (GC). • Initial Use • How Can VM Help? Minimizes RFI’s and COR’s. • • Analysis 3: Precast Floor Planks Building the project twice (GC & Subs). • • Opportunity for the owner to walkthrough virtually. Analysis 4: Solar PV Panels • • Electrical Breadth • Summary • Acknowledgements • Image courtesy of Google images.

  13. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 2: BIM – Virtual Mockup Williamstown, MA PRESENTATION OUTLINE Keep in Mind The Process Project Background • Analysis 1: Implementation of • Start in the early stages of the project. • Modeling software (AutoCAD 2012). • MEP Prefabrication Need to be developed though out the • Rendering software (3ds Max Design 2012). • project. Analysis 2: BIM – Virtual • Mockup Ability to manipulate. • Choose a section. • The Process • Determining what is in the section. • Analysis 3: Precast Floor Planks • Analysis 4: Solar PV Panels • Electrical Breadth • Summary • Acknowledgements • Image courtesy of Google images.

  14. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 2: BIM – Virtual Mockup Williamstown, MA Foreman Foreman Wage Interpretation Time PRESENTATION OUTLINE Feedback Cost Benefits Trade ($/Hr) Savings (2 Hrs) Project Background • Concrete $55.20 $110.40 Iron $83.08 $166.16 Analysis 1: Implementation of • Tagging and tracking. • Time it Professional to take 50% MEP Prefabrication Plumbing $75.72 $151.43 Future maintenance. • Professional took me to of the time Future renovations. • Glazing $54.43 $108.86 Task Analysis 2: BIM – Virtual • Wage ($/Hr) model Mockup Gypsum $66.18 $132.36 (Hrs.) Cost Benefits • (Hrs.) Boards Determining a Analysis 3: Precast Floor Planks • 1 $97 ½ $48.5 Gutter $83.08 $166.16 section to model Sheeting $66.18 $132.35 Analysis 4: Solar PV Panels • Determining Electrical Breadth • Metal Panels $83.08 $166.16 What is in the 8 $97 3 $291 Roofer $66.18 $132.35 Summary • section Wood $45.38 $90.76 Section Acknowledgements • 40 $97 15 $1,455 Flooring modeling Sealants $44.30 $88.60 Total 49 $97 18 ½ $1,795 WaterProofing $54.43 $108.86 Total $1,554.45

  15. The Sterling and Francine Clark Art Institute Mohamed Alali, CM Analysis 2: BIM – Virtual Mockup Williamstown, MA PRESENTATION OUTLINE Conclusion & Recommendation Project Background • Analysis 1: Implementation of • Go with virtual mockup to fix issues in advance and better • Increased efficiency. • MEP Prefabrication experience the building. Increased coordination. • Analysis 2: BIM – Virtual • Mockup Will benefit the owner in future restaurant. • Less RFI’s and COR’s. • Conclusion & • Recommendation Very low cost, do both. • Better for future renovations and • Analysis 3: Precast Floor Planks • maintenance. Analysis 4: Solar PV Panels • Costs $240.55 • Electrical Breadth • Virtual Mockups has limitations. • Summary • Acknowledgements • Image courtesy of Google images.

  16. Analysis 3 Precast Roof Planks

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend