Presentation of CEI Services for Wiles Road from Riverside Drive to Rock Island Road Broward County, FL RLI NO. J211239P1 Wiles Road II Wiles Road II Outline Eisman & Russos Experience I. Experience and Qualifications with Roadway


slide-1
SLIDE 1

Presentation of CEI Services for Wiles Road from Riverside Drive to Rock Island Road Broward County, FL

RLI NO. J211239P1

slide-2
SLIDE 2

Wiles Road II Where Commitment And Action Meet

I. Experience and Qualifications with Roadway Construction

  • a. Eisman & Russo
  • b. Individual Team Members
  • II. Construction Management Approach
  • a. Scope
  • b. Utility
  • c. Coordination
  • d. Environmental
  • III. Challenges and Solutions
  • a. Scope
  • b. Utility
  • c. Coordination
  • d. Environmental

Outline

Wiles Road II

Eisman & Russo’s Experience

  • Principal with Eisman & Russo
  • Over 20 Years in South East Florida
  • Largest CEI Division of Eisman & Russo
  • Extensive FDOT Roadway Construction
  • Broward County Highway Engineering
  • Municipal Roadway Construction

Experience and Qualifications

slide-3
SLIDE 3

Eisman & Russo’s Experience

Pembroke Road from SW 145th Avenue to Silver Shore Boulevard Broward, County

Experience and Qualifications Wiles Road II

SR-7/US 441 Reconstruction from Fillmore Street to Stirling Road Broward, County NW 57th Avenue/Red Road From Okeechobee Boulevard to West 29st Street. Miami Dade, County Education Corridor Improvements, Coconut Creek. Broward, County

slide-4
SLIDE 4

Team Member’s Experience

Experience and Qualifications Wiles Road II

Organization Chart

CEI Project Manager

  • J. Scott Gombar, P. E.

Senior Project Engineer Leo Offredi, P. E. Contract Compliance/Administrative Assistant Marielena Gombar Project Engineer Guillermo Villanueva, EI Senior Inspectors Kyle Wann William Rhoades Inspector Peter S. McIntosh QA/QC Team

  • J. Scott Gombar, P. E.

Ido Shimony, P. E. Chris Charvat

Broward County HCED Project Manager

Manuel Fontan, P.E. Testing Lab – GCES Engineering Services (CBE) Survey – Aylward Engineering & Survey (CBE) Aerial Photograph – Smith Aerial Photograph

slide-5
SLIDE 5

Team Member’s Experience

Experience and Qualifications Wiles Road II

Eisman & Russo, Inc. FDOT Prequalification 10.1 Roadway Construction Engineering Inspection

CTQP Final Estimates 1 CTQP Final Estimates 2 CTQP Asphalt Paving Level 1 CTQP Asphalt Paving Level 2 CTQP Earthwork Level 1 CTQP Earthwork Level 2 Nuclear Radiation Safety CTQP Concrete / ACI Level 1 CTQP Drilled Shaft Inspection CTQP QC Manager FDOT Critical Structures NPDES Florida Advanced MOT IMSA Traffic Signal Technician 1 IMSA Traffic Signal Inspector

Position CEI Staff Project Manager

  • J. Scott Gombar, P. E.

       

Senior Project Engineer Leo Offredi, P. E.

              

Project Engineer Guillermo Villanueva, E.I.

   S          S S

Senior Roadway Inspectors KyleWann

            S

William Rhoades

              

Roadway Inspectors Peter McIntosh

            S

S = Scheduled

Qualifications/Certifications

slide-6
SLIDE 6

Experience and Qualifications Wiles Road II

Leonardo Offredi, P.E. – Senior Project Engineer

 16 years of experience in bridge and roadway construction  Identical current experience to Wiles II project  Experience working with Broward County / No learning curve  Experience working with FPL, FPL Fibernet, AT&T, TECO, Comcast, Broward County Traffic, SBDD, SFWMD  Experience with Complete Streets  Takes Ownership of Project  Establish Project Specific Goals  Manage Schedule and Budget

Team Member’s Experience

slide-7
SLIDE 7

Wiles Road II

Team Member’s Experience

Roadway Construction Experience Drainage Earthwork Asphalt Signalization Lighting Utility Relocation

SR-7 Reconstruction from Fillmore Street to Stirling Rd. X X X X X X Pembroke Road from SW 145th Avenue to Silver Shores X X X X X X I75 Express Lanes Segment D X X X X X X NW 135th Street, Opa-Locka X X X X X X

Leo Offredi, P.E.

Experience and Qualifications

slide-8
SLIDE 8

Experience and Qualifications Wiles Road II

Team Member’s Experience

Guillermo Villanueva, EI –Project Engineer

 11 years of experience in bridge and roadway construction  CEI Project Engineer for I-75 Express lanes Project  Contractor Project Engineer/Manager  Successful partnering with Contractor  Established trust with Contractor  Has worked on numerous road and bridge projects with construction costs from $32-$86 M  Experience working with FPL, Broward County Traffic, SBDD, SFWMD  Experience in Scheduling Review  Monthly Pay Requisitions

slide-9
SLIDE 9

Experience and Qualifications Wiles Road II

Team Member’s Experience

Roadway Construction Experience Drainage Earthwork Asphalt Signalization Lighting Utility Relocation

SR 826 Palmetto Expressway (Coral Way 24th St. to Tamiami Trail 8th St. ) X X X X X X Beach Blvd./Kernan Blvd. Interchange X X X X X X SR 589 Veterans Expressway X X X X X X I75 Express Lanes Segment D X X X X X X

Guillermo Villanueva, EI

slide-10
SLIDE 10

Experience and Qualifications Wiles Road II

Inspection Staff

 Kyle Wann

 8 years of Experience  Senior Inspector for Pembroke Road Project

 William Rhoades

 21 years of Experience  Senior inspector for Education Corridor Improvements in Coconut Creek

 Peter McIntosh

 18 years of Experience

 Earthwork specialist for I-75 express lanes and Eller Drive projects  Tested and inspected over 25,000 LF of drainage and 426 drainage structures

Team Member’s Experience

slide-11
SLIDE 11

Wiles Road II I. Experience and Qualifications

  • II. Construction Management Approach
  • III. Challenges and Solutions
slide-12
SLIDE 12

Construction Management Approach

Wiles Road II

I. Scope

  • Traffic Control Phasing
  • Drainage
  • Widening
  • Milling and Resurfacing
  • Signalization and Lighting
  • Complete Streets

II. Utilities

  • FPL
  • FPL Fibernet
  • AT&T
  • TECO Gas
  • Comcast
  • City of Coral Springs
  • Advanced Cable

III. Coordination

  • MOT
  • Adjacent Project
  • Motorists Traffic
  • Pedestrian Traffic
  • Business Access
  • Stakeholders
  • Homeowners Associations
  • Business
  • Broward County Transit / Broward County Schools
  • Emergency Services

IV. Environmental

  • Red Lichen Sanctuary
  • NPDES
slide-13
SLIDE 13

Construction Management Approach

Wiles Road II

Scope

Traffic Control Phasing

Phase I Phase II Phase III Phase IV

slide-14
SLIDE 14

Construction Management Approach

Wiles Road II

Scope

Drainage

  • 2,400 feet of Drainage Pipe
  • Connecting to Existing Drainage
  • New Drainage
  • 1,000 feet of French Drain
slide-15
SLIDE 15

Construction Management Approach

Wiles Road II

Scope

Widening Earthwork Curb and Gutter Sidewalk Construction Gravity wall construction

slide-16
SLIDE 16

Construction Management Approach

Wiles Road II

Scope Milling and Resurfacing Overbuild Straightedge and Cross Slope Control

slide-17
SLIDE 17

Construction Management Approach

Wiles Road II

Scope Signalization and Lighting Riverside Intersection

  • W. Leiter Intersection

Lighting installation on North side of project

slide-18
SLIDE 18

Construction Management Approach

Wiles Road II

Utilities

  • FPL
  • FPL Fibernet
  • AT&T
  • TECO Gas
  • Comcast
  • City of Coral Springs
  • Advanced Cable
slide-19
SLIDE 19

Construction Management Approach

Wiles Road II

Coordination

  • MOT
  • Adjacent Project
  • Motorists Traffic
  • Pedestrian Traffic
  • Business Access
slide-20
SLIDE 20

Construction Management Approach

Wiles Road II

Coordination

  • Stakeholders
  • Broward County
  • EOR
  • Homeowners Associations
  • Business
  • Broward County Transit
  • Broward County Schools
  • Emergency Services
slide-21
SLIDE 21

Construction Management Approach

Wiles Road II

Environmental

Red Lichen Sanctuary / NPDES

slide-22
SLIDE 22

Wiles Road II I. Experience and Qualifications II. Construction Management Approach

  • III. Challenges and Solutions

i. Scope ii. Utilities III. Coordination IV. Environmental

slide-23
SLIDE 23

Wiles Road II

Challenges and Solutions

Scope

  • Challenge:
  • Drainage Structure S-417
  • Conflict with Utilities
  • Solution:
  • Drainage
  • Communication between

contractor and utility companies/agencies

slide-24
SLIDE 24

Wiles Road II

Challenges and Solutions

Scope

  • Challenge:
  • Milling and Resurfacing
  • Straight edge deficiencies at manholes
  • Solution:
  • Milling and Resurfacing
  • Inspection staff to measure manhole lid

elevation at all locations

slide-25
SLIDE 25

Wiles Road II

Challenges and Solutions

Scope

  • Challenge:
  • Signalization
  • Plans do not include existing signal for Pedestrian

between E. Leitner and NW 74thAvenue

  • Solution:
  • Signalization
  • Coordinate with EOR before project commences
slide-26
SLIDE 26

Wiles Road II

Challenges and Solutions

Utilities

  • Challenge:
  • Installation of new concrete

FPL poles from west project limit to 255+00 (1600 feet)

  • Solution:
  • Review Commitments with County
  • Review Utility Work Schedules
  • Pre-Activity meeting with utilities and contractor
  • Utilities participate Progress meetings
slide-27
SLIDE 27

Wiles Road II

Challenges and Solutions

Coordination

  • Challenge:
  • Phasing coordination with existing Wiles Rd

project

  • Lane closure conflict with existing Wiles Rd

project

  • Solution:
  • Invite CEI and Contractor of Wiles Rd I project
  • First item of discussion is MOT Coordination

between Projects

MOT

slide-28
SLIDE 28

Wiles Road II

Challenges and Solutions

Coordination

  • Challenge:
  • Mast arm at NE Corner of W. Leitner (Whispering Woods

Association)

  • Solution:
  • Set up Field Meetings with Contractor and include

Stakeholders

Stakeholders

slide-29
SLIDE 29

Wiles Road II

Challenges and Solutions

Environmental

  • Challenge:
  • Red Lichen Sanctuary
  • Slurry Drill Shaft
  • Solution:
  • Daily inspection of BMP’s and Storm Water

Pollution Prevention Plan

  • Coordinate with Contractor to ensure drill shaft

slurry will be handled properly

slide-30
SLIDE 30

Wiles Road II