Ravine Park Prescribed Burn Stakeholder Meeting March 11, 2020 Meeting Agenda CRP Services Project Background Causes of Altered Hydrology Sgt. Floyd Monument


slide-1
SLIDE 1

Ravine Park Prescribed Burn

Stakeholder Meeting – March 11, 2020

slide-2
SLIDE 2

Meeting Agenda

slide-3
SLIDE 3

CRP Services

– – –

slide-4
SLIDE 4

Project Background

slide-5
SLIDE 5

Causes of Altered Hydrology

  • First Brides

Grave

  • Sgt. Floyd

Monument First Brides Grave Looking North (undated) Looking South (approx. 1900)

slide-6
SLIDE 6

Watershed – 1930s

slide-7
SLIDE 7

Watershed – Present Day

slide-8
SLIDE 8

Solutions to Restore Watershed Hydrology

slide-9
SLIDE 9
  • Ecosystem Restoration at Ravine Park

Before After

slide-10
SLIDE 10

Ecosystem Restoration at Ravine Park

Ravine Park Timberhill Oak Savanna (Decatur County)

slide-11
SLIDE 11
  • Ecosystem Restoration at Ravine Park

Ravine Park Timberhill Oak Savanna (Decatur County)

slide-12
SLIDE 12

Prescribed Burning

– – – – –

slide-13
SLIDE 13

Prescribed Burning

– – – – – –

slide-14
SLIDE 14

Prescribed Burning

slide-15
SLIDE 15

Additional Resources

slide-16
SLIDE 16
  • Public Notifications
slide-17
SLIDE 17

Project Timeline

JEO Hired

July 2019

Burn Coordination Begins

August 2019

  • Sept. 2019 – Feb. 2020
  • Contracting Process
  • Burn Planning

CRP Services Hired

  • Stakeholder Meeting
  • Public Open House
  • Burn Plan Approval
  • Install Control Lines

March 2020

  • Jan. 2020

Burn Coordination Begins

Spring or Fall 2020

Possible Burn Windows