Preparing a long term management plan for the future of the Slufter - - PowerPoint PPT Presentation

preparing a long term management plan for the future of
SMART_READER_LITE
LIVE PREVIEW

Preparing a long term management plan for the future of the Slufter - - PowerPoint PPT Presentation

Preparing a long term management plan for the future of the Slufter An analysis of the functional, spatial and geotechnical possibilities Roderik Heerema, MSc Wednesday October 24, 2012 Content Introduction The Port of Rotterdam


slide-1
SLIDE 1

Preparing a long term management plan for the future of the Slufter

An analysis of the functional, spatial and geotechnical possibilities

Roderik Heerema, MSc Wednesday October 24, 2012

slide-2
SLIDE 2

Content

  • Introduction
  • The Port of Rotterdam
  • Contaminated dredged material management in the

Netherlands

  • The Slufter
  • Conclusions
slide-3
SLIDE 3

Introduction

slide-4
SLIDE 4

DEME

Introduction

slide-5
SLIDE 5

Introduction

slide-6
SLIDE 6

Introduction

slide-7
SLIDE 7

Introduction

slide-8
SLIDE 8

The Port of Rotterdam

slide-9
SLIDE 9

The Port of Rotterdam

slide-10
SLIDE 10

The Port of Rotterdam

  • Every year:

– €500 Million Turnover – 430 million tons of goods throughput – 34,000 ocean going vessels and 100,000 inland vessels – Third largest port in the world

  • Expanding…
slide-11
SLIDE 11

The Port of Rotterdam Maasvlakte 2

slide-12
SLIDE 12

Contaminated dredged material management in the Netherlands

  • 3 to 5 million cubic meters of contaminated material dredged

yearly

  • Several facilities…
  • Total remaining storage capacity 85 million cubic meters
  • Enough for the next 32 years

Hollandsch Diep Ijseloog The Slufter

slide-13
SLIDE 13

The Slufter | CDF

  • Large scale Confined Disposal Facility
  • Built in 1987
  • Storage of contaminated dredged material
slide-14
SLIDE 14

The Slufter | Location

slide-15
SLIDE 15

The Slufter | Dimensions

6km 2km 260ha 3.7 miles 1.2 miles 642 acres

slide-16
SLIDE 16

The Slufter | Dimensions

NAP +24m NAP +6m NAP +2m NAP -28m

Dredged material

NAP

52m 30m

Total capacity 150 million m3

171 ft 98 ft 196 yd³

slide-17
SLIDE 17

The Slufter | History

  • Why it was built
  • The “Rhine Research Project”
  • The Slufter through the years…
slide-18
SLIDE 18

The Slufter | History

slide-19
SLIDE 19

The Slufter | Today

The Slufter is increasingly losing its function

  • Reduced supply of contaminated dredged material

– Expected lifetime in 1987 was 15 years – More than 24 years later only 50% has been filled

  • Overcapacity
  • Surplus of space which is not ready for use
slide-20
SLIDE 20

The Slufter | Functions

slide-21
SLIDE 21

The Slufter | Functions

slide-22
SLIDE 22

The Slufter

  • Building on dredged material

– Clay and silt particles – Very low bearing capacity

Dredged material Retaining structure New land Remaining storage capacity

A Geotechnical Challenge

slide-23
SLIDE 23

The Slufter

A Geotechnical Challenge

slide-24
SLIDE 24

The Slufter

400m

A Geotechnical Challenge

slide-25
SLIDE 25

The Slufter

A Geotechnical Challenge

slide-26
SLIDE 26

The Slufter

A Geotechnical Challenge

slide-27
SLIDE 27

The Slufter

The principle of dry storage

  • 1. Remove water sheet and lower ground water level
  • 2. Initiate a process of ripening dredged material
  • 3. Obtain a layer with sufficient bearing capacity

Ripened dredged material Dredged material

A Geotechnical Challenge

slide-28
SLIDE 28

The Slufter

A Geotechnical Challenge

slide-29
SLIDE 29

The Slufter | Solution

A long term approach

– Use the incoming supply of dredged material as elevation material – Elevate until the layer has sufficient bearing capacity and develop from thereon – Lower the ring-dike – Move towards a phased dismantlement of the Slufter

slide-30
SLIDE 30

30ha 2017 2022 2032 60ha 120ha

slide-31
SLIDE 31

Conclusions

  • Accept the current situation!
  • Initiate dry storage!
  • Use the space!
  • Create value!
slide-32
SLIDE 32

Questions?