SLIDE 1
Preparing a long term management plan for the future of the Slufter
An analysis of the functional, spatial and geotechnical possibilities
Roderik Heerema, MSc Wednesday October 24, 2012
SLIDE 2 Content
- Introduction
- The Port of Rotterdam
- Contaminated dredged material management in the
Netherlands
SLIDE 3
Introduction
SLIDE 4
DEME
Introduction
SLIDE 5
Introduction
SLIDE 6
Introduction
SLIDE 7
Introduction
SLIDE 8
The Port of Rotterdam
SLIDE 9
The Port of Rotterdam
SLIDE 10 The Port of Rotterdam
– €500 Million Turnover – 430 million tons of goods throughput – 34,000 ocean going vessels and 100,000 inland vessels – Third largest port in the world
SLIDE 11
The Port of Rotterdam Maasvlakte 2
SLIDE 12 Contaminated dredged material management in the Netherlands
- 3 to 5 million cubic meters of contaminated material dredged
yearly
- Several facilities…
- Total remaining storage capacity 85 million cubic meters
- Enough for the next 32 years
Hollandsch Diep Ijseloog The Slufter
SLIDE 13 The Slufter | CDF
- Large scale Confined Disposal Facility
- Built in 1987
- Storage of contaminated dredged material
SLIDE 14
The Slufter | Location
SLIDE 15
The Slufter | Dimensions
6km 2km 260ha 3.7 miles 1.2 miles 642 acres
SLIDE 16 The Slufter | Dimensions
NAP +24m NAP +6m NAP +2m NAP -28m
Dredged material
NAP
52m 30m
Total capacity 150 million m3
171 ft 98 ft 196 yd³
SLIDE 17 The Slufter | History
- Why it was built
- The “Rhine Research Project”
- The Slufter through the years…
SLIDE 18
The Slufter | History
SLIDE 19 The Slufter | Today
The Slufter is increasingly losing its function
- Reduced supply of contaminated dredged material
– Expected lifetime in 1987 was 15 years – More than 24 years later only 50% has been filled
- Overcapacity
- Surplus of space which is not ready for use
SLIDE 20
The Slufter | Functions
SLIDE 21
The Slufter | Functions
SLIDE 22 The Slufter
- Building on dredged material
– Clay and silt particles – Very low bearing capacity
Dredged material Retaining structure New land Remaining storage capacity
A Geotechnical Challenge
SLIDE 23
The Slufter
A Geotechnical Challenge
SLIDE 24 The Slufter
400m
A Geotechnical Challenge
SLIDE 25
The Slufter
A Geotechnical Challenge
SLIDE 26
The Slufter
A Geotechnical Challenge
SLIDE 27 The Slufter
The principle of dry storage
- 1. Remove water sheet and lower ground water level
- 2. Initiate a process of ripening dredged material
- 3. Obtain a layer with sufficient bearing capacity
Ripened dredged material Dredged material
A Geotechnical Challenge
SLIDE 28
The Slufter
A Geotechnical Challenge
SLIDE 29
The Slufter | Solution
A long term approach
– Use the incoming supply of dredged material as elevation material – Elevate until the layer has sufficient bearing capacity and develop from thereon – Lower the ring-dike – Move towards a phased dismantlement of the Slufter
SLIDE 30
30ha 2017 2022 2032 60ha 120ha
SLIDE 31 Conclusions
- Accept the current situation!
- Initiate dry storage!
- Use the space!
- Create value!
SLIDE 32
Questions?