potomac yard land bay e arlington virginia
play

Potomac Yard Land Bay E Arlington, Virginia Drew Heilman - PowerPoint PPT Presentation

Potomac Yard Land Bay E Arlington, Virginia Drew Heilman Construction Management April 12, 2010 Potomac Yard Land Bay E Arlington, Virginia Presentation Outline Project Overview Implementation of Solyndra PV System


  1. Potomac Yard Land Bay E Arlington, Virginia Drew Heilman │ Construction Management │ April 12, 2010

  2. Potomac Yard Land Bay E Arlington, Virginia Presentation Outline • Project Overview • Implementation of Solyndra PV System (Electrical Breadth) • Implementation of Curtain Wall System (Mechanical Breadth) • Implementation of Chilled Beams (Critical Industry Issue) • Conclusions and Recommendations • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

  3. Potomac Yard Land Bay E Arlington, Virginia Project Overview: Presentation Outline • Two Tower Office Building with Underground Parking • 9-Story 370,000 S.F. Office Space • Project Overview • 3 P-Levels – 235,000 S.F., 600 parking spaces • Implementation of Solyndra PV System (Electrical Breadth) • Cost: $75 million Negotiated GMP • Implementation of Curtain Wall System (Mechanical Breadth) • Duration: 20 months, 1/2/08 - 9/30/09 • Implementation of Chilled Beams (Critical Industry Issue) • Design-Bid-Build • Conclusions and Recommendations • LEED Gold • Acknowledgements and Questions • White TPO Roof • Two Building Facades • Cast-In-Place Concrete Structure • Forced air VAV mechanical system Drew Heilman │ Construction Management │ April 12, 2010

  4. Potomac Yard Land Bay E Arlington, Virginia Presentation Outline Location: • Project Overview • Arlington, VA • Implementation of Solyndra PV System (Electrical Breadth) • Regan National Airport • Implementation of Curtain Wall System (Mechanical Breadth) • US Rte. 1 • Implementation of Chilled Beams (Critical Industry Issue) • George Washington Memorial • Conclusions and Recommendations Parkway • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

  5. Potomac Yard Land Bay E Arlington, Virginia Owner: Meridian Group President & CEO: James Daivis Presentation Outline General Contractor: James G. • Project Overview Davis Construction Vice President: James Dugan • Implementation of Solyndra PV System (Electrical Breadth) • Implementation of Curtain Wall System (Mechanical Breadth) Architect: Davis, Carter, Scott • Implementation of Chilled Beams (Critical Industry Issue) LTD. Sr. Project Sr. Layout Project Manager: Ben Engineer: Mike Superintendent: Apfellbaum O'Neil Jim Keglovich • Conclusions and Recommendations MEP Engineer: Allen & Shariff • Acknowledgements and Questions Corporation Project Manager: Project Manager: Superintendent: Meghan Callahan Scott Rhoades Fred Dandeneau Glazing: TSI/ Exterior Wall Systems, Inc. APM: Robert APM: Steve Assistant Super.: Forbes Ghent Andrew Fisher Drew Heilman │ Construction Management │ April 12, 2010

  6. Potomac Yard Land Bay E Arlington, Virginia Purpose for Analyses Presentation Outline • Energy conservation • Project Overview • Solyndra PV System • Implementation of Solyndra PV System (Electrical Breadth) • Chilled Beam Mechanical System • Implementation of Curtain Wall System (Mechanical Breadth) • Implementation of Chilled Beams (Critical Industry Issue) • Schedule Acceleration • Conclusions and Recommendations • Curtain Wall System • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

  7. Potomac Yard Land Bay E Arlington, Virginia Opportunity • Need for energy conservation Presentation Outline • Over 50% of US energy consumption in commercial buildings • Project Overview • Unusable rooftop area • Implementation of Solyndra PV System (Electrical Breadth) • Implement a solar collection system • Implementation of Curtain Wall System (Mechanical Breadth) • Solyndra PV System • Implementation of Chilled Beams (Critical Industry Issue) • Great for application with existing white TPO roof • Conclusions and Recommendations Goal • Determine advantages • Acknowledgements and Questions • Reduce building’s energy consumption • Determine savings and payback Drew Heilman │ Construction Management │ April 12, 2010

  8. Potomac Yard Land Bay E Arlington, Virginia Solyndra System • Founded in 2005 in Fremont, California Presentation Outline • State of the art highly automated production • Project Overview • Reliable hermetic seal on ends of each module • Implementation of Solyndra PV System (Electrical Breadth) • Great application on cool roofs • Implementation of Curtain Wall System (Mechanical Breadth) • Absorbs energy from 360 degrees • Implementation of Chilled Beams (Critical Industry Issue) • Direct • Diffuse • Conclusions and Recommendations • Reflected • Acknowledgements and Questions • Can produce 99% of output regardless of orientation when used with highly reflective roof Drew Heilman │ Construction Management │ April 12, 2010

  9. Potomac Yard Land Bay E Arlington, Virginia Solyndra Advantages • Flat installation, higher panel placement • Lightweight design, 3lb/ft^2 Presentation Outline • No roof penetrations, self ballasted • Project Overview • 25-year power warranty • Implementation of Solyndra PV System (Electrical Breadth) • Superior wind performance, tested and certified for 130 mph • Implementation of Curtain Wall System (Mechanical Breadth) • 3x faster installation • Implementation of Chilled Beams (Critical Industry Issue) • 50% reduction in installation cost • Conclusions and Recommendations • 30% Investment Tax Credit (ITC) when applied on a cool roof • Acknowledgements and Questions • Installation labor • Reflective roof material • Fasteners and adhesive agents • Insulation • Supporting Materials Drew Heilman │ Construction Management │ April 12, 2010

  10. Potomac Yard Land Bay E Arlington, Virginia Application • Allow for two feet maintenance walkways around panels Presentation Outline • Mechanical installation • Project Overview • Connect mounting hardware to panel • Implementation of Solyndra PV System (Electrical Breadth) • Transport panels to location • Implementation of Curtain Wall System (Mechanical Breadth) • Plug in DC connectors and grounding cable • Implementation of Chilled Beams (Critical Industry Issue) • Install lateral clips to connect panels • Conclusions and Recommendations • Place ballasting material on mounting hardware • Five qualified workers two 8-hour days • Acknowledgements and Questions • Electrical installation • Run wiring from panels to inverter • Install inverter • Two electricians 5-10 days to complete Drew Heilman │ Construction Management │ April 12, 2010

  11. Potomac Yard Land Bay E Arlington, Virginia Energy Consumption (Electrical Breadth) • Mechanical Equipment Presentation Outline • 745.7 watts = 1HP • Project Overview • 261 work-days in 2010 • Implementation of Solyndra PV System (Electrical Breadth) • 16 hour/day operation • Implementation of Curtain Wall System (Mechanical Breadth) • Average energy cost Balt./Wash. 2009: $.137/kWh • Implementation of Chilled Beams (Critical Industry Issue) • Lighting Load • Conclusions and Recommendations • Lighting Power Density, ASHRAE 90.1 • LPD is an estimate of W/ft^2 • Acknowledgements and Questions • 261 work-days in 2010 • 10 hour/day operation • Average energy cost Balt./Wash. 2009: $.137/kWh Drew Heilman │ Construction Management │ April 12, 2010

  12. Potomac Yard Land Bay E Arlington, Virginia Energy Consumption (Electrical Breadth) • Receptacle Load Presentation Outline • 1VA = 1Watt • Project Overview • NEC 2008 Table 20.44 Article 220: Branch Circuit-Feeder • Implementation of Solyndra PV System (Electrical Breadth) • 1 st 10kVA = 100% • Implementation of Curtain Wall System (Mechanical Breadth) • After 10kVA = 50% • Implementation of Chilled Beams (Critical Industry Issue) • 261 work-days in 2010 • Conclusions and Recommendations • 10 hour/day operation • Average energy cost Balt./Wash. 2009: $.137/kWh • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

  13. Potomac Yard Land Bay E Arlington, Virginia Energy Production (Electrical Breadth) • Solyndra Panels (1030) Presentation Outline • GAISMA Insolation • Project Overview • Implementation of Solyndra PV System (Electrical Breadth) • Implementation of Curtain Wall System (Mechanical Breadth) • Implementation of Chilled Beams (Critical Industry Issue) • Conclusions and Recommendations • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

  14. Potomac Yard Land Bay E Arlington, Virginia System Cost • $1,400 per panel Presentation Outline • 1,030 panels implemented • Project Overview • $1,442,00 total system cost • Implementation of Solyndra PV System (Electrical Breadth) Energy and Cost Savings • Implementation of Curtain Wall System (Mechanical Breadth) • 276.7 kWh/panel • Implementation of Chilled Beams (Critical Industry Issue) • 282,112 kWh total • Conclusions and Recommendations • 1.38 % energy savings per year • $38,649.38 energy cost savings during first year • Acknowledgements and Questions Drew Heilman │ Construction Management │ April 12, 2010

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend