Alternative Refinement February 6, 2012 1 POTOMAC YARD METRORAI L - PowerPoint PPT Presentation

Potomac Yard Metrorail Station Environmental I mpact Statement Alternative Refinement February 6, 2012 1 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP Agenda 1. Welcome and Review of Project to Date 2. Refinement of Alternatives


  1. Potomac Yard Metrorail Station Environmental I mpact Statement Alternative Refinement February 6, 2012 1 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  2. Agenda 1. Welcome and Review of Project to Date 2. Refinement of Alternatives 3. Functionality and Appearance 4. Cost Drivers 5. Schedule 6. Next Steps 2 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  3. Study Area 3 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  4. Process to Date 1. Potomac Yard Metrorail Station Concept Development Study (February, 2010) 2. Scoping Process (June 2011) & first meeting of PYMI G 3. Screening Document (October 2011) and second meeting of PYMI G 4. Refinement of Alternatives We are Here 2011- Fall 2013 End of 2013 February Early-mid 2012 2011 2013 4 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  5. Station Location Zones 5 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  6. Refinement of Stations Criteria for Refinement: NPS Property • Wetlands • Existing, Approved Plans • Ownership • Track Geometry • Construction I mpacts/ Access • Potential Ridership Capture • 6 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  7. Alternative A 7 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  8. Alternative A 8 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  9. Alternative A Alternative A Platform & Facilities Preliminary Wetland Areas Construction Access and Impact Area 9 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  10. Alternative A Alternative A Platform & Facilities Preliminary Wetland Areas Construction Access and Impact Area 10 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  11. Alternative A Alternative A Platform & Facilities Preliminary Wetland Areas Construction Access and Impact Area 11 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  12. Alternative B 12 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  13. Alternative B 13 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  14. Alternative B Alternative B Platform & Facilities New Track for Alternative B Preliminary Wetland Areas Construction Access and Impact Area 14 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  15. Alternative B Alternative B Platform & Facilities New Track for Alternative B Preliminary Wetland Areas Construction Access and Impact Area 15 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  16. Alternative B Alternative B Platform & Facilities New Track for Alternative B Preliminary Wetland Areas Construction Access and Impact Area 16 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  17. Functionality and Appearance: Example: At-Grade Station – Morgan Boulevard 17 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  18. Alternative D 18 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  19. Alternative D 19 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  20. Alternative D Alternative D Platform & Facilities New Track for Alternative D Preliminary Wetland Areas Construction Access and Impact Area 20 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  21. Alternative D Alternative D Platform & Facilities New Track for Alternative D Preliminary Wetland Areas Construction Access and Impact Area 21 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  22. Alternative D Slide 23 Slide 21 Slide 24 Alternative D Platform & Facilities New Track for Alternative D Preliminary Wetland Areas Construction Access and Impact Area 22 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  23. Alternative D – North End Alternative D Platform & Facilities New Track for Alternative D Preliminary Wetland Areas Construction Access and Impact Area 23 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  24. Alternative D – South End Alternative D Platform & Facilities New Track for Alternative D Preliminary Wetland Areas Construction Access and Impact Area 24 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  25. Functionality and Appearance: Example: Aerial Station – Tysons Corner 25 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  26. Functionality and Appearance: Example: Aerial Station – Tysons Corner – during construction 26 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  27. Cost Drivers Alt A Alt B Alt D Structures Required • 2 pedestrian • 2 pedestrian • New Metrorail bridge over Four Mile Run; bridges bridges • 2 new Metrorail bridges • Retaining wall • 1 pedestrian bridge • Aerial track and supports New Track 0-feet Approximately Approximately 6,000-feet Construction 2,000-feet Complexity of Moderate Moderate-High High Construction Staging Requires High Medium Medium-Low Construction Along Live Tracks 27 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  28. Overall Project Schedule Upcoming activities are shown in next slide 28 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  29. Further Cost Drivers and Upcoming Schedule 29 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

  30. Next Steps I ndividual environmental impact • methodology reports Environmental analysis for each of the • proposed alternatives Next level of cost information • Cost estimates (Expected Fall, 2012) • Next Meeting (tentatively May, 2012) • 30 POTOMAC YARD METRORAI L STATI ON I MPLEMENTATI ON WORK GROUP

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.