Potomac-Appalachian Transmission Highline Annual Update For Year - - PowerPoint PPT Presentation

potomac appalachian transmission highline
SMART_READER_LITE
LIVE PREVIEW

Potomac-Appalachian Transmission Highline Annual Update For Year - - PowerPoint PPT Presentation

Potomac-Appalachian Transmission Highline Annual Update For Year 2010 Presented July 20, 2011 Basics of the Annual Update 2010 Projected Revenue Requirement was presented in the October 1, 2009 update filing. 2010 Projected Revenue


slide-1
SLIDE 1

Potomac-Appalachian Transmission Highline

Annual Update For Year 2010

Presented July 20, 2011

slide-2
SLIDE 2

Basics of the Annual Update

  • 2010 Projected Revenue Requirement was presented in the

October 1, 2009 update filing.

  • 2010 Projected Revenue Requirement was based on:

Projected CWIP & Reg. Asset Balances (13-month average)

Projected Expenses

Income Taxes

Projected Amortization of Regulatory Asset

  • Rates became effective January 1, 2010.
  • 2010 Actual Transmission Revenue Requirement was filed
  • n June 3, 2011.

2

slide-3
SLIDE 3

True Up Adjustment 2010

3

PATH WV PATH AYE Total PATH 2009 PTRR $ 18.1 $ 11.4 $ 29.5 2009 ATRR 13.3 11.3 24.6 True Up Adjustment $ (4.8) $ (0.1) $ ( 4.9)

in millions

slide-4
SLIDE 4

Components of True Up PATH- WV 2010

in millions

Projected Actual Surcharge / (Refund) Total O&M $ 5.1 $ 3.9 $ (1.2)

  • Amort. of Reg. Asset

1.2 1.2 0.0 Taxes Other than Income Tax 0.0 0.2 0.2 Return on Rate Base 8.1 5.5 (2.6) Income Tax 3.7 2.5 ( 1.2) Total $ 18.1 $ 13.3 $ (4.8)

4

slide-5
SLIDE 5

Components of True Up PATH- AYE 2010

5

Projected Actual Surcharge / (Refund) Total O&M $ 2.5 $ 2.6 $ 0.1

  • Amort. of Reg. Asset

0.1 0.1 0.0 Taxes Other than Income Tax 0.6 0.2 (0.4) Return on Rate Base 5.6 5.7 0.1 Income Tax 2.6 2.7 0.1 Total $ 11.4 $ 11.3 $ (0.1)

in millions

slide-6
SLIDE 6

Rate Base for 2010 PATH-WV

6

Projected Actual Difference CWIP $ 68.9 $ 33.8 $ (35.1) Regulatory Asset 3.3 3.3 0.0 Deferred Income Taxes 4.2 4.4 0.2 Land Held for Future Use 0.0 9.8 9.8 Cash Working Capital 0.8 0.7 (0.1) Total $ 77.2 $ 52.0 $ (25.2)

in millions PATH Rate Base is calculated using a 13-month average balance

slide-7
SLIDE 7

Rate Base for 2010 PATH-AYE

7

Projected Actual Difference Plant in Service $ 9.8 $ 19.7 $ 9.9 Deferred Income Taxes 0.3 0.4 0.1 Cash Working Capital 0.3 0.4 0.1 CWIP 42.3 33.5 (8.8) Regulatory Asset 0.5 0.5 0.0 Total $ 53.2 $ 54.5 $ 1.3

in millions PATH Rate Base is calculated using a 13-month average balance

slide-8
SLIDE 8

Key Reasons for Refund

  • Lower than projected O&M Expense
  • Costs related to safety, education, siting, and outreach were

lower than expected due to delays in the CPCN process

  • Lower than projected CWIP expenditures
  • The extension of the PATH project in-service date to 2015

pushed back all scheduled activities and associated costs including major siting and ROW activities, progress payments for materials and preliminary construction activities resulting in the major reduction of expected spend.

8

slide-9
SLIDE 9

Next Steps

  • PATH will post 2012 Projected Transmission

Revenue Requirement on September 1, 2011.

  • The 2012 revenue requirement will include a $4.9

million credit, effectively returning the overcollection to customers throughout 2012.

  • Interest will also be applied to the $4.9 million credit

and included in the 2012 revenue requirement.

  • 9
slide-10
SLIDE 10

Questions?

10