port of san francisco
play

Port of San Francisco Hazardous Materials Abatement Building 49, - PowerPoint PPT Presentation

Port of San Francisco Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R August 9, 2018 1 AGENDA 1. Welcome, Introductions, & General Information Tim Leung 2. Project


  1. Port of San Francisco Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R August 9, 2018 1

  2. AGENDA 1. Welcome, Introductions, & General Information – Tim Leung 2. Project Overview – Dan Leung 3. CMD – Finbarr Jewell 4. OLSE– Anna Liu 5. ENVIRONMENTAL – Soko Made 6. Bid Documents – Tim Leung 7. Questions

  3. Work consists primarily of: Removal and disposal of hazardous materials: lead paint, asbestos- • containing materials, PCB and Mercury-containing fixtures. Seal surfaces by 3-layer application of Global Encasement Inc.’s • “LeadLock” or equivalent. Spot abatement of lead-containing paints prior to torch cutting (as • needed) for removal of pipe-rack, metal hopper, etc. From: Building 49 • Crane 14 tower • Metal hopper and pipe-rack • Shipyard Relics • Boom and Cab exterior of Crane 30 • Hazardous materials removal from Building 49 includes: Remove lead- and asbestos-containing materials as identified • in specifications, including dust on floors and interior horizontal surfaces. Remove & replace corrugated metal roof w. ACM mastic. • Characterize & dispose of debris pile. •

  4. CRANE 30 GANTRY (N.I.C.) SURCHARGE HOPPER LATHE STAMP NORTH Photographed 11/01/17 9

  5. Building 49 Roof with ACM mastic Building 49 Debris Pile 10

  6. Crane 14 11

  7. Remove & Dispose: Hopper and Pipe Rack Stabilize & Re-use Historic Shipyard Relics Stamp Lathe 12

  8. Bid Opening August 21, 2018 • Award of Contract September 2018 • NTP, Construction Start November 2018 • Construction Term 90 Consecutive Calendar Days • Substantial Completion February 2019 • Final Completion April 2019 •

  9. Presented By: Finbarr Jewell For questions email finbarr.jewell@sfgov.org Goals for Minority Participation Contractor to be chapter 12B • • in each trade = 25.8% compliant, refer to Section 00 45 70 for details. Goals for Female Participation • in each trade = 6.9% Refer to Section 00 73 41 for details. •

  10. 18

  11. Presented By: Anna Liu anna.liu@sfgov.org

  12. Presented By: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements See Section 01 74 50 for details • Minimum Diversion Rate of 75% Required • Source ‐ separated C&D debris material must be taken to a facility that reuses • and/or recycles that material MIXED C&D debris material must be taken to a REGISTERED FACILITY by a • REGISTERED TRANSPORTER Diversion Reporting – Use Form C for initial, monthly, and final reports • Weight Tags are required for monthly reporting • Contractor MUST include materials from ALL Subcontractors in reports • City Representative is responsible for reviewing, signing, and approving all • reports submitted by the Contractor.

  13. QBD  Addendum

  14. Questions? 26

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend