Port of San Francisco Hazardous Materials Abatement Building 49, - - PowerPoint PPT Presentation

port of san francisco
SMART_READER_LITE
LIVE PREVIEW

Port of San Francisco Hazardous Materials Abatement Building 49, - - PowerPoint PPT Presentation

Port of San Francisco Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R August 9, 2018 1 AGENDA 1. Welcome, Introductions, & General Information Tim Leung 2. Project


slide-1
SLIDE 1

Port of San Francisco

Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R

August 9, 2018

1

slide-2
SLIDE 2
slide-3
SLIDE 3

AGENDA

  • 1. Welcome, Introductions, & General Information – Tim Leung
  • 2. Project Overview – Dan Leung
  • 3. CMD – Finbarr Jewell
  • 4. OLSE– Anna Liu
  • 5. ENVIRONMENTAL – Soko Made
  • 6. Bid Documents – Tim Leung
  • 7. Questions
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8

Work consists primarily of:

  • Removal and disposal of hazardous materials: lead paint, asbestos-

containing materials, PCB and Mercury-containing fixtures.

  • Seal surfaces by 3-layer application of Global Encasement Inc.’s

“LeadLock” or equivalent.

  • Spot abatement of lead-containing paints prior to torch cutting (as

needed) for removal of pipe-rack, metal hopper, etc. From:

  • Building 49
  • Crane 14 tower
  • Metal hopper and pipe-rack
  • Shipyard Relics
  • Boom and Cab exterior of Crane 30

Hazardous materials removal from Building 49 includes:

  • Remove lead- and asbestos-containing materials as identified

in specifications, including dust on floors and interior horizontal surfaces.

  • Remove & replace corrugated metal roof w. ACM mastic.
  • Characterize & dispose of debris pile.
slide-9
SLIDE 9

9

Photographed 11/01/17

SURCHARGE

CRANE 30 GANTRY (N.I.C.)

NORTH

LATHE STAMP

HOPPER

slide-10
SLIDE 10

10

Building 49

Building 49 Roof with ACM mastic Debris Pile

slide-11
SLIDE 11

11

Crane 14

slide-12
SLIDE 12

12

Remove & Dispose: Hopper and Pipe Rack Stabilize & Re-use Historic Shipyard Relics

Lathe Stamp

slide-13
SLIDE 13
  • Bid Opening

August 21, 2018

  • Award of Contract

September 2018

  • NTP, Construction Start

November 2018

  • Construction Term

90 Consecutive Calendar Days

  • Substantial Completion

February 2019

  • Final Completion

April 2019

slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16

Presented By: Finbarr Jewell For questions email finbarr.jewell@sfgov.org

  • Goals for Minority Participation

in each trade = 25.8%

  • Goals for Female Participation

in each trade = 6.9%

  • Refer to Section 00 73 41 for details.
  • Contractor to be chapter 12B

compliant, refer to Section 00 45 70 for details.

slide-17
SLIDE 17
slide-18
SLIDE 18

18

slide-19
SLIDE 19
slide-20
SLIDE 20

Presented By: Anna Liu anna.liu@sfgov.org

slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24

Presented By: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements

  • See Section 01 74 50 for details
  • Minimum Diversion Rate of 75% Required
  • Source‐separated C&D debris material must be taken to a facility that reuses

and/or recycles that material

  • MIXED C&D debris material must be taken to a REGISTERED FACILITY by a

REGISTERED TRANSPORTER

  • Diversion Reporting – Use Form C for initial, monthly, and final reports
  • Weight Tags are required for monthly reporting
  • Contractor MUST include materials from ALL Subcontractors in reports
  • City Representative is responsible for reviewing, signing, and approving all

reports submitted by the Contractor.

slide-25
SLIDE 25

QBD  Addendum

slide-26
SLIDE 26

Questions?

26