Pilot on Thermal Enhanced SVE of Mercury in Soil and Bedrock under - - PowerPoint PPT Presentation
Pilot on Thermal Enhanced SVE of Mercury in Soil and Bedrock under - - PowerPoint PPT Presentation
Pilot on Thermal Enhanced SVE of Mercury in Soil and Bedrock under an active Chloro-Alkali Plant Eric Bergeron (Golder Associates, Montreal, QC, Canada) Lena Torin & ke Eriksson (Golder Associates, Gothenburg, Sweden) Berndt-Olof Jorlv
Background
March 14, 2016 2
■
Mercury based Chlor-Alkali plant started in 1969 in Stenungsund
■
Decision from the Sweden government:
■ Plant must be closed down by
December 2017
■ The mercury contamin-ation
needs to be remediated
■
Investigations show almost no contamination outside the plant building
■
Up to 1,5 ton of primarily elemental Hg could be present directly under the plant
Cross-Section of the Site
March 14, 2016 3
- Approx. 1 500 kg Hg
- Approx. 500 kg Hg are thought to be
present in deep fractures
Excavation of the thin fill will probably remediate less than approx. 25 % of the Hg. Low temperature heating of soil/ bedrock coupled with SVE was determined as the preferential, sustainable remediation technique for the site.
Pilot design
March 14, 2016 4
■
Collaboration between INOVYN (process engineering) and Golder Associates
■
3 heating wells (HW), triangular pattern
■ Indirect heating of stainless steel
casing by 140OC steam from plant
■ 2.5 m down, into the bedrock ■
2 extraction wells (EW)
■ EW-S: 1 m deep (sand and top highly
fractured ”bad” bedrock)
■ EW-D: 2.6 m deep (”good” bedrock) ■
2 monitoring wells (MW), ~5 m deep, 4 sampling levels (0.3 m, 1.75, 3, 5 m)
■
SVE started May 7th (baseline), heating started May 21th
The pilot inside the Chloro-Alkali plant
March 14, 2016 5
EW-S &D MW-1 MW-2 HW-1 to 3
Results from drilling for the pilot
March 14, 2016 6
10 m ■
Water encountered 1.3 mbgs inside, but ~ 5 mbgs or more outside the plant
■
Shallow wells will be drilled next week to try to dewater the pilot zone
■
Deep bedrock → very low permeability
■
Mass balance shows within the pilot:
■ Approx. 5 kg Hg in vadose zone ■ A few mg in water in the bedrock 20 m boring
Hg in matrix (mg/ kg) Max Mean Sand 4 900 850 ”Bad” top bedrock 7.2 3.0 Bedrock 2.3 0.6
Sand Top bedrock Bedrock
MW:s EW-S
Results from the pilot
March 14, 2016 7
~20% of Hg extracted after 8 months Virtually no gas extracted from ”good” bedrock
Hg in gas Temperature
Hg-speciation results for soil and bedrock
March 14, 2016 8
■
Speciation by Braunschweig University of Technology
■ Pyrolysis speciation for soil and bedrock ■ University developed speciation method for
water and gas (bubbled through water)
■
Not only elemental Hg in soil and bedrock
■
Almost 50% elemental Hg in sand that had Hg droplets
■
Elemental Hg has probably diffused into the ”bad” top bedrock
■
No elemental Hg in ”good” bedrock
■
Several other Hg-species present (HgCl2, HgS and/or HgO) Sand: 4900 mg/kg ”Bad” top bedrock: 7,2 mg/kg
Hg-Speciation of Gas
March 14, 2016 9 Hgpart: Particle bound Hg; HgIIb: Dissolved organic Hg (bound to BrCl-oxidable organic compounds); HgIIa: Dissolved inorganic, reactive Hg; Hg0: Elemental Hg During = 3 months after heating started
Extraction Rate Over Time
March 14, 2016 10
Energy Requirements
March 14, 2016 11
■
Sandy layer ( ̴ 0,5 m): 178 kW.h/m3
■
Bad bedrock layer ( ̴ 0,4 m): 157 kW.h/m3
■
Gneissic Bedrock ( ̴ 3,1 m): 60 kW.h/m3
Adapted from TerraTherm and Weston 1997
Results
March 14, 2016 12
Observations:
■
Extraction rate needs to be increased significantly
■
Temperature increase of 22°C → a seven-fold increase in vapor pressure → 2.6 fold increase in extraction rate
■
Estimated treatment time : 12 years
■
Bedrock dewatering is necessary Solution:
■
↑soil temperature up to 100 oC
■
Soil temperature ↑ 50 to 100 oC → 26 fold increase of the vapor pressure
■
7.2 fold increase of the extraction rate expected
■
Estimated treatment time : 21 months
Full-Scale
March 14, 2016 13
Full-Scale
March 14, 2016 14
Next steps…
March 14, 2016 15
■
Full scale detail design
■
Get a decision from the regulators on necessary remediation
■
The plant will close down during autumn 2017
■
After that process equipment (cells etc.) will be taken down and remediated
■
Drilling for full scale remediation will probably not start before the cells are away Control room
The good collaboration with INOVYN has been key for the success of this pilot! Thanks: to INOYN! to the team! for the good teamwork!
Skall försöka hitta mer foton på
- ss som varit