Permanent Parking Lot July 12, 2017 F-1 -16 Location Map F-1 -17 - - PowerPoint PPT Presentation

permanent parking lot
SMART_READER_LITE
LIVE PREVIEW

Permanent Parking Lot July 12, 2017 F-1 -16 Location Map F-1 -17 - - PowerPoint PPT Presentation

Community Services Commission Huntington Central Park Permanent Parking Lot July 12, 2017 F-1 -16 Location Map F-1 -17 Senior Center in Central Park Raptor Foraging Area F-1 -18 1000 Radius Map F-1 -19 Basics Design for 42 marked


slide-1
SLIDE 1

Huntington Central Park Permanent Parking Lot

July 12, 2017

Community Services Commission

F-1-16

slide-2
SLIDE 2

Location Map

F-1-17

slide-3
SLIDE 3

Senior Center in Central Park Raptor Foraging Area

F-1-18

slide-4
SLIDE 4

1000’ Radius Map

F-1-19

slide-5
SLIDE 5

Basics

 Design for 42 marked parking stalls including 2 ADA

accessible

 Need to provide capacity for 1 school bus  Parking lot hours same as Central Park: 5 am – 10 pm daily  Basic lighting included for lot and driveway(s)  Reviewed access and circulation options for:  Costs  Traffic safety  Maneuvering

F-1-20

slide-6
SLIDE 6

Alternatives

 Identified 2 basic alternatives  No connection to Senior Center driveway – existing  Connection to Senior Center driveway

F-1-21

slide-7
SLIDE 7

Alternative 1 – Single Point Driveway

F-1-22

slide-8
SLIDE 8

Alternative 1

 Essentially the existing configuration  No connection to Senior Center driveway  Requires turn around area for buses  Limited access from Goldenwest (right in/right out)  No accidents related to driveway since 2005 opening  Goldenwest traffic can be challenging to some –

requires patience to wait for appropriate gaps

 Estimated construction costs - $255,000

F-1-23

slide-9
SLIDE 9

Alternative 3 – Full Access Driveway from Senior Center Driveway

F-1-24

slide-10
SLIDE 10

Alternative 3

 Median opening for full access  All vehicles can use signal access  Potential removal of existing driveway  Turnaround needed for buses  Additional construction challenges due to differing

elevations of Senior Center driveway

 Estimated construction cost - $343,000

F-1-25

slide-11
SLIDE 11

Conclusions

 Both alternatives are feasible for construction  Both alternatives within expected budget - $610,000  Greater convenience with Alternative 3  Potential aesthetic considerations with Alternative 3  Both alternatives provide safe access – Alt. 3 with

additional controls that may be more acceptable to some motorists

F-1-26

slide-12
SLIDE 12

Conclusions

 No superior alternative based on engineering  Decisions comes down to preferences  Need to weigh relative importance of:  Convenience  Aesthetics  Costs  Traffic safety improvements

F-1-27

slide-13
SLIDE 13

Recommended Action

1.

Approve one of the two alternative plans as presented to convert the temporary parking lot to a permanent parking lot and make recommendation for approval to City Council. And;

2.

Make recommendation to City Council to update the Central Park Master Plan of Recreational Uses for Central Park to identify the approximate one acre site as a permanent parking lot.

F-1-28