Peirce Island WWTF Upgrade Construction Public Information Meeting May 24, 2017 T opics of Discussion Introductions Work Completed Since Last Meeting Work to be Completed in Coming M onth Work Anticipated in Next 6 Months
T
- pics of Discussion
- Introductions
- Work Completed Since Last Meeting
- Work to be Completed in Coming M onth
- Work Anticipated in Next 6 Months
- Events & Recreation
- Public Input/ Comments/ Concerns
- Next Meeting
May 24, 2017 Peirce Island WWTF Upgrade Construction 2
Introductions
- City Staff:
– Don Song, Wastewater Project Manager, 603-610-7305
dsong@cityofportsmouth.com
– T
erry Desmarais, City Engineer, 603-766-1421 tldesmarais@cityofportsmouth.com
- Website:
http:/ / www.portsmouthwastewater.com/ piupgrade.html
– News and Updates – Recreational Info – Project Info – Report Form – Etc.
Peirce Island WWTF Upgrade Construction 3 May 24, 2017
September 19, 2016 Peirce Island WWTF Upgrade Construction 4
Headworks Construction Sludge Thickener Construction
Areas of Ongoing Construction May 2017
Headworks Grit Building Primary Clarifier
- No. 2
Primary Clarifier
- No. 1
GT1 GT2 Solids Processing Building Biological Aerated Filter (BAF) Chlorine Contact Tank Ops. Bldg Gen Elec Permanent Fence Construction Staging Fence Chem. Piscataqua River
New Pump Station Existing Filter Building Demolition & BAF Building Excavation & Construction Y ard Piping and Utility Service
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 5 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 6 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 7 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 8 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 9 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 10 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 11 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 12 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 13 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 14 May 24, 2017
Work Completed Since Last Meeting
Peirce Island WWTF Upgrade Construction 15 May 24, 2017
Work to be Completed in Coming Month
- Continue underground piping installation near the new
Headworks Building
- Begin installation of brick façade of the new Headworks Building
- Begin installation of roof system of the new Headworks Building
- Complete installation of the new Sanitary Pump Station
- Continue installation of utilities near the new Sanitary Pump
Station
- Complete excavation of the existing Filter Building (on Shapleigh
Island side of site), including blasting and rock excavation
- Begin reinforcing steel for the BAF Building foundation
Peirce Island WWTF Upgrade Construction 16 May 24, 2017
Work to be Completed in Coming Month, Cont.
- Continue excavation and installation of new underground power
and communications ductbank, beginning near the pool
- Demolish duct bank and scum tank to prepare for generator
installation
- Begin excavation and construction of concrete pads for the new
Electrical Building and standby generator
- Continue excavation and installation of underground piping near
new Gravity Thickener
- Leak test the new Gravity Thickener
- Complete parking lot improvements
Peirce Island WWTF Upgrade Construction 17 May 24, 2017
September 19, 2016 Peirce Island WWTF Upgrade Construction 18
Headworks Construction Sludge Thickener Construction New Electrical Facilities
Anticipated Construction May 2017 – September 2017
Headworks Grit Building Primary Clarifier
- No. 2
Primary Clarifier
- No. 1
GT1 GT2 Solids Processing Building Biological Aerated Filter (BAF) Chlorine Contact Tank Ops. Bldg Gen Elec Permanent Fence Construction Staging Fence Chem. Piscataqua River
New Pump Station Existing Filter Building Demolition & BAF Building Excavation & Construction Grit Building Construction Y ard Piping and Utility Service
Work to be Completed in Coming Month, Cont.
Peirce Island WWTF Upgrade Construction 19 May 24, 2017
Reconstruction
- f Four Tree
Island Parking Lot
Work to be Completed in Coming Month, Cont.
Peirce Island WWTF Upgrade Construction 20 May 24, 2017
Boat Ramp Overflow Parking Lot
Events and Recreation
- Upcoming
– Market Square Day – Big Brothers Big Sisters Race – March of Dimes Walk
Peirce Island WWTF Upgrade Construction 21 May 24, 2017
Public Input / Comments / Concerns
Next Meeting
- Public Construction Meeting
– Next Meeting: June 21, 2017, 11:00 AM
- City Council / Public Site T
- urs
– June 20, 2017 – More details to be announced
Peirce Island WWTF Upgrade Construction 23 May 24, 2017