Abbyville Hydrogeologic Peer Review

  • Topics:

–Wastewater –Grading Plan –AUL S ite

slide-2
SLIDE 2

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

WWTF Sensitive Receptors

Private Wells WWTF AUL Test Wells Mill River

slide-3
SLIDE 3

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

slide-4
SLIDE 4

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

slide-5
SLIDE 5

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Private Wells

slide-6
SLIDE 6

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Image from Cucamonga Water District, CA

slide-7
SLIDE 7

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Private Wells

  • Bedrock Wells –

Approximately 14 in Proximity, 160 – 525 feet Deep

  • Wells Tap Multiple

Fractures in Various 3D Orientations

  • Fracture Water from

Where Fractures Intersect Overburden Aquifer

  • Capture Zones of Bedrock

Wells Difficult to S pecify

slide-8
SLIDE 8

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Private Wells

  • Conductivity of Overburden

Aquifer on S ite Much Higher Than Fractured Bedrock

  • Intersection of Overburden

Aquifer With Bedrock at Bottom

  • WWTF GW Flow Traveling

Horizontally and Downward

  • Opportunity for S

ignificant Contribution from WWTF to Private Wells Minimal

slide-9
SLIDE 9

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Private Wells

  • S

till Recommend High Level WWTF Treatment for 2-Year TOT to Public Drinking Water Wells

  • Pre and Post Construction Monitoring of

Intervening Monitoring Wells and Private Wells Themselves

Agreed To By Applicant

slide-10
SLIDE 10

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Town Test Well Site & Franklin Wells

  • Bedrock

Protection Unknown

  • More Likely

to Receive Groundwater Flow from WWTF

Test Wells Test Wells

slide-11
SLIDE 11

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Town Test Well Site & Franklin Wells

  • Test Well S

ite Calculated to be Approx. 1– Year TOT from WWTF

  • Recommend Higher Treatment S

tandards for WWTF for Being < 2-Year TOT

  • Recommend Pre & Post Construction

Monitoring

Agreed To By Applicant

slide-12
SLIDE 12

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Mill River

  • TMDL for Phosphorus Requires 50%

Overall and 66% Wastewater Reduction

  • Reductions from 2005 Time Period of

TMDL Data

  • This and all New Development S

ince 2005 Requires 100% Mitigation

  • S

tormwater Controls Pending New MS 4 Permit

  • WW Controls Per MassDEP. Enforcement

Unknown

slide-13
SLIDE 13

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Mill River Recommendations

  • Provide Phosphorus Mitigation to Extent

Practical to Protect Town from Potential Future Regulatory Issues

– Maximize Unsaturated Thickness Beneath WWTF Beds – Provide High Level P Treatment at WWTF – Provide Capacity for Future WWTF Expansion to Tie-in Existing Nearby Homes

Agreed To By Applicant

slide-14
SLIDE 14

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

AUL Site

  • Will Higher GW Levels & More

Flow S pread Contaminants Towards Mill River?

  • Predicted 0.4-Foot Rise of

Water Table at AUL from WWTF

  • Lagoons Already in

Groundwater so No Further Influence Likely

  • Based on Applicant’ s Review of

AUL Documents and Field S urvey, Landfill Base Appears to be Above 100-Yr Flood El.

slide-15
SLIDE 15

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

AUL Site

  • Landfill Location Between Tail

Race and River Makes S ignificant GW changes from Proposed WWTF Unlikely

  • S

ites are Closed and Under MassDEP Direction

  • Applicant is Landowner and Thus

Responsible Party to MassDEP

  • Recommend Let MassDEP Opine

if Concerned about WWTF Impacts

slide-16
SLIDE 16

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Site Grading

  • S

tormwater Infiltration Basins < 4-Ft S HGW S eparation

From UCI

slide-17
SLIDE 17

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Stormwater Basins

  • Applicant Agreed to Base Inf. Basin

Designs on S HGW Determined from Either:

– S

  • il Mottling in New Test Pits Witnessed by

Town Health Agent – Frimpter Adj usted Values Based on February 20, 2018 Data

  • S

HGW to be No Lower Than February 20, 2018 Readings

slide-18
SLIDE 18

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Site Grading - Steep Slopes

  • ~ 40 feet

Vertical Drop at 2:1 S lope

  • Cut Begins at

property Line to #51 Lawrence S t.

slide-19
SLIDE 19

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Steep Slopes Recommendations

  • Can’ t Be Mowed. S

eed and Plug for Trees/ S hrubs

  • Hydroseed w Bonded Fiber Matrix
  • Initial S

eed Both NE Erosion Contol & Rye/ Fescue w S econd Overseed

  • S

tormwater Controls at Top

  • Benching to Break up S

lope

  • Monitor and Repair Erosion

Agreed To By Applicant

slide-20
SLIDE 20

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Recommendations

  • Town to S

ubmit Comments on GWDP When Engineering Report S ubmitted

  • WWTF Designed to Treatment Levels for

Less Than 2-Year TOT to Public S upply Wells

Agreed To By Applicant

slide-21
SLIDE 21

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Recommendations

  • Maximize Unsaturated Thickness Beneath

Disposal Beds

  • Build WWTF with Excess Capacity to Tie

in Existing Development

  • Provide Curbside Public Water S

upply S hutoffs for Lawrence S treet Homes

  • Pre and Post Construction Monitoring

Agreed To By Applicant

slide-22
SLIDE 22

Horsley W itten Group, I nc. Horsley W itten Group, I nc.

Recommendations

  • Ensure S

tormwater Infiltration Basins Meet MAS WS

  • Waiver Needed for Town Excavation

Bylaw?

  • Improved S

teep S lope S tabilization and Monitoring

Agreed To By Applicant