hutchinson wwtf solar pv ep4 41 john paulson project
play

Hutchinson WWTF Solar PV EP4-41 John Paulson - PowerPoint PPT Presentation

Hutchinson WWTF Solar PV EP4-41 John Paulson Project/Environmental/Regulatory Manager Xcel RDF Advisory Board April 12, 2016 Site Preparation Panoramic Xcel RDF Advisory Board 2 Project Presentation 4/12/16 Site Preparation Aerial Xcel


  1. Hutchinson WWTF Solar PV EP4-41 John Paulson Project/Environmental/Regulatory Manager Xcel RDF Advisory Board April 12, 2016

  2. Site Preparation Panoramic Xcel RDF Advisory Board 2 Project Presentation 4/12/16

  3. Site Preparation Aerial Xcel RDF Advisory Board 3 Project Presentation 4/12/16

  4. Ballast Piers 18”H x 30”D - 410 total Xcel RDF Advisory Board 4 Project Presentation 4/12/16

  5. Xcel RDF Advisory Board 5 Project Presentation 4/12/16

  6. Xcel RDF Advisory Board 6 Project Presentation 4/12/16

  7. Xcel RDF Advisory Board 7 Project Presentation 4/12/16

  8. Layout of piers using nylon line Pier Layout Xcel RDF Advisory Board 8 Project Presentation 4/12/16

  9. First rows being installed Xcel RDF Advisory Board 9 Project Presentation 4/12/16

  10. Ballasted Fence Installation Xcel RDF Advisory Board 10 Project Presentation 4/12/16

  11. Ballasted Fence Completed Xcel RDF Advisory Board 11 Project Presentation 4/12/16

  12. All Panels Installed Xcel RDF Advisory Board 12 Project Presentation 4/12/16

  13. Reflective Panels Xcel RDF Advisory Board 13 Project Presentation 4/12/16

  14. Flexible Conduit Independent Support Rails Xcel RDF Advisory Board 14 Project Presentation 4/12/16

  15. e-Gauge Monitoring System http://www.ci.hutchinson.mn.us/departmentsfacilities/public- works/park-garage/greenstep-cities/ Xcel RDF Advisory Board 15 Project Presentation 4/12/16

  16. Work Zone Cam w/Time Lapse Video http://www.ci.hutchinson.mn.us/departmentsfacilities/public- works/park-garage/greenstep-cities/ Xcel RDF Advisory Board 16 Project Presentation 4/12/16

  17. City of Hutchinson Solar PV Project History  October, 2011: Westwood: Renewable Energy Suitability Study June – Sept, 2012 : Staff and Council discussions regarding Solar PV project  October, 2012: Signed “ Agreement Letter” to Develop a Solar PV System   March 2013: Xcel Energy RDF Proposal Submitted  March 12, 2014 : Xcel Award Letter received by the City  April 23, 2014 : Planning meeting to move forward May – September: Updated Xcel Award requirements  — Further developments per the Term Sheet and site requirements  October 14, 2014 : Term Sheet executed with AMERESCO  December 23, 2014: Energy Service Agreement w/AMERESCO  June 19, 2015: Xcel Grant Contract approved October – November 2015: Construction of System 11/25/15 Commissioned  Xcel RDF Advisory Board 17 Project Presentation 4/12/16

  18. Solar PV Project Specifics  Solar PV size = 400 KW = 470,070 kwh/year guaranteed (80% derated from actual) (Actual = 587,587 kwh/year) ~15% of the WWTP Annual Load  Utility costs = 0.737/kwh and annual increases = 1.5%  Solar System Payback = 18 years (~14 years using higher than guaranteed system output)  At year 30, system has generated $370,000 – after paying for itself  Pricing = $1,467,000 – Xcel Grant = $958,360 Xcel RDF Advisory Board 18 Project Presentation 4/12/16

  19. Solar PV Site Land Use Challenges  Emergency Services Training Site (Police & Fire)  Stockpiling Public Works Materials  State Bonding $ used for improvements 1999  Office of M&B approval to proceed  City Dump Site 1950-1980  Phase I Assessment 1999  VIC Program April 2002  Phase II Assessment June 2002  Additional Assessment September 2002  Restrictive Covenant July 2007  No disturbance without MPCA approval  RAP November 2007 Xcel RDF Advisory Board 19 Project Presentation 4/12/16

  20. Solar PV Site Land Use Challenges  RAP and Covenant Requirements  Construction Contingency Plan  Site Health and Safety Plan  Routine inspections of site and LEL monitoring  NO PENETRATIONS!  Design Considerations  Compacted clay fill over existing cover  Geotextile  Clean granular over Geotextile  DIFFERENTIAL SETTLEMENT  Undisturbed 10 years (Manufacturer White Paper)  Density Testing Xcel RDF Advisory Board 20 Project Presentation 4/12/16

  21. Project Outreach and Awareness  Minnesota Brownfields Presentation  Wide variety of brownfields professionals coming together to discuss solar PV development on brownfields  Excellent feedback and inquiries  Lee Gabler, Xcel Energy's Senior Director of Customer Strategy and Solutions also presented  Hutchinson Leader Newspaper Multiple articles about the project  Clean Energy Research Teams Highlighted project in newsletter  LinkedIn Project Post Over 100 views  MPR Interview Interview 3/29/16, has not aired yet  Mn Wastewater Operators Association Central Section Meeting  Presentation this morning 4/12/16 to 30+ Wastewater Professionals  Hutchinson City Website with e-Gauge and Workzone Cam Xcel RDF Advisory Board 21 Project Presentation 4/12/16

  22. Solar PV Construction Offsite Challenges Different Project Adjacent to Solar PV Project Xcel RDF Advisory Board 22 Project Presentation 4/12/16

  23. City of Hutchinson Questions and Comments “Project funding provided, in part, by customers of Xcel Energy through a grant from the Renewable Development Fund.”

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend