Payment D39PZ: Procurement and Contracts 2 Lecture Plan 1. Payment - - PowerPoint PPT Presentation

payment
SMART_READER_LITE
LIVE PREVIEW

Payment D39PZ: Procurement and Contracts 2 Lecture Plan 1. Payment - - PowerPoint PPT Presentation

...last week (or things you should now understand) the difference between a certificate and an instruction the difference between an instruction and a Variation the role of certificates in controlling money and time the


slide-1
SLIDE 1

D39PZ: Procurement and Contracts 1

...last week (or things you should now understand)

  • the difference between a certificate and an instruction
  • the difference between an instruction and a Variation
  • the role of certificates in controlling money and time
  • the responsibilities of the CA with regard to the issue of

instructions and certificates

  • key certificates associated with key post-contract events

(e.g. Interim Certificates, Practical Completion Certificate, etc.)

slide-2
SLIDE 2

2

Unit 8: Contract Administration: Payment

D39PZ: Procurement and Contracts

slide-3
SLIDE 3

D39PZ: Procurement and Contracts 3

Lecture Plan

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-4
SLIDE 4

D39PZ: Procurement and Contracts 4

Payment under SBC

  • Reviews the principles upon which the Employer’s periodic

payments to the Contractor under SBC/Q are based

  • SBC incorporates several obligations from the Construction

Act regarding payment practice, including:

  • The Employer has 14 days from the “interim payment due

date” to pay the certified amount to the Contractor (cl. 4.12.1)

  • If it does not, then:
  • The Contractor can charge interest on the outstanding amount at 5%

above the base rate (cl. 4.12.6; cl. 1.1);

  • The Contractor can suspend the Works (cl. 4.14); and
  • The Contractor can terminate its own employment if payment still
  • utstanding a further 14 days past the due date (i.e. 28 days after

interim payment due date (cl. 8.9.1.1)

slide-5
SLIDE 5

D39PZ: Procurement and Contracts 5

The Contract Sum

  • The amount of money the Employer will pay the Contractor

for building the Works (Article 2)

  • Was originally the winning tenderer’s tender price. When

the tender offer was accepted, the tender price became the Contract Sum.

  • If the Employer makes no changes (i.e. no Variations),

and there are no unforeseen circumstances, the initial Contract Sum will be the amount finally paid.

  • This is unrealistic. SBC/Q needs provisions to continually update and

document the agreed Contract Sum.

slide-6
SLIDE 6

D39PZ: Procurement and Contracts 6

Interim payments

  • The long time required to construct the Works and their

large capital value requires the Employer to pay the Contractor as the Works are completed.

  • Interim valuations are performed at agreed regular

intervals by the QS to ascertain the current value of the Works

  • This is the Gross Valuation
  • In principle, the difference between one Gross Valuation and

the immediately preceding Gross Valuation is the amount to be paid by the Employer for that period’s work

  • This amount is subject to Retention (and other Employer “set-
  • ffs” as permitted by SBC/Q)
slide-7
SLIDE 7

D39PZ: Procurement and Contracts 7

Retention

  • Retention is governed by cls. 4.9.2, 4.18 and 4.20.
  • An agreed Retention Percentage is withheld by the

Employer from each payment due following a Gross Valuation.

  • The Employer’s (monthly) payments to the Contractor will be

less than suggested by the Gross Valuation.

slide-8
SLIDE 8

D39PZ: Procurement and Contracts 8

Retention

  • Retention is deducted at the full Retention Percentage

stated in the Contract Particulars from Works not yet covered by a Practical Completion Certificate (cl. 4.20.2.1)

  • Retention is also deducted at the full Retention

Percentage from materials on site and Listed Items (cl. 4.20.2.2)

  • Retention is deducted at half the Retention Percentage

stated in the Contract Particulars from Works that are covered by a Practical Completion Certificate but are not yet covered by a Certificate of Making Good - i.e. during the Rectification Period (cl. 4.20.3)

slide-9
SLIDE 9

D39PZ: Procurement and Contracts 9

Terminology

  • Interim
  • Something that happens several times at regular intervals
  • SBC/Q defaults to valuations at monthly intervals.
  • Gross Valuations (cl. 4.16)

The QS’s ascertainment of the total value of the partially completed Works on the date of each interim valuation.

  • Interim valuations (cl. 4.10)

The QS’s monthly activity of ascertaining the amount due in an Interim Certificate. This requires a Gross Valuation.

slide-10
SLIDE 10

D39PZ: Procurement and Contracts 10

Terminology

  • Interim Certificates (cls. 4.9.2, 4.10.1, 4.12)

The regular certificates denoting the interim payments that must be paid by the Employer to the Contractor.

  • Retention (cls. 4.9.2, 4.18, 4.20)

A proportion of the sums otherwise due to Contractor withheld by the Employer until the end of the project to ensure the Contractor to complete the Works.

  • Retention Bond (cl. 4.19)

As alternative of the Employer deducting Retention, the Contractor can obtain a Retention Bond which will pay out to the Employer if the Contractor defaults on its obligations.

slide-11
SLIDE 11

D39PZ: Procurement and Contracts 11

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-12
SLIDE 12

D39PZ: Procurement and Contracts 12

Payment generally

  • Contract parties are free to agree:
  • The sum to be paid for the Works
  • Whether payment is to be in installments
  • When installments are due and how they are to be paid
  • We have seen typical such agreements in the SBC
slide-13
SLIDE 13

D39PZ: Procurement and Contracts 13

“Paid when paid” clauses

  • Payment under The Housing Grants, Construction and

Regeneration 1996 Act:

  • Sections 109 and 110 establish the Contractor’s

statutory right to periodic payment.

  • Section 110(1) requires that a mechanism for

ascertaining payments is provided by construction contracts.

  • Section 113 prohibits “paid when paid” clauses
  • These were typically used by the Contractor with its

subcontractors and were considered unfair.

slide-14
SLIDE 14

D39PZ: Procurement and Contracts 14

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-15
SLIDE 15

D39PZ: Procurement and Contracts 15

Division of responsibility

  • Gross valuation is the process used to implement the

period payments from the Employer to the Contractor

  • QS ascertains (quantifying) the amount of the Gross

Valuation (cl.4.10.2)

  • This is done using their own calculations, or they can

review an application from the Contractor received not less than 7 days before the due date (cl. 4.11.1)

  • Using figures provided by the QS, the CA certifies the

amount that must be paid by the Employer to the Contractor for that period of work (cl 4.10.1)

slide-16
SLIDE 16

D39PZ: Procurement and Contracts 16

Content of a Gross Valuation

  • When ascertaining each Gross Valuation, the QS will

include:

  • those parts of the Works “properly executed” on the

date of valuation (cl. 4.16.1.1)

  • materials or goods stored on site and clearly identifiable

as being destined for inclusion in the Works (cl. 4.16.1.2)

  • materials or goods stored off site but identified in the

Contract Documents as “Listed Items” and therefore clearly identified as being destined for inclusion in the Works, (cl. 4.16.1.3)

slide-17
SLIDE 17

D39PZ: Procurement and Contracts 17

Content of a Gross Valuation

  • The QS must will also include the following in a Gross

Valuation (from which Retention is not deducted):

  • any amounts to be included in Interim Certificates in accordance with clause 4.4 as a

result of payments made or costs incurred by the Contractor under clause 2.6.2 (additional insurance premiums due to early use by employer), 2.21 (fees or charges legally demandable), 2.23 (patent rights – instructions), 3.17 (CA’s instructions requiring contractor to open up for inspection any work covered up or to arrange for or carryout any tests of material or goods or of any executed work), 6.5 (contractor’s insurance of liability

  • f employer), 6.10.2 (Terrorism cover – policy extension and premiums) or 6.10.3

Terrorism cover – policy extension and premiums) or paragraph B.2.1.2 or C.3.1 of Schedule 3 (insurance);

  • Any amount payable under cl 4.14.2 due to suspension of work
  • Any sum due to the Contractor as a consequence of a claim for Loss and Expense (cl.

4.23)

  • Any amounts in respect of any restoration, replacement or repair of loss or damage and

removal and disposal of debris under paragraph B.3.5 or C.4.5.2 of Schedule 3 or clause 6.11.5.2; and

  • Additions caused by the fluctuation option
slide-18
SLIDE 18

D39PZ: Procurement and Contracts 18

Deductions from a Gross Valuation

  • The QS ascertains the value of the following so they can

be deducted from each Gross Valuation:

  • Errors arising from contractors’ wrong setting out (cls. 4.16.3.1 and

2.10).

  • Employer’s costs in using an alternative contractor to fix defects (cls.

4.16.3.1 and 2.38)

  • Employer’s costs in using an alternative contractor to undertake

instructions that the original Contractor is refusing to implement (cls. 4.16.3.1 and 3.11)

  • Works not in accordance with the Contract Documents but not

justifying an instruction to correct (cls. 4.16.3.1 and 3.18.2).

  • Deductions caused by insurance premium reductions occur at any

renewal of Terrorism cover by contractor due to variation in rate on which the premium is based (cl. 6.10.2)

  • Deductions caused by a fluctuations option, if present

(cl. 4.16.3.2)

slide-19
SLIDE 19

D39PZ: Procurement and Contracts 19

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-20
SLIDE 20

D39PZ: Procurement and Contracts 20

Interim Certificates: procedure

  • The QS conducts an interim valuation as required by the

CA to ascertain the “Gross Valuation” so that an amount payable by the Employer can be stated as due in an Interim Certificate (cl. 4.9.2).

  • The QS will attend the site to:
  • Confirm and value the work completed (cl. 4.16.1.1)
  • Confirm and value any materials or goods stored on site

and due to be incorporated in the Works (cl. 4.16.1.2)

  • Confirm presence of any Listed Items (this may require a

visit to the Contractor’s or supplier’s storage facility) (cl. 4.16.1.3)

slide-21
SLIDE 21

D39PZ: Procurement and Contracts 21

Interim Certificate

slide-22
SLIDE 22

D39PZ: Procurement and Contracts 22

Statement of Retention

  • cl. 4.18.2 requires a

Statement of Retention to be issued with every Interim Certificate

slide-23
SLIDE 23

D39PZ: Procurement and Contracts 23

Interim Certificates (cls. 4.9 to 4.12)

  • Issued regularly as the Works progress to:
  • document the progress of the Works;
  • Mark an event; and
  • ensure regular interim payments from Employer to Contractor
  • Issued in accordance with:
  • cl. 4.9.1 - timing of certificate issue
  • cl. 4.9.2 - ascertaining the amount to be certified
  • Interim Certificates overcome the absence of a common

law right to interim payments

slide-24
SLIDE 24

D39PZ: Procurement and Contracts 24

Interim Certificates

  • Interim Certificates are not conclusive.
  • They are intended to be reasonably accurate.
  • However, they have significant commercial consequence

(for Contractor and Employer), and QS and CA professional liability.

  • An Interim Certificate (and its appended Statement of

Retention) documents are the outcome of an interim valuation.

  • Financial reports, case flow projections, etc. may also be produced,

but they are not mandated by the SBC.

  • An interim valuation is a fair assessment of the value of

the Works satisfactorily completed by the Contractor to date

slide-25
SLIDE 25

D39PZ: Procurement and Contracts 25

Interim Certificates

  • Each Gross Valuation must “adjust” the Contract Sum to

incorporate additions or deductions caused by Variations, additions and deductions (cl. 4.16): here are some deductions…

  • Liquidated Damages (if Non-Completion Certificate issued) (cl. 2.32.2.2)
  • Errors in setting out that do not have to be amended (cl. 2.10)
  • Cost of employing an alternative contractor to rectify defects the

Contractor is reusing to fix (cl. 2.38)

  • Cost of employing an alternative contractor to implement

instructions the Contractor is refusing to do (cl. 3.11)

  • Value of Works not in accordance with the Contract which does

not require to be replaced (cl. 3.18.2)

  • The updated Contract Sum is the Gross Valuation (cl. 4.16).
slide-26
SLIDE 26

D39PZ: Procurement and Contracts 26

Interim Certificates: procedure

  • The Contractor can (and usually does) make an application

for payment under cl. 4.11.1 in advance of the interim valuation.

  • The Contractor’s application will typically include:
  • Works completed to date, charged at “bill rates.”
  • Works completed in response to CA Instructions requiring variations,

charged in accordance with the Valuation Rules (cls. 5.6 to 5.10).

  • Wherever possible, variations should be measured and suitable bill

rates applied (cl. 5.6 - “Measurable Work”).

  • If a variation “cannot properly be valued by measurement,” Daywork

may be used (cl. 5.7 - “Daywork”).

  • All Dayworks sheets must be signed by the Clerk of Works.
slide-27
SLIDE 27

D39PZ: Procurement and Contracts 27

Interim Certificates: procedure

“The daywork sheet is to the construction client what the Jolly Roger is to the high seas – a flag that strikes terror into the hearts of its intended victims. It is the bloody banner that chills the mind, that freezes the hand that writes the cheque.”

Bingham, T. (2004). “Blood and Treasure.” Building, 30 April

slide-28
SLIDE 28

D39PZ: Procurement and Contracts 28

  • A typical dayworks

sheet

  • The contractor requests

payment of the actual labour, materials, and plant costs incurred to comply with an instruction that requires work that “cannot properly be valued by measurement” (cl. 5.7).

slide-29
SLIDE 29

D39PZ: Procurement and Contracts 29

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-30
SLIDE 30

D39PZ: Procurement and Contracts 30

Instructions vs. Variations

  • Reminder:
  • Instructions address how the Works are being completed

(Instructions are issued to change the way in which Contractor are working or correct parts of the Works that have been assembled incorrectly)

  • Variations change the definition of the Works themselves

(variations are issued when it is required the contents of the Contract Documents to be ‘varied’ – usually by issuing revised drawings, bills, specifications etc.)

  • CA can only issue instructions in accordance with their right

to do so under SBC/Q cls. 3.14 to 3.22.

  • instructions issued under cl. 3.14 are Variations
slide-31
SLIDE 31

D39PZ: Procurement and Contracts 31

Instructions

  • Instructions are usually issued when the CA or Clerk of

Works observes the Contractor to be acting contrary to the Contract Documents (e.g. work “not in accordance”)

  • The Contractor will not be paid to comply with an instruction
  • The instruction was required because the Contractor was not

doing what it should have been doing.

  • The Contractor would be paid for complying with an

instruction if the instruction was issued in error

slide-32
SLIDE 32

D39PZ: Procurement and Contracts 32

Variations

  • Variations change the content of the Contract

Documents

  • e.g. by issuing a new drawing, specification, etc.
  • Variations are usually required:
  • to correct a mistake or discrepancy in the Contract

Documents

  • cl. 2.14.3 states “errors and inadequacies” dealt with by a Variation

because the fix will likely change the Contract Sum.

  • cl. 2.15 states “discrepancies” in Contract Documents dealt with by

an instruction

slide-33
SLIDE 33

D39PZ: Procurement and Contracts 33

Variations

  • Variations may also be required to:
  • the Works as defined in the Contract Documents simply

can’t be built

  • It either won’t work or can’t be built
  • if the Employer’s changes its mind about what is required
  • If uncontrolled, many of this type of Variation become

problematic

  • Because the need for a Variation was not created by the

Contractor, the Contractor will be fully paid for complying with a Variation.

slide-34
SLIDE 34

D39PZ: Procurement and Contracts 34

Types of Variation

  • There are two types of Variation
  • Variations that change the content of the Contract

Documents (cl. 5.1.1)

  • Variations that oblige the Contractor to use certain working

methods (e.g. working at night) (cl. 5.1.2)

slide-35
SLIDE 35

D39PZ: Procurement and Contracts 35

Adjusting the Contract Sum

  • The Contract Sum can be increased or decreased if:
  • a Variation has been issued (cl. 4.3.1.1)
  • an Acceleration Quotation or a Variation Quotation has been

submitted by the Contractor and accepted by the Employer (cl. 4.3.1.2)

  • a change in premiums the Contractor must pay for any “all

risk” insurance of the Works they were obliged to take out (cl. 4.3.1.3).

slide-36
SLIDE 36

D39PZ: Procurement and Contracts

Valuing variations Measurable Work 5.6.1 To the extent that a Valuation relates to the execution of

additional or substituted work which can properly be valued by measurement or to the execution of work for which an Approximate Quantity is included in the Contract Bills and subject to clause 5.8 in the case of CDP Works, such work shall be measured and shall be valued in accordance with the following rules:

.1 where the additional or substituted work is of similar character to, is executed under similar conditions as, and does not significantly change the quantity of, work set out in the Contract Bills, the rates and prices for the work so set out shall determine the valuation;

slide-37
SLIDE 37

D39PZ: Procurement and Contracts

Measurable Work 5.6.1

.2 where the additional or substituted work is of similar character to work set

  • ut in the Contract Bills but is not executed under similar conditions

thereto and/or significantly changes its quantity, the rates and prices for the work so set out shall be the basis for determining the valuation and the Valuation shall include a fair allowance for such difference in conditions and/or quantity; .3 where the additional or substituted work is not of similar character to work set out in the Contract Bills, the work shall be valued at fair rates and prices; .4 where the Approximate Quantity is a reasonably accurate forecast of the quantity of work required the rate or price for the Approximate Quantity shall determine the valuation; and

slide-38
SLIDE 38

D39PZ: Procurement and Contracts

Measurable Work 5.6.1

.5 where the Approximate Quantity is not a reasonably accurate forecast of the quantity of work required, the rate or price for that Approximate Quantity shall be the basis for determining the valuation and the Valuation shall include a fair allowance for such difference in quantity. Provided that clauses 5.6.1.4 and 5.6.1.5 shall apply only to the extent that the work has not been altered or modified other than in quantity.

5.6.2 To the extent that a Valuation relates to the omission of work set out in the Contract Bills and subject to clause 5.8 in the case of CDP Works, the rates and prices for such work therein set out shall determine the valuation of the work omitted.

slide-39
SLIDE 39

D39PZ: Procurement and Contracts

Measurable Work 5.6.3 In any valuation of work under clauses 5.6.1 and 5.6.2:

.1 measurement shall be in accordance with the same principles as those governing the preparation of the Contract Bills, as referred to in clause 2.13; .2 allowance shall be made for any percentage or lump sum adjustments in the Contract Bills; and .3 allowance, where appropriate, shall be made for any addition to or reduction of preliminary items of the type referred to in the Standard Method of Measurement, provided that no such allowance shall be made in respect of compliance with an Architect/Contract Administrator’s instruction for the expenditure of a Provisional Sum for defined work.

slide-40
SLIDE 40

D39PZ: Procurement and Contracts 40

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-41
SLIDE 41

D39PZ: Procurement and Contracts 41

The Rectification Period

  • The Final Certificate is the final outcome of the Contract.
  • It is issued after the Rectification Period has ended.
  • The Rectification Period commences after issue of the

Practical Completion Certificate (cl. 2.34).

  • The Rectification Period is a period of time in which the

Contractor must make good all defects (cl. 2.38).

  • Default duration is 6 months (Contract Particulars).
slide-42
SLIDE 42

D39PZ: Procurement and Contracts 42

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-43
SLIDE 43

D39PZ: Procurement and Contracts 43

Events prior to Final Certificate

  • Interim Certificates will have been issued at regular intervals

to direct the Employer's payments (cl. 4.9.1)

  • The Practical Completion Certificate has been issued (cl.2.30)
  • Further Interim Certificates have been issued every two

months during the Rectification Period to permit further adjustment of the Contract Sum and any payments from Employer to Contractor (cl. 4.9.1)

  • The Certificate of Making Good has been issued (cl. 2.39)
slide-44
SLIDE 44

D39PZ: Procurement and Contracts 44

The Final Certificate (cls. 1.10 & 4.15)

  • Signifies the CA’s satisfaction with the Works.
  • Issued within two months (cl. 4.15.1) after either:
  • the end of the Rectification Period (cl. 4.15.1.1)
  • the issue of the Certificate of Making Good (cl. 4.15.1.2); or
  • settlement of the “final account” in accordance with cl. 4.5.2

(cl. 4.15.1.3)

  • States the finally adjusted Contract Sum (4.15.2.1)
  • States the sum previously certified (and paid) plus the amount
  • f any advance payment paid pursuant to cl. 4.8 and where

relevant any sums referred to in cl.4.9.2.4 (4.15.2.2)

  • States the final balance due
slide-45
SLIDE 45

D39PZ: Procurement and Contracts 45

Legal standing of the Final Certificate

  • cl. 1.9 defines the effect of the Final Certificate.

It provides conclusive evidence that:

  • the Works have been completed in accordance with the

Contract Documents and all Instructions (cl. 1.9.1.1);

  • all required adjustments of the Contract Sum have been

taken into account (cl. 1.9.1.2);

  • all extensions of time due under cl. 2.28 have been granted

(cl. 1.9.1.3);

  • all loss and expense due to the Contractor has been paid (cl.

1.9.1.4).

slide-46
SLIDE 46

D39PZ: Procurement and Contracts 46

The Final Certificate

slide-47
SLIDE 47

D39PZ: Procurement and Contracts 47

Putting it all together...

slide-48
SLIDE 48

D39PZ: Procurement and Contracts 48

  • 1. Payment principles
  • 2. Payment under the Construction Act
  • 3. Gross Valuations
  • 4. Interim Certificates
  • 5. Quantifying instructions and Variations
  • 6. The Rectification Period
  • 7. The Final Certificate
  • 8. Summary
slide-49
SLIDE 49

D39PZ: Procurement and Contracts 49

slide-50
SLIDE 50

D39PZ: Procurement and Contracts 50

slide-51
SLIDE 51

D39PZ: Procurement and Contracts 51

slide-52
SLIDE 52

D39PZ: Procurement and Contracts 52

slide-53
SLIDE 53

D39PZ: Procurement and Contracts 53

slide-54
SLIDE 54

D39PZ: Procurement and Contracts 54

slide-55
SLIDE 55

D39PZ: Procurement and Contracts 55

slide-56
SLIDE 56

D39PZ: Procurement and Contracts 56

slide-57
SLIDE 57

D39PZ: Procurement and Contracts 57

slide-58
SLIDE 58

D39PZ: Procurement and Contracts 58

slide-59
SLIDE 59

D39PZ: Procurement and Contracts 59

Remember to read the full Unit notes and Appendices, and complete your independent study