pavement at smo
play

PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September - PowerPoint PPT Presentation

REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September 25, 2017 MAY 24 TH , 2017 COUNCIL MEETING Direct staff to return to Council as soon as possible with options for projects to remove the now unneeded


  1. REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September 25, 2017

  2. MAY 24 TH , 2017 COUNCIL MEETING “Direct staff to return to Council as soon as possible with options for projects to remove the now unneeded pavement at either end of the runway”

  3. 3,500’ Runway Pavement Removal AIRPORT PAVEMENT Taxiway Runway Safety Area (RSA) Runway Protection Zone (RPZ) 436.5 300 300 436.5

  4. PAVEMENT REPLACEMENT OPTIONS OPTION 1: HYDROSEEDING $3.4M OPTION 2: ARTIFICIAL TURF $5.7M OPTION 3: PULVERIZE & STABILIZE $2.7M

  5. OPTION 1: HYDROSEEDING Outside RSA  Remove unused pavement and apply hydroseed (556,000 SF) Within RSA  Pulverize existing pavement and stabilize (90,000 SF) COST  Estimated $3.44M Surface treatment used at San Bernardino International Airport

  6. OPTION 1: HYDROSEEDING

  7. 3,500’ Runway OPTION 1: HYDROSEEDING Taxiway Runway Safety Area (RSA) Pavement Removal

  8. OPTION 2: ARTIFICIAL TURF Outside RSA  Remove unused pavement and install artificial turf (556,000 SF) Within RSA  Pulverize existing pavement and stabilize (90,000 SF) COST  Estimated $5.69M Surface treatment used at San Diego International Airport

  9. OPTION 2: ARTIFICIAL TURF

  10. 3,500’ Runway OPTION 2: ARTIFICIAL TURF Taxiway Runway Safety Area (RSA) Pavement Removal

  11. OPTION 3: PULVERIZE & STABILIZE IN PLACE Outside and Within RSA  Pulverize unused pavement and stabilize (646,000 SF) COST  Estimated $2.73M Surface treatment used at San Jose International Airport

  12. OPTION 3: PULVERIZE & STABILIZE IN PLACE

  13. 3,500’ Runway OPTION 3: PULVERIZE Taxiway Runway Safety Area (RSA) Pavement Removal

  14. ANTICIPATED SCHEDULE  All three options are expected to have similar implementation schedules Design Design Construction Construction Procurement Procurement (2-4 months) (3-4 months) (2-4 months) (4-6 months)

  15. NEXT STEPS  Council would provide staff with direction  Staff would prepare a Request for Proposal for design services  Staff would return to Council end 2017/early 2018 for (1) award of design contract and (2) approval of recommended budget actions.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.