REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September 25, 2017 MAY 24 TH , 2017 COUNCIL MEETING Direct staff to return to Council as soon as possible with options for projects to remove the now unneeded


slide-1
SLIDE 1

REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS

Airport Commission Meeting September 25, 2017

slide-2
SLIDE 2

MAY 24TH, 2017 COUNCIL MEETING

“Direct staff to return to Council as soon as possible with options for projects to remove the now unneeded pavement at either end of the runway”

slide-3
SLIDE 3

AIRPORT PAVEMENT

3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal

436.5 300

Runway Protection Zone (RPZ)

436.5 300

slide-4
SLIDE 4

PAVEMENT REPLACEMENT OPTIONS OPTION 1: HYDROSEEDING $3.4M OPTION 2: ARTIFICIAL TURF $5.7M OPTION 3: PULVERIZE & STABILIZE $2.7M

slide-5
SLIDE 5

OPTION 1: HYDROSEEDING

Outside RSA

 Remove unused pavement and apply hydroseed (556,000 SF)

Within RSA

 Pulverize existing pavement and stabilize (90,000 SF)

COST

 Estimated $3.44M

Surface treatment used at San Bernardino International Airport

slide-6
SLIDE 6

OPTION 1: HYDROSEEDING

slide-7
SLIDE 7

3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal

OPTION 1: HYDROSEEDING

slide-8
SLIDE 8

Outside RSA

 Remove unused pavement and install artificial turf (556,000 SF)

Within RSA

 Pulverize existing pavement and stabilize (90,000 SF)

COST

 Estimated $5.69M

Surface treatment used at San Diego International Airport

OPTION 2: ARTIFICIAL TURF

slide-9
SLIDE 9

OPTION 2: ARTIFICIAL TURF

slide-10
SLIDE 10

3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal

OPTION 2: ARTIFICIAL TURF

slide-11
SLIDE 11

OPTION 3: PULVERIZE & STABILIZE IN PLACE

Outside and Within RSA

 Pulverize unused pavement and stabilize (646,000 SF)

COST

 Estimated $2.73M

Surface treatment used at San Jose International Airport

slide-12
SLIDE 12

OPTION 3: PULVERIZE & STABILIZE IN PLACE

slide-13
SLIDE 13

3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal

OPTION 3: PULVERIZE

slide-14
SLIDE 14

 All three options are expected to have similar

implementation schedules

Design Procurement (2-4 months) Design (3-4 months) Construction Procurement (2-4 months) Construction (4-6 months)

ANTICIPATED SCHEDULE

slide-15
SLIDE 15

NEXT STEPS

Council would provide staff with direction Staff would prepare a Request for Proposal for

design services

Staff would return to Council end 2017/early 2018 for

(1) award of design contract and (2) approval of recommended budget actions.