REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS
Airport Commission Meeting September 25, 2017
PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September - - PowerPoint PPT Presentation
REPLACEMENT OF EXCESS PAVEMENT AT SMO RUNWAY ENDS Airport Commission Meeting September 25, 2017 MAY 24 TH , 2017 COUNCIL MEETING Direct staff to return to Council as soon as possible with options for projects to remove the now unneeded
Airport Commission Meeting September 25, 2017
3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal
436.5 300
Runway Protection Zone (RPZ)
436.5 300
Remove unused pavement and apply hydroseed (556,000 SF)
Pulverize existing pavement and stabilize (90,000 SF)
Estimated $3.44M
3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal
Remove unused pavement and install artificial turf (556,000 SF)
Pulverize existing pavement and stabilize (90,000 SF)
Estimated $5.69M
3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal
Pulverize unused pavement and stabilize (646,000 SF)
Estimated $2.73M
3,500’ Runway Taxiway Runway Safety Area (RSA) Pavement Removal
All three options are expected to have similar
Design Procurement (2-4 months) Design (3-4 months) Construction Procurement (2-4 months) Construction (4-6 months)
Council would provide staff with direction Staff would prepare a Request for Proposal for
Staff would return to Council end 2017/early 2018 for