PASEO CARIBE PASEO CARIBE CONDOMINIUM TOWER & PARKING Coupled - - PowerPoint PPT Presentation

paseo caribe paseo caribe
SMART_READER_LITE
LIVE PREVIEW

PASEO CARIBE PASEO CARIBE CONDOMINIUM TOWER & PARKING Coupled - - PowerPoint PPT Presentation

ARCHITECTURAL ENGINEERING THE PENNSYLVANIA STATE UNIVERISITY THESIS PROJECT PASEO CARIBE PASEO CARIBE CONDOMINIUM TOWER & PARKING Coupled Shear Wall Systems in High Seismic Zones PASEO CARIBE PASEO CARIBE CONDOMINIUM TOWER & PARKING


slide-1
SLIDE 1

PASEO CARIBE PASEO CARIBE

CONDOMINIUM TOWER & PARKING CONDOMINIUM TOWER & PARKING CONDOMINIUM TOWER & PARKING

PASEO CARIBE PASEO CARIBE

CONDOMINIUM TOWER & PARKING

Coupled Shear Wall Systems in High Seismic Zones

ARCHITECTURAL ENGINEERING THE PENNSYLVANIA STATE UNIVERISITY THESIS PROJECT

slide-2
SLIDE 2

PASEO CARIBE PASEO CARIBE

CONDOMINIUM TOWER & PARKING CONDOMINIUM TOWER & PARKING CONDOMINIUM TOWER & PARKING

ARCHITECTURAL ENGINEERING THE PENNSYLVANIA STATE UNIVERISITY THESIS PROJECT

slide-3
SLIDE 3

INTRODUCTION BACKGROUND BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

BACKGROUND BACKGROUND

LOCATION

San Juan, Puerto Rico Bordered by the Caribbean &

South American Plates

slide-4
SLIDE 4

INTRODUCTION BACKGROUND BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

BACKGROUND BACKGROUND

LOCATION

UBC 1997 Seismic Zone 3

  • N. American
  • N. American

Plate Plate

  • S. American Plate
  • S. American Plate

Caribbean Plate Caribbean Plate

slide-5
SLIDE 5

INTRODUCTION BACKGROUND BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

BACKGROUND BACKGROUND

Project Overview

IV Phase Development Project

slide-6
SLIDE 6

INTRODUCTION BACKGROUND BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

BACKGROUND BACKGROUND

Project Overview

Parking Garage: Phase II

10 stories, 1700 parking spaces

slide-7
SLIDE 7

INTRODUCTION BACKGROUND BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

BACKGROUND BACKGROUND

Project Overview

Parking Garage: Phase II

10 stories, 1700 parking spaces

Condominium Tower: Phase III

  • Add. 14 stories

4 – 3,500 ft2

aparts / floor

slide-8
SLIDE 8

INTRODUCTION BACKGROUND EXISTING EXISTING STRUCTURE STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

EXISTING STRUCTURE EXISTING STRUCTURE

slide-9
SLIDE 9

INTRODUCTION BACKGROUND EXISTING EXISTING STRUCTURE STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

EXISTING STRUCTURE EXISTING STRUCTURE

Gravity System

Cast-in-Place Bearing Wall

9” Post-Tensioned Flat Slab 36 – 12” Walls: 620 LF / Floor Typical Open Span: 17’ E-W

Lateral System

Bearing Walls act as Shear Walls Very Stiff 10’ x 160’ Core

4 Elevator Shafts 3 Sets of Stairs

slide-10
SLIDE 10
  • Lateral Discontinuity
  • Transition of Occupancy at 8th Floor
  • Vertical Irregularity: UBC Table 16L
  • Type 1: Soft Story – Transfer Girders
  • Type 2: Weight Mass – Doubled Slab Area
  • Type 3: Vertical Geometry > 1.3L
  • Type 4: In plane Discontinuity

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM PROBLEM STATEMENT STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

PROBLEM STATEMENT PROBLEM STATEMENT

slide-11
SLIDE 11
  • Lateral Discontinuity

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM PROBLEM STATEMENT STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

PROBLEM STATEMENT PROBLEM STATEMENT

slide-12
SLIDE 12

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM PROBLEM STATEMENT STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

PROBLEM STATEMENT PROBLEM STATEMENT

Multiple Lateral Discontinuities Large Self Weight = 92,000k Low R Bearing Wall Value = 4.5

VERY LARGE SEISMIC FORCES V = 8400 KIPS

slide-13
SLIDE 13

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM PROBLEM STATEMENT STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

PROBLEM STATEMENT PROBLEM STATEMENT

Non-Structural Issues

In plan, no open space > 22’ E-W Material and Labor Intensive

Design

Concrete:

11200 cy

Formwork:

520,000 ft2

Rebar:

560 tons

slide-14
SLIDE 14

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

DESIGN GOALS DESIGN GOALS

Efficient Lateral System:

Reduce No. Lateral Elements to 4

in each direction

Limit No. Irregularities Has a Predictable and Clean

Failure Mechanism

Does not interfere with the

Architecture & Assigned Use of Space

slide-15
SLIDE 15

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

KEY ELELEMENTS KEY ELELEMENTS

Reduce Vase Shear:

Use a frame gravity system with a

higher R: 5.5

Reduce the Weight with a lighter Steel

Frame

Improved Capacity:

Higher f’c = 5ksi Thicker 24” walls Diagonally Reinforced Coupled Walls Higher T to increase participation of

coupled beam

Limit discontinuity and use symmetry to

keep a low ρ factor

slide-16
SLIDE 16

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Method

Take advantage of the Existing 27’x30’

Parking Grid

slide-17
SLIDE 17

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Method

Take advantage of the Existing 27’x30’

Parking Grid

Requirements

Existing Height w/ 9” P/T Slab: 230 ft UBC Overall Height Restriction: 240 ft Clear Story Height Required:

9 ft

Max Story Height Increase:

8 in

slide-18
SLIDE 18

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Results – Apartments

Spacing: 7.5’ Max Span: 27’ Apartments:

W10 x 26 W10 x 26 Corridor: W14 x 30 W14 x 30

∆Hstory = 5” ∆Htotal = 70”

slide-19
SLIDE 19

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Results – Parking Garage

CIRCULATION

slide-20
SLIDE 20

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Results – Transition Level, 8th

A6

15’ W40x183 Girder

slide-21
SLIDE 21

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

FRAME SYSTEM FRAME SYSTEM

Results – Connection

415 545 0.85 642 Web Buckling 415 543 0.75 724 Local Web Crippling 415 519 1 519 Local Web Yielding 415 419 0.9 465 Lateral Flange Bending

Ru, kips ΦRn, k Φ Rn, kips Check

slide-22
SLIDE 22

Proposed Layout

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

slide-23
SLIDE 23

Proposed Layout Method

Direct Shear – ETABS Axial Dead & Live – RAM

Steel System W = 62,000 kips 25% Reduction

Torsion

Eccentric Loading Accidental Torsion, Ax = 2

Load Combinations

ρ = 1.1 Ca = 0.33 0.8D + 1.2E

(Load Case 1)

1.48D + 1.2E + 0.55L

(Load Case 2)

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

slide-24
SLIDE 24

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

ETABS MODEL

slide-25
SLIDE 25

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Summary Results

slide-26
SLIDE 26

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Coupled Beams

CR Ratio = 27% Results Details

Vertical: #4@6” Horizontal: #6@9” Diagonal Ties: #4@4”

slide-27
SLIDE 27

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Coupled Beams

CR Ratio = 27% Results Details

Vertical: #4@6” Horizontal: #6@9” Diagonal Ties: #4@4”

slide-28
SLIDE 28

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Flexure ФMn

1st Level

L = 33 ft B.Z: 39 #11 Web: #10@9” ФMn = 146337 ft-k > 144233 ft-k

slide-29
SLIDE 29

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

slide-30
SLIDE 30

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

slide-31
SLIDE 31

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Flexure, ФMn

Cut-Off Requirements – 0.8*L Vertical Reinforcement

Flexural Demand vs. Height Coupled Walls 4290 ft - kips 2400 ft - kips 1210 ft - kips

80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240

400 1400 2400 3400 4400 5400 6400 Mu, ft-kips Story Height, ft Moment Demand 12th Story Mn REQ 16th Story Mn REQ 19th Story Mn REQ ∆ = 12.8ft ∆ = 12.8 ft

slide-32
SLIDE 32

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Flexure, ФMn

Cut-Off Requirements – 0.8*L Vertical Reinforcement

∆ = 12.8 ft

slide-33
SLIDE 33

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Ductility & Plastic Hinge Development

Preferred Plastic Hinge at Base: Minimize Impact on Non- Structural Systems Θ1 < θ9 θ9 θ1 ∆

slide-34
SLIDE 34

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Ductility & Plastic Hinge Development

Virtual Work

slide-35
SLIDE 35

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Minimum Shear and Magnified Shear

Demand

u u pr v u

V M M V * ) / ( * ϖ =

slide-36
SLIDE 36

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Boundary Zones

Requirements Length

Ties: #5@6”

c f A P

g u

' 10 . < . 1 <

u u u

V l M , ' 3

c cv u

f A V < 3 <

u u u

V l M

  • u

w

P P l ft Z B 2 . 1 . ) ( . =

slide-37
SLIDE 37

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Final Design

slide-38
SLIDE 38

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Final Design

slide-39
SLIDE 39

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED COUPLED WALLS WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

COUPLED WALLS COUPLED WALLS

Final Design

slide-40
SLIDE 40

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES COMMODITIES CONSTRUCTION &COST CONCLUSION

COMMODITIES COMMODITIES

Architecture

Saved 160 ft2 / Floor Flexible and Open Plan for:

Architect Owner Future Tenants

Larger Open Areas of up to 50’

slide-41
SLIDE 41

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES COMMODITIES CONSTRUCTION &COST CONCLUSION

COMMODITIES COMMODITIES

Acoustics

slide-42
SLIDE 42

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES COMMODITIES CONSTRUCTION &COST CONCLUSION

COMMODITIES COMMODITIES

Acoustics Vibrations

Living Areas: W10X15 TO W10X26

slide-43
SLIDE 43

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION CONSTRUCTION &COST &COST CONCLUSION

CONSTRUCTION CONSTRUCTION

U.S Cost

$1,000,000 Savings Formwork 450,000 sfca Rebar Placement 100 tons

Puerto Rico

$400,000 Deficit Concrete Labor Market 12% Finishes & Partitions

323%

slide-44
SLIDE 44

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION CONSTRUCTION &COST &COST CONCLUSION

CONSTRUCTION CONSTRUCTION

slide-45
SLIDE 45

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION CONCLUSION

CONCLUSION CONCLUSION

Current design reflects the labor

practices and situation of the country

Designers applied the best and most

economical design to a complicated structure

Coupled wall systems proved to be an

effective resisting system, allowed for increased floor area and architectural freedom

Reduced the amount of material and

labor required for the project

Overall: Good design when the

resources are available

slide-46
SLIDE 46

INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION &COST CONCLUSION

THANK YOU THANK YOU